Title: To authorize the Director of Public Utilities to enter into contract with General Maintenance and Engineering Company for the Parts Storage Building Roof Replacement for the Division of Sewerage and Drainage, to authorize the expenditure of $89,293.00 from the Sewerage System Operating Fund. ($89,293.00)
Date Ver.Action ByActionResultAction DetailsMeeting Details
12/17/20031 ACTING CITY CLERK Attest  Action details Meeting details
12/16/20031 MAYOR Signed  Action details Meeting details
12/15/20031 Columbus City Council Read for the First Time  Action details Meeting details
12/15/20031 Columbus City Council ApprovedPass Action details Meeting details
12/15/20031 Columbus City Council Waive the 2nd ReadingPass Action details Meeting details
12/15/20031 COUNCIL PRESIDENT Signed  Action details Meeting details
12/2/20031 CITY ATTORNEY Reviewed and ApprovedPass Action details Meeting details
12/2/20031 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
11/25/20031 Utilities Drafter Sent for Approval  Action details Meeting details
11/25/20031 Auditor Reviewer Reviewed and Approved  Action details Meeting details
11/25/20031 CITY AUDITOR Reviewed and Approved  Action details Meeting details
11/25/20031 Utilities Drafter Sent for Approval  Action details Meeting details
11/24/20031 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
11/24/20031 Utilities Drafter Sent for Approval  Action details Meeting details
11/24/20031 EBOCO Reviewer Reviewed and Approved  Action details Meeting details
11/24/20031 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
11/18/20031 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
11/17/20031 Utilities Reviewer Reviewed and Approved  Action details Meeting details
11/13/20031 Utilities Drafter Sent for Approval  Action details Meeting details

Explanation

The purpose of this legislation is to authorize the Director of Public Utilities to enter into contract with General Maintenance and Engineering Company for the Jackson Pike Wastewater Treatment Plant Parts Storage Building Roof Replacement.

 

The Jackson Pike Wastewater Treatment Plants has a need for the roof to be replaced for its Parts Storage Building located on the grounds of the plant. Bids were solicited and opened on October 29, 2003. Six (6) bids were received. Three (3) bids were deemed non-responsive for failure to submit the bid in its entirety as specified in the proposal specifications. The following is the bid tabulation:

 

General Maintenance and Engineering Co $69,293.00

K&W Roofing Inc. $70,700.00

Hartley Company $75,887.00 (Non-Responsive)

U.S. Roofing Inc. $85,000.00

Pete Miller Inc $85,923.00 (Non-Responsive)

Kromer-States Roofing $87,000.00 (Non-Responsive)

 

The Division of Sewerage and Drainage recommended an award be made to the lowest, responsive and responsible bidder General Maintenance and Engineering Company.

 

SUPPLIER: General Maintenance and Engineering Co. (31-4188545)

 

FISCAL IMPACT: $89,293.00 is budgeted and needed for this project. The amount requested includes contingency dollars also budgeted for this project.

 

 

 

 

Title

To authorize the Director of Public Utilities to enter into contract with General Maintenance and Engineering Company for the Parts Storage Building Roof Replacement  for the Division of Sewerage and Drainage, to authorize the expenditure of $89,293.00 from the Sewerage System Operating Fund. ($89,293.00)

 

Body

 

WHEREAS, the Jackson Pike Wastewater Treatment Plant Parts Storage Building has a need for the roof to be replaced, and

 

WHEREAS, bids for the project were opened on October 29, 2003,  six (6) bids were received, three (3) bids were deemed non-responsive for failure to submit the proposal in its entirety, and

 

WHEREAS, the Division of Sewerage and Drainage awarded the contract to General Maintenance and Engineering Company, the lowest, responsive, and responsible bidder, now, therefore

 

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS

 

Section 1. That the Director of Public Utilities be and is hereby authorized to enter into contract with General Maintenance and Engineering Company for Parts Storage Building Roof Replacement  for the Division of Sewerage and Drainage, Jackson Pike Wastewater Treatment Plant.

 

Section 2. That the expenditure of $89,293.00 or so much thereof as may be needed, be and the same hereby is authorized from the Sewerage System Operating Fund, Fund No. 650, OCA 604819, Object Level 1: 06, Object Level 03: 6624

 

Section 3. That this Ordinance shall take effect and be in force from and after the earliest period allowed by law.