Explanation
BACKGROUND: This project involves lining sanitary laterals using Cured-In-Place Pipe (CIPP) technology and redirection of roof laterals to prevent excess stormwater from entering the City’s sanitary sewer system. This project is a Consent Order project and is an improvement identified in the Integrated Plan and 2015 WWMP Update Report. The project is needed to mitigate water in basement events and sanitary sewer overflows to the goal of a 10 year Level of Service (LOS).
Planning Area: 11 - North Linden
PROJECT TIMELINE: Contract work is required to be substantially complete in a manner acceptable to the City within 365 days from the date that a Notice To Proceed (NTP) is given by the City, with final completion occurring within 365 days.
PROCUREMENT INFORMATION: The Division advertised for competitive bids submission for the subject services on the City's Vendor Services website and in the City Bulletin in accordance with the overall provisions of Chapter 329 of the Columbus City Codes. The Division of Sewerage and Drainage received two (2) bids on November 17, 2021 from the following:
NAME TAX ID DAX # City/State Status Expiration Bid Amount
BLD Services, LLC 47-2946608 004610 Columbus, OH MAJ 3/12/2022 $3,287,329.40
Musson Brothers, Inc. 34-0802152 006456 Akron, OH MAJ 6/8/2022 $5,965,753.23
BLD Services, LLC is the lowest, responsible, responsive bidder, according to the provisions of Chapter 329 of the Columbus City Codes.
EMERGENCY DESIGNATION is not requested at this time.
ECONOMIC / ENVIRONMENTAL IMPACT: This project is a Consent Order project and is an improvement identified in the Integrated Plan and 2015 WWMP Update Report. The project is needed to mitigate water in basement events and sanitary sewer overflows to the goal of a 10 year Level of Service (LOS). Public meetings were conducted to solicit public input regarding the project, and descriptions of the work associated with this project were included on t...