Legislation Details

File #: 2885-2026    Version: 1
Type: Ordinance Status: First Reading
File created: 10/8/2026 In control: Public Utilities & Sustainability Committee
On agenda: 11/2/2026 Final action:
Title: To authorize the Director of Columbus Water & Power to enter into a construction contract with Kenmore Construction Co., Inc. for the Jackson Pike Water Reclamation Plant Screening Improvements project; to authorize the appropriate and expenditure of $15,910,000.00 within the Sanitary Revolving Loan Fund to pay for the contract; to make this ordinance contingent upon the Ohio Water Development Authority approving a loan for this project; and to authorize the expenditure of up to $2,000.00 from the Sanitary Bond Fund to pay the Department of Public Service for prevailing wage services. ($15,912,000.00)
Indexes: MBE Participation, WBE Participation
Attachments: 1. ORD 2885-2026 2A-1 Utilization, 2. ORD 2885-2026 Kenmore SOS, 3. ORD 2885-2026 Accounting Template
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

Explanation   

1.  BACKGROUND

This ordinance authorizes the Director of Columbus Water & Power to enter into a construction contract with Kenmore Construction Co., Inc., for the Jackson Pike Water Reclamation Plant (JPWRP) Screening Improvements project, CIP 650252-100010, in an amount up to $15,910,000.00; and to encumber funds with the Department of Public Service for prevailing wage services in an amount up to $2,000.00, for a total expenditure of $15,912,000.00.

                     

The JPWRP operates two mechanical screens to remove large debris as wastewater enters the plant as part of their headworks treatment process. The current screenings press is unable to process the large amount of leaves and debris that are captured by the mechanical screens. This construction contract will replace the existing screens with new screens to reduce maintenance costs, demolition of the existing trash racks to increase safety, installation of a new crane to replace the existing non-functional crane, install a new roof, install new skylights to aid in removing the existing screens and installation of the new screens, purchase of a new truck to haul screenings dumpsters, and install a concrete pad for spare screenings dumpsters.

 

The Community Area for this ordinance will be 99- Citywide. 

 

TIMELINE: Substantial Completion of the contract work is required to be completed in a manner acceptable to the City within 690 days of the Notice to Proceed (NTP). Final Completion is 750 days from the date of NTP. Work will continue until the project is completed and accepted by the City.

 

ESTIMATED COST OF PROJECT: The bid amount and proposed award amount is $15,910,000.00, including a 10% construction contingency amount that will be utilized to fund needed and approved changes in the work. No contract modifications are anticipated at this time; however, construction exigency might later compel modification of this contract, if unforeseen difficulties are encountered.

 

Cost summary:

 

Original Contract                                                                             $15,910,000.00

Future Anticipated Needs                                                                $               0.00

Prevailing Wage Services                                                                $         2,000.00

CONTRACT TOTAL                                                                    $15,912,000.00

 

2.  ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT

The JPWRP Screening Improvements project will ensure that debris continues to be removed from the incoming wastewater for disposal. This process protects the downstream equipment from debris that would otherwise cause plugging resulting in excessive downtime for repairs. Effective removal of debris will ensure the downstream equipment is protected, and capacity is not reduced due to screenings debris.

 

3.  CONSTRUCTION CONTRACT AWARD

An Invitation for Bids for the JPWRP Screening Improvements project was advertised on the Vendor Services and Bid Express websites from August 10, 2026, through September 9, 2026. One bid was received for the project and opened on September 9, 2026. The following company submitted a bid:

 

Name                                                                                                Bid Amount       CC Number      Exp. Date          Status                    

Kenmore Construction Co., Inc.                        $15,910,000.00        CC006456         11/4/2026            MAJ

 

Kenmore Construction Co., Inc.’s bid was deemed the lowest, best, most responsive and responsible bid in the amount of $15,910,000.00.

 

The certification of Kenmore Construction Co., Inc. was in good standing at the time the bid was awarded.

 

4. CONTRACT COMPLIANCE INFORMATION

Kenmore Construction Co., Inc.’s contract compliance number is CC006456 and expires 11/4/2026.  

 

Searches in the Excluded Party List System (Federal) and the Findings for Recovery list (State) produced no findings against Kenmore Construction Co., Inc.

 

Kenmore Construction Co., Inc. listed the following companies as subcontractors for this project:

 

Company Name                                                                                      City/State                                                                ODI Certification Status

Howard Painting, Inc.                                                                         Defiance, Ohio                                                                 MAJ

Radico, Inc.                                                                                       Columbus, Ohio                                                                 MAJ

Holloway, Henderson & Martin, LLC                                                  Columbus, Ohio                                                                WBE

KLE Construction                                                                              Cleveland, Ohio                                                                 MBE

Columbus Door Sales, LLC                                                                Columbus, Ohio                                                                 MAJ

Proline Electric, Inc.                                                                           Lancaster, Ohio                                                                MAJ

Harold J. Becker Company, Inc.                                                         Columbus, Ohio                                                                 MAJ

Koehring & Sons, Inc                                                                         Beech Grove, Indiana                                                        MAJ

 

The certification of Kenmore Construction Co., Inc. and of the above companies were in good standing at the time the bid was awarded.

 

5. PRE-QUALIFICATION STATUS

Kenmore Construction Co., Inc. has met code requirements with respect to pre-qualification, pursuant to relevant sections of Columbus City Code Chapter 329. 

 

6. FISCAL IMPACT

The construction portion of this project is anticipated to be financed with a loan from the Water Pollution Control Loan Fund (WPCLF), a program jointly administered by the Ohio EPA's Division of Environmental and Financial Assistance and the Ohio Water Development Authority (OWDA). City Council authorized this loan application and acceptance of funding via Ordinance 3119-2025, passed by Council on 12/15/25. This loan is expected to be approved at the OWDA December Board meeting. This ordinance is contingent upon the loan being approved by OWDA. Columbus Water & Power will inform the Auditor's Office when this loan has been approved.  The WPCLF program is a reimbursement loan.  The City will pay invoices for the work and then submit the paid invoices to OWDA for reimbursement. 

Funds must be appropriated in the WPCLF Loan Fund, Fund 6111.

Funding in the amount of $2,000.00 is appropriated and available within the Sanitary Bond Fund, Fund 6109, to pay the Department of Public Service to provide prevailing wage services for this project.

 

Title

To authorize the Director of Columbus Water & Power to enter into a construction contract with Kenmore Construction Co., Inc. for the Jackson Pike Water Reclamation Plant Screening Improvements project; to authorize the appropriate and expenditure of $15,910,000.00 within the Sanitary Revolving Loan Fund to pay for the contract; to make this ordinance contingent upon the Ohio Water Development Authority approving a loan for this project; and to authorize the expenditure of up to $2,000.00 from the Sanitary Bond Fund to pay the Department of Public Service for prevailing wage services. ($15,912,000.00)

 

Body

WHEREAS, Columbus Water & Power is engaged in the JPWRP Screening Improvements project; and

 

WHEREAS, one bid for the JPWRP Screening Improvements project was received and opened on September 9, 2026; and

 

WHEREAS, the lowest, best, most responsive and responsible bid was from Kenmore Construction Co., Inc.; and

 

WHEREAS, Ordinance 3119-2025 authorized this project to be funded by a loan to be obtained through the Water Pollution Control Loan Fund (WPCLF) Loan Account; and

 

WHEREAS, this ordinance is contingent upon that loan being approved; and

 

WHEREAS, funds must be appropriated within the Sanitary Revolving Loan Fund, Fund 6111; and

 

WHEREAS, it is necessary to authorize an expenditure of funds from the Sanitary Revolving Loan Fund to pay for the project; and

 

WHEREAS, it is necessary to expend funds from the Sanitary Bond Fund to provide for payment to the Department of Public Service for prevailing wage services associated with said project; and

 

WHEREAS, it is necessary in the daily operation of the Columbus Water & Power to authorize the Director of Columbus Water & Power to enter into a construction contract with Kenmore Construction Co., Inc. for the JPWRP Screening Improvements project; and NOW, THEREFORE,

 

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:

 

SECTION 1.  That the appropriation of $15,910,000.00, or so much thereof as may be needed, is hereby authorized in the Sanitary Revolving Loan Fund, Fund 6111, per the accounting codes in the attachment to this ordinance.

 

SECTION 2.  This ordinance is contingent upon the Ohio Water Development Authority's Board approving the loan for this project.

 

SECTION 3.  That the Director of Columbus Water & Power is hereby authorized to enter into a construction contract for the Jackson Pike Water Reclamation Plant Screening Improvements project with Kenmore Construction Co., Inc, 700 Home Rd. Akron, OH 44310; in an amount up $15,910,000.00; in accordance with the terms and conditions of the contract on file in the Columbus Water & Power; and to obtain the necessary Prevailing wage services for this project from the Department of Public Service in an amount up to $2,000.00.

 

SECTION 4.  That a transfer of appropriations and funds of up to $2,000.00, or so much thereof as may be needed, is hereby authorized in the Sanitary Bond Fund, Fund 6109 to pay for the prevailing wage services.

 

SECTION 5.  That the expenditure of $15,912,000.00, or so much thereof as may be needed, is hereby authorized to pay for this contract per the accounting codes in the attachment to this ordinance.

 

SECTION 6.  That funds are hereby deemed appropriated and expenditures and transfers authorized to carry out the purposes of this ordinance and the City Auditor shall establish such accounting codes as necessary.

 

SECTION 7.  That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this ordinance.

 

SECTION 8.  That the City Auditor is hereby authorized to transfer the unencumbered balance in a project account to the unallocated balance account within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies are no longer required for said project.

 

SECTION 9.  That this ordinance shall take effect and be in force from and after the earliest period allowed by law.