header-left
File #: 0288-2012    Version: 1
Type: Ordinance Status: Passed
File created: 2/2/2012 In control: Public Service & Transportation Committee
On agenda: 3/5/2012 Final action: 3/6/2012
Title: To authorize the Director of Public Service to enter into agreement with the Director of the Ohio Department of Transportation and to grant consent and propose cooperation with the State of Ohio for this bridge rehabilitation project on the IR70 Eastbound ramp over IR 270 Northbound. ($0.00)
Explanation
1.  BACKGROUND
This ordinance authorizes The Director of Public Service to enter into an agreement with the Ohio Department of Transportation (ODOT) for a bridge rehabilitation project on I-70 Eastbound ramp over I-270 Northbound on the West side of Columbus.
This project proposes to waterproof and overlay the bridge deck on IR70 eastbound ramp over IR270 northbound (SLM 22.92).  Also, a polymer modified joint(PMJ) system and sub-decking  will be placed over the travel lanes on IR270.   This project is estimated to begin construction in the spring of 2013. (FRA-70-22.92 PID 88000)  
 
2.  FISCAL IMPACT
The estimated construction cost of this project is $733,000.00 which will be funded by ODOT.  There is no cost to the City for this project.
Title
To authorize the Director of Public Service to enter into agreement with the Director of the Ohio Department of Transportation and to grant consent and propose cooperation with the State of Ohio for this bridge rehabilitation project on the IR70 Eastbound ramp over IR 270 Northbound. ($0.00)
Body
The following is an ordinance enacted by the City of Columbus, Ohio, hereinafter referred to as the Legislative Authority or Local Public Agency or "LPA", in the matter of the stated described project.
WHEREAS, the LPA has identified the need for the described project:
This project proposes to waterproof and asphalt overlay the bridge deck on IR70 Eastbound over IR270 Northbound(SLM 22.92).  Also, a PMJ joint system and sub-decking will be placed over the travel lanes; now, therefore
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
SECTION 1.  Consent Statement
Being in the public interest, the LPA gives consent to the Director of Transportation to complete the above described project.
SECTION 2.  Cooperation Statement
The LPA shall cooperate with the Director of Transportation in the above described project as follows:
The City hereby agrees to cooperate with the Director of Transportation of the State of Ohio in the planning, design and construction of the identified highway improvement project and grants consent to the Ohio Department of Transportation for its development and construction of the project in accordance with plans, specifications and estimates as approved by the Director.
The City agrees to assume and bear one hundred percent (100%) of the cost of Preliminary Engineering.
The City agrees to assume and bear one hundred percent (100%) of the cost of Right-of-Way and construction less the amount of federal funds set aside by the Director of Transportation and the Federal Highway Administration.
The City agrees to assume and bear one hundred percent (100%) of the total cost of those features requested by the City which are not necessary for the improvement as determined by the State and Federal Highway Administration.
SECTION 3 - Utilities and Right-of-Way Statement
The LPA agrees to acquire and/or make available to ODOT, in accordance with current State and Federal regulations, all necessary right-of-way required for the described project.  The LPA also understands that right-of-way costs include eligible utility costs.  The LPA agrees to be responsible for all utility accommodation, relocation, and reimbursement and agrees that all such accommodations, relocations, and reimbursements shall comply with the current provisions of 23 CFR 645 and the ODOT Utilities Manual.
SECTION 4 - Maintenance
Upon completion of the described project, and unless otherwise agreed, the LPA shall:  (1) provide adequate maintenance for the project in accordance with all applicable state and federal law, including, but not limited to, Title 23, U.S.C., Section 116; (2) provide ample financial resources, as necessary, for the maintenance of the described project; (3) maintain the right-of-way, keeping it free of obstructions, and (4) hold said right-of-way inviolate for public highway purposes.
SECTION 5 - Consultants and Authority to Sign
The Director of Public Service of said City is hereby empowered on behalf of the City of Columbus  to enter into contracts with the Director of Transportation necessary to complete the above described project.
SECTION 6.  This ordinance shall take effect and be in force from and after the earliest period allowed by law.