Explanation
BACKGROUND: This ordinance authorizes the Public Utilities Director to modify an existing contract with ABB, Inc. for the Division of Electricity for the Italian Village Substation.
Amount of additional funds to be expended: $82,663.00
Current Contract Amount: $6,906,910
Reasons additional goods/services could not be foreseen:
The Columbus Department of Development Building Services Division's review of the permit drawings determined that there is a 6" water line through the site that was not previously identified. This water line necessitates that the Gas Insulated Switchgear (GIS) building be located with the setback required by a City Street Easement. Therefore, the building must be moved 15' north from the location specified in the original bid proposal, thus requiring additional bus/trench at a cost of $69,876.
Another change in the scope of work requires the installation of a 5-ton air conditioning unit, at a cost of $8,937, to provide a conditioned environment not to exceed 85 degrees for the proper operation of equipment to be housed in the GIS building. This service was not included in the original specifications.
It is also requested that the contract be modified to add one additional city employee to attend witness testing of 138KV GIS Switchgear and transformer testing at a cost of $3,850.00.
Reason other procurement processes are not used: ABB, Inc. was awarded the original contract for the Italian Village Substation project based upon the lowest bid received March 3, 2004. It would not be feasible to bid this work separately and would cause a delay in the project.
How cost of modification was determined: The cost of the design changes were determined through negotiations with the contractor and the cost of the witness testing is at the cost established in the existing contract.
Contract Compliance Number: 363100018
Emergency action is requested in order to avoid delays in the construction schedule that could impact the cost of the project.
FISCAL IMPACT: There is sufficient funding in the Voted 1995 and 1999 Street Lighting and Electricity Distribution Improvements Fund 553, Italian Village Substation Project 670607, for this expenditure.
Title
To authorize the Director of Public Utilities to modify an existing contract for the Division of Electricity with ABB, Inc. for the Italian Village Substation; to authorize the expenditure of $82,663.00 from the Voted 1995 and 1999 Street Lighting and Electricity Distribution Improvements Fund; and to declare an emergency. ($82,663.00)
Body
WHEREAS, bids were solicited and opened on March 3, 2004 to build an electrical substation in the Italian Village area; and
WHEREAS, the Public Utilities Director, under the authority of Ordinance 0934-2004, passed July 19, 2004, has entered into contract EL004478, with ABB, Inc. based upon the lowest responsive and responsible bid received; and
WHEREAS, it is necessary to change the scope of the work to include items that were not included in the original specifications; and
WHEREAS, emergency action is necessary to avoid unnecessary delay in the project; and
WHEREAS, an emergency exists in the usual daily operation of the Department of Utilities, Division of Electricity, in that it is immediately necessary to modify the existing contract with ABB, Inc. for the Italian Village Substation for the immediate preservation of the public health, peace, property, safety and welfare; now, therefore,
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
SECTION 1. That the Public Utilities Director is hereby authorized and directed to modify an existing contract with ABB, Inc. for the Italian Village Substation to increase bus/trench quantities necessitated by a change to the location of the Gas Insulated Switchgear (GIS) building, to include an air conditioning unit in the GIS building, to add one additional city employee to attend witness testing of equipment; and to increase the contract by an amount of $82,663.00.
SECTION 2. That this contract modification is in compliance with Section 329.13 of Columbus City Codes, 1959.
SECTION 3. That to pay the cost of the aforesaid contract modification, the expenditure of $82,663.00, or so much thereof as may be needed, is hereby authorized from the Voted 1995 and 1999 Street Lighting and Electricity Distribution Improvements Fund 553, Division No. 60-07, Italian Village Substation Project Number 670607, OCA Code 670607, Object Level Three 6621.
SECTION 4. That for the reasons stated in the preamble hereto, which is hereby made a part hereof, this ordinance is hereby declared to be an emergency measure and shall take effect and be in force from and after its passage and approval by the Mayor, or ten days after passage if the Mayor neither approves nor vetoes the same.