Title: To authorize the Director of Public Utilities to re-establish funds needed for the Parklane Avenue Stormwater System Improvements Project and to authorize the expenditure of $90,802.10; within the Storm Recovery Zone (Super BAB's) Fund; for the Division of Sewerage and Drainage Division. ($90,802.10)
Explanation
Background:  Ordinance No. 0468-2007 was passed by Columbus City Council on May 07, 2007.  This Ordinance authorized the Public Utilities Director to enter into a professional engineering agreement for the Parklane Avenue Stormwater System Improvements Project.
Purchase Order Number EL007071 was established with P.B. America, Inc.  The purchase order was mistakenly cancelled although services for this project under the professional engineering agreement are not complete.
Therefore, the Department of Public Utilities, Division of Sewerage and Drainage needs to re-establish funds in the amount of $90,802.10 for expenditures covered by the original ordinance and agreement for this project.
 
Fiscal Impact:  There is sufficient cash and authority for this expenditure.
 
Title
To authorize the Director of Public Utilities to re-establish funds needed for the Parklane Avenue Stormwater System Improvements Project and to authorize the expenditure of $90,802.10; within the Storm Recovery Zone (Super BAB's) Fund; for the Division of Sewerage and Drainage Division.  ($90,802.10)
Body
WHEREAS, Ordinance No. 0468-2007 was passed by Columbus City Counsel on May 07, 2007 authorizing the City of Columbus to enter into a professional engineering agreement for the Parklane Avenue Stormwater System Improvements Project; and
WHEREAS, the balance of Purchase Order EL007071 for the aforementioned project was mistakenly cancelled; and
WHEREAS, re-establishment of funds is needed for the aforementioned project to complete the services within the professional engineering agreement; and
WHEREAS, it has become necessary in the usual daily operation of the Department of Public Utilities, Division of Sewerage and Drainage, to authorize funds to be re-establish within the Storm Recovery Zone (Super BAB's) Fund, for the Parklane Avenue Stormwater System Improvements Project; for the preservation of the public health, peace, property, safety and welfare; now, therefore,
 
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
SECTION 1.      That the expenditure of $90,802.10 is hereby authorized as follows:  Division of Sewerage and Drainage, Dept./Div. No. 60-15, Storm Recovery Zone (Super BAB's) Fund, Fund No. 677, Project 610755-100000, OCA Code 677755, Object Level One 06, Object Level Three 6682.
SECTION 2.      That the City Auditor is hereby authorized to transfer the unencumbered balance in a project account to the unallocated balance account within the same fund upon receipt of certification by the Director of the Department administering said project has been completed and the monies are no longer required for said project; except that no transfer shall be so made from a project account funded by monies from more than one source.
SECTION 3.      That the City Auditor is authorized to establish proper project accounting numbers as appropriate.
SECTION 4.      That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this Ordinance.
SECTION 5.  That this Ordinance shall take effect and be in force from and after the earliest period allowed by law.