Title: To authorize the Director of Public Service to enter into contract with Complete General Construction Company for the Bridge Rehabilitation - Ohio Center Way over Conrail project; to provide for the payment of construction administration and inspection services in connection with the project; to amend the 2012 C.I.B; to authorize the transfer of funds within the Streets and Highways G.O. Bonds Fund; to authorize the expenditure of up to $1,264,683.75 from the Streets and Highways G.O. Bonds Fund; and to declare an emergency. ($1,264,683.75)
Explanation
1. BACKGROUND
This legislation authorizes the Director of Public Service to enter into a contract for the Bridge Rehabilitation - Ohio Center Way over Conrail Contract for the Division of Design and Construction.

This project consists of rehabilitation of the Convention Center bridges, including pier patching, expansion joint replacements, expansion joint seal replacements, replacement of steel diaphragms, and two spans of pre-stressed concrete beams, and other such work as may be necessary to complete the contract in accordance with the plans and specifications.

The estimated Notice to Proceed date is August 16, 2012. The project was let by the Office of Support Services through Vendor Services and Bid Express. Two bids were received on July 3, 2012, (both majority) and tabulated as follows:

Company Name Bid Amt City/State Majority/MBE/FBE
Complete General Construction Co. $1,149,712.50 Columbus, OH Majority
Righter Company, Inc. $1,698,550.00 Columbus, OH Majority
Award is to be made to Complete General Construction, as the lowest responsive and responsible and best bidder. The contract amount will be $1,149,712.50.
Searches in the Excluded Party List System (Federal) and the Findings for Recovery list (State) produced no findings against Complete General Construction Company.
2. CONTRACT COMPLIANCE
The contract compliance number for Complete General Construction Company is 314366382 and expires on 11/1/2013.
3. FISCAL IMPACT
Funding for this project budgeted in the 2012 C.I.B. and is contingent upon the 2012 bond sale.
4. EMERGENCY DESIGNATION
Emergency action is requested in order to provide for necessary bridge rehabilitation work at the earliest possible time to ensure the safety of the travelling public.