File #: 1453-2012    Version: 1
Type: Ordinance Status: Passed
File created: 6/22/2012 In control: Public Utilities Committee
On agenda: 7/23/2012 Final action: 7/25/2012
Title: To authorize the Director of Public Utilities to modify and increase the engineering services agreement with Stantec Consulting Services, Inc. for Phase 4 of the Geographical Information System (GIS) Conversion Services Project; to authorize the transfer of $124,397.52 within the Electric Permanent Improvement Fund, Fund 565; to authorize an amendment to the 2012 Capital Improvements Budget; and to authorize an the appropriation and expenditure of $124,397.52 from the Electric Permanent Improvement Fund. ($124,397.52)
Attachments: 1. ORD 1453-2012 Information, 2. ORD 1453-2012 Sub I..pdf
Explanation

1. BACKGROUND: This Ordinance authorizes the Director of Public Utilities to modify and increase an engineering services agreement with Stantec Consulting Services, Inc. for the Division of Power and Water (Power). The original agreement provided for professional engineering services for Phase I of the Geographical Information System (GIS) Conversion Services Project which consisted of data source preparation and documentation, project management and production methodology, proof of concepts of one (1) complete distribution circuit, verification of existing Power GIS data within the Downtown area and two (2) ArcFM software licenses. Phase II authorized the expenditure for engineering services to complete the downtown underground power distribution system and to start the overhead distribution system. Phase II also included two (2) additional sets of software and training for the software purchased for this project. Phase III completed the distribution power system to include overhead and underground distribution power lines. Phase IV will complete the secondary power system to include overhead and underground secondary power lines and meters to the City of Columbus power customers.

1.1 Amount of additional funds for Phase IV: $124,397.52
Org. Contract (Phase 1) Ord. 1474-2009 $199,321.60
Modification #1 (Phase 2) Ord. 1784-2010 $210,948.20
Modification #2 (Phase 3) Ord. 1568-2011 $98,000.00
Modification #3 (Phase 4) current $124,397.52
Total $632,667.32

1.2. Reasons additional goods/services could not be foreseen:
This was a planned modification as indicated in the original authorizing legislation, Ordinance No. 1474-2009.

1.3. Reason other procurement processes are not used:
This was a planned contract modification identified in the original contracting legislation. The engineering services during this phase are a continuation of the services in Phase I, P...