Explanation
1. BACKGROUND
This ordinance authorizes the Director of Public Utilities to enter into a professional services contract modification to add funding with Black & Veatch Corporation for the Wastewater Treatment Facilities (WWTF)-General Program #5 project, CIP #650360-100003, in an amount up to $1,200,000.00.
Overall Engineering Consultant Services (OEC) are necessary to provide technical and engineering assistance to the City and its design professionals in planning and coordination of the work. The OEC services are separated into several tasks, as follows:
Task 1 - Planning Services
Task 2 - Design Services
Task 3 - Construction Related Services
Task 4 - Commissioning and Start-up Services
Task 5 - General and Additional Services
Task 6 - Project Management
The City will request a task order from the consultant as necessary work is identified. The task order submitted typically includes a detailed scope of work, direct and indirect costs, task schedule, estimated hours, personnel categories required with labor rates, and reimbursable expenses. After negotiation and upon acceptance by the city, the consultant shall commence work. The Engineer shall provide such professional engineering services as may be necessary to accomplish the work required to be performed and shall at the firm’s cost, furnish all necessary competent personnel, equipment, and materials to perform the work.
The Community Planning Area is “99 - Citywide”
1.1 Amount of additional funds to be expended: $1,200,000.00
Original Contract Amount: $800,000.00 (ORD 0601-2023 PO382045)
Mod #1 Amount: $1,200,000.00 (ORD 1376-2024 PO458457)
Mod #2 Amount: $1,200,000.00 (Current)
Total (Orig.+ Modifications): $3,200,000.00
1.2. Reason other procurement processes are not used:
This contract was originally planned as a 3-year effort with annual funding modifications because it includes tasks which stretch across several funding years, and because the nature of the work requires the firm to develop a deep and detailed understanding of our plants and how we operate them. A new procurement effort is not required to add funding.
1.3. How cost of modification was determined:
The cost of this modification was determined by negotiations between Black & Veatch Corporation and the project team based upon the contract rates and titles established in the original contract and an estimate of the number of hours needed for each title for the tasks to be assigned to the contract modification.
2. ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT
The project provides many metrics on various environmental factors that are noted in the work to be performed. The information provided assists and guides the City in decision making on environmental issues. These decisions have a direct impact on the capital improvement program budget amounts and scheduling to address the environmental needs. No community outreach is considered for this project.
3. CONTRACT COMPLIANCE INFORMATION
Black & Veatch Corporation’s contract compliance number is CC008038 and expires on 8/11/27.
Searches in the Excluded Party List System (Federal) and the Findings for Recovery list (State) produced no findings against Black & Veatch Corporation.
As part of their proposal, Black & Veatch Corporation has proposed the following nine subcontractors to perform contract work:
Company Name City/State ODI Certification Status
Dynotec, Inc Columbus, Ohio MBE
Brown and Caldwell Columbus, Ohio MAJ
Burgess & Niple Columbus, Ohio MAJ
DLZ Columbus, Ohio MBE
MODIFI Design dba Hydrous Columbus, Ohio WBE
Geosyntec Columbus, Ohio MAJ
Advanced Engineering Consultants Columbus, Ohio MBE
Coldwater Columbus, Ohio WBE
Stantec Columbus, Ohio MAJ
The certification of Black & Veatch Corporation and the above companies was in good standing at the time the bid was awarded.
5. FISCAL IMPACT
Funding in the amount of $1,200,000.00 is available and appropriated within the Sanitary Bond Fund, Fund 6109.
Title
To authorize the Director of the Department of Public Utilities to enter into a professional services contract modification with Black & Veatch Corporation for the Waste Water Treatment Facilities-General Program #5 project; and to authorize an expenditure of up to $1,200,000.00 from the Sanitary Bond Fund for the contract. ($1,200,000.00)
Body
WHEREAS, the Department of Public Utilities is engaged in the WWTF-General Program #5 project; and
WHEREAS, it is necessary to expend funds from the Sanitary Bond Fund, Fund 6109, to pay for work performed under this contract modification; and
WHEREAS, it has become necessary in the usual daily operation of the Department of Public Utilities, Division of Sewerage and Drainage, to authorize the Director of Public Utilities to enter into a professional engineering service agreement with Black & Veatch Corporation for the WWTF-General Program #5 project for the preservation of the public health, peace, property, safety and welfare; NOW, THEREFORE
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
SECTION 1. That the Director of Public Utilities is hereby authorized to enter into a contract modification to add funding for the current year for the WWTF-General Program #5 project with Black & Veatch Corporation, 445 Hutchinson Ave Ste. 540, Columbus, OH 43235, in an amount up to $1,200,000.00, in accordance with the terms and conditions of the contract on file in the Department of Public Utilities.
SECTION 2. That the expenditure of $1,200,000.00, or so much thereof as may be needed, is hereby authorized to pay for this contract per the accounting codes in the attachment to this ordinance.
SECTION 3. Funds are hereby deemed appropriated and expenditures and transfers authorized to carry out the purposes of this ordinance and the City Auditor shall establish such accounting codes as necessary.
SECTION 4. That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this ordinance.
SECTION 5. That the City Auditor is hereby authorized to transfer the unencumbered balance in a project account to the unallocated balance account within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies are no longer required for said project.
SECTION 6. That this Ordinance shall take effect and be in force from and after the earliest period allowed by law.