Title: To authorize the Director of Public Utilities to execute a construction contract with George J. Igel & Company, Inc.; to encumber funds to provide for payment of inspection, material testing and related services to the Design and Construction Division; to authorize the transfer of $72,170.00 within the Storm Recovery Zone Super Build America Bonds Fund; to authorize an amendment to the 2012 Capital Improvements Budget; and to authorize the expenditure of $1,072,170.00 for the Southwesterly Compost Facility Stormwater Diversion Swale Improvements Project, for the Divisions of Sewerage and Drainage from the Storm Recovery Zone Super Build America Bonds Fund. ($1,072,170.00)
Attachments: 1. ORD1461-2012Bid Tab, 2. ORD1461-2012QFF, 3. ORD1461-2012Map, 4. ORD1461-2012 Director's Legislation Information Sheet, 5. ORD1461-2012Sub-Contractor Work Identification Form
Explanation
1.  BACKGROUND:  This legislation authorizes the Director of Public Utilities to enter into a construction contract with George J. Igel & Company, Inc. in the amount of $931,169.76; to encumber funds with the Design and Construction Division for inspection, testing, and prevailing wage coordination services in the amount of $141,000.24; all in connection with the Southwesterly Compost Facility Stormwater Diversion Swale Improvements Project.
The work for which proposals are invited consists of all labor and materials for the construction of approximately 29,146 cubic yards of excavation; 6,584 cubic yards of embankment; 174 cubic yards of rock channel protection; 4,373 feet of 12-inch ditch underdrain, as per plan; 75 feet of 15-inch storm sewer; 112 feet of 30-inch storm sewer; 195 feet of 36-inch storm sewer; 340 feet of 42-inch storm sewer; manholes, catch basins, headwalls and endwalls.
 
This project includes $1,072,170.00 for Stormwater Improvements as directed by the Project Engineer, which will be paid from the Storm Recovery Zone Super Build America Bonds Fund.
2.  CONSTRUCTION CONTRACT AWARD:  The Director of Public Utilities publicly opened four (4) bids on May 23, 2012.  These bids were received from: George J. Igel-$931,169.76, John Eramo - $1,022,128.08, Darby Creek Excavating - $1,297,074.18, and Complete General - $1,410,224.40.
The lowest and best bid was from George J. Igel & Company, Inc. for $931,169.76.  Additional information regarding each bidder, description of work, contract timeframe, detailed amounts and sub-contractors can be found on the attached Legislation Information Form.
Contract Compliance Information:  31-4214570, expires 02/22/2013, Majority
Searches in the Excluded Party List System (Federal) and the Findings for Recovery list (State) produced no findings against George J. Igel & Company, Inc.
3.  FISCAL IMPACT:  A transfer of $72,170.00 is needed to provide sufficient cash for this project in the Storm Recovery Zone Super Build America Bonds Fund.  An amendment to the 2012 Capital Improvements Budget will also be necessary.
Title
To authorize the Director of Public Utilities to execute a construction contract with George J. Igel & Company, Inc.; to encumber funds to provide for payment of inspection, material testing and related services to the Design and Construction Division; to authorize the transfer of $72,170.00 within the Storm Recovery Zone Super Build America Bonds Fund; to authorize an amendment to the 2012 Capital Improvements Budget; and to authorize the expenditure of $1,072,170.00 for the Southwesterly Compost Facility Stormwater Diversion Swale Improvements Project, for the Divisions of Sewerage and Drainage from the Storm Recovery Zone Super Build America Bonds Fund.  ($1,072,170.00)
Body
WHEREAS, four (4) bid proposals were received and publicly opened in the offices of the Director of Public Utilities on May 23, 2012 for the construction of the Southwesterly Compost Facility Stormwater Diversion Swale Improvements Project; and
WHEREAS, it is necessary to authorize the Director of the Department of Public Utilities to award and execute a construction contract and to encumber and expend funds to provide for payment of inspection, testing and prevailing wage coordination services costs associated with the Southwesterly Compost Facility Stormwater Diversion Swale Improvements Project; and
WHEREAS, it is necessary to authorize a transfer of $72,170.00 within the Storm Recovery Zone Super Build America Bonds Fund for the purpose of providing sufficient funding for the aforementioned project expenditure; and
WHEREAS, it is necessary to authorize an amendment to the 2012 Capital Improvements Budget for the purpose of providing sufficient authority for the aforementioned project expenditure; and
WHEREAS, this project is needed to prevent offsite stormwater from entering the Compost Facility reducing the frequency of overflows from the Compost Facility Leachate Basin.
 
WHEREAS, in the usual daily operation of the Department of Public Utilities, Divisions of Sewerage and Drainage it is necessary to enter into a construction contract with George J. Igel & Company, Inc. for the Southwesterly Compost Facility Stormwater Diversion Swale Improvements Project for the preservation of public health, peace, property and safety; now therefore,
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
SECTION 1.  That the Director of Public Utilities be, and hereby is, authorized to award and execute a contract for construction of the Southwesterly Compost Facility Stormwater Diversion Swale Improvements Project with the lowest and best bidder, George J. Igel & Company, Inc., 2040 Alum Creek Drive, Columbus, OH 43207; in the amount of $931,169.76 in accordance with the terms and conditions of the contract on file in the Office of the Division of Sewerage and Drainage; and to obtain the necessary inspection, testing and prevailing wage coordination services from the Design and Construction Division; and to pay up to a maximum amount of $141,000.24
SECTION 2.  That the City Auditor is hereby authorized to transfer $72,170.00 within the Division of Sewerage and Drainage, Dept/Div. No. 60-15, Storm Recovery Zone Super Build America Bonds Fund, Fund No. 677, Object Level One 06, Object Level Three 6621, as follows:
Project No. | Project Name | OCA Code | change
610411-100000 | Stormwater I/I Livingston/James | 677411 | -$72,170.00
610051-100000 | Compost Facility Diversion Swale | 677051 | +$72,170.00
 
SECTION 3.  That the 2012 Capital Improvements Budget is hereby amended as follows:
Proj. No. | Proj. Name | Current Authority | Revised Authority | Change
610411-100000 | Stormwater I/I Livingston/James | $125,652 | $53,482 | -$72,170
610051-100000 | Compost Facility Diversion Swale | $1,000,000 | $1,072,170 | +$72,170
SECTION 4.  That for the purpose of paying the cost of the construction contract, the following expenditure, or as much thereof as may be needed is hereby authorized as follows:  Division 60-15, Storm Recovery Zone Super Build America Bonds Fund, Fund No. 677, Project 610051-100000, Object Level Three 6621, OCA Code 677051, Amount $931,169.76.
SECTION 5.  That for the purpose of paying the cost of inspection, testing and prevailing wage coordination services, the following expenditure, or as much thereof as may be needed is hereby authorized as follows:  Division 60-15, Storm Recovery Zone Super Build America Bonds Fund, Fund No. 677, Project 610051-100000, Object Level Three 6687, OCA Code 677051, Amount $141,000.24.
SECTION 6.  That the said construction company shall conduct the work to the satisfaction of the Director of Public Utilities and the Administrators of the Division of Sewerage and Drainage
 
SECTION 7.  That the City Auditor is hereby authorized and directed to transfer any unencumbered balance in the project account to the unallocated balance within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies no longer required for said project; except that no transfer shall be made from a project account by monies from more than one source.
SECTION 8.  That the City Auditor is authorized to establish proper project accounting numbers as appropriate.