File #: 1886-2008    Version: 1
Type: Ordinance Status: Passed
File created: 11/14/2008 In control: Utilities Committee
On agenda: 12/15/2008 Final action: 12/17/2008
Title: To authorize the Director of Public Utilities to execute a contract modification to the professional engineering services agreement with Stantec Consulting Services, Inc., for the Southerly Wastewater Treatment Plant Digester Rehabilitation project; to authorize the transfer and expenditure of $972,976.00 from within the Sanitary Sewer Revenue Bonds Fund; and to amend the 2008 Capital Improvements Budget, for the Division of Sewerage and Drainage. ($972,976.00).
Attachments: 1. ORD1886-2008 Legislation Information.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
12/17/20081 ACTING CITY CLERK Attest  Action details Meeting details
12/16/20081 MAYOR Signed  Action details Meeting details
12/15/20081 Columbus City Council Approved  Action details Meeting details
12/15/20081 COUNCIL PRESIDENT Signed  Action details Meeting details
12/8/20081 Columbus City Council Read for the First Time  Action details Meeting details
11/25/20081 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
11/25/20081 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
11/24/20081 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
11/24/20081 Utilities Drafter Sent for Approval  Action details Meeting details
11/21/20081 EBOCO Reviewer Sent for Approval  Action details Meeting details
11/20/20081 Finance Reviewer Reviewed and Approved  Action details Meeting details
11/20/20081 Finance Reviewer Reviewed and Approved  Action details Meeting details
11/20/20081 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
11/20/20081 Utilities Drafter Sent for Approval  Action details Meeting details
11/20/20081 Auditor Reviewer Reviewed and Approved  Action details Meeting details
11/20/20081 CITY AUDITOR Reviewed and Approved  Action details Meeting details
11/20/20081 Utilities Drafter Sent for Approval  Action details Meeting details
11/19/20081 Utilities Reviewer Sent for Approval  Action details Meeting details
11/19/20081 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
11/19/20081 Utilities Drafter Sent for Approval  Action details Meeting details
11/17/20081 Utilities Reviewer Reviewed and Approved  Action details Meeting details
11/17/20081 Utilities Drafter Sent for Approval  Action details Meeting details
11/17/20081 Utilities Reviewer Reviewed and Approved  Action details Meeting details
11/14/20081 Utilities Drafter Sent for Approval  Action details Meeting details
Explanation
 
1.      BACKGROUND:
 
A.      Need.  This legislation authorizes the Director of Public Utilities to modify the professional engineering services agreement with Stantec Consulting Services, Inc. (formerly R.D. Zande and Associates, Inc.), for the Southerly Wastewater Treatment Plant Digester Rehabilitation project.  The Stantec Consulting Services, Inc. modification amount requested under this ordinance is $972,976.00.  The contract total including this modification is $9,615,470.25.  The proposed contract modification provides additional funding for technical project representation, field project representation, and construction management services now needed during construction. It is not deemed either feasible or reasonable to suspend work with the entity currently under contract and undertake continuation of these services with another procurement.  The cost of the modification is a continuation of the vendor's current pricing structure, as verified by City staff.  The Division has determined that these services cannot be performed by City personnel at this time, and has planned for the procurement of these services on a routine basis.
 
B.      Contract Compliance No.:  112167170/001 (MAJ) (Expires 01/07/2010)
 
C.      Emergency Designation:  Emergency designation is not requested.
 
2.      FISCAL IMPACT:
 
This ordinance authorizes the transfer of funds from within the Sanitary Sewer Revenue Bonds Fund for this expenditure. The 2008 Capital Improvements Budget is amended for this expenditure upon passage of this ordinance.
 
 
Title
 
To authorize the Director of Public Utilities to execute a contract modification to the professional engineering services agreement with Stantec Consulting Services, Inc., for the Southerly Wastewater Treatment Plant Digester Rehabilitation project; to authorize the transfer and expenditure of $972,976.00 from within the Sanitary Sewer Revenue Bonds Fund; and to amend the 2008 Capital Improvements Budget, for the Division of Sewerage and Drainage. ($972,976.00).
 
Body
 
WHEREAS, Contract No. EL900074 was authorized by Ordinance No. 2853-98 as passed by Columbus City Council on November 16, 1998, for purposes of authorizing the Director of Public Utilities to enter into a contract for professional engineering services with R. D. Zande & Associates, Inc., now acquired by Stantec Consulting Services, Inc., and so referred to hereafter, for the Southerly Wastewater Treatment Plant Digester Rehabilitation project; and
WHEREAS, it is necessary to modify the subject contract in order to provide funding for additional construction-phase engineering, start-up, and commissioning assistance services now needed during the project's construction of Contract S66; and
 
WHEREAS, it is necessary to authorize the transfer of funds within the Sanitary Sewer Revenue Bonds Fund to provide sufficient funding for the aforementioned project expenditure; and
 
WHEREAS, it is necessary to authorize an amendment to the 2008 Capital Improvements Budget for the purpose of providing sufficient spending authority for the aforementioned project expenditure; and
 
WHEREAS, it is necessary for City Council to authorize the expenditure of funds from the Sanitary Sewer Revenue Bonds Fund; and
 
WHEREAS, the Division of Sewerage and Drainage, Department of Public Utilities is requesting that this Council authorize the Director of Public Utilities to modify the professional engineering services agreement  with Stantec Consulting Services, Inc., for the Southerly Wastewater Treatment Plant Digester Rehabilitation project at the earliest practical date; Now, Therefore,
 
 
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
 
Section 1.  That the Director of Public Utilities be, and hereby is, authorized to modify Contract No. EL900074 with Stantec Consulting Services, Inc., 1500 Lake Shore Drive, Columbus, Ohio 43204, for professional engineering services for the Southerly Wastewater Treatment Plant Digester Rehabilitation project, in accordance with the terms and conditions as shown in the contract modification on file in the office of the Division of Sewerage and Drainage.
 
Section 2.  That the City Auditor is hereby authorized to transfer $972,976.00 within the Sanitary Sewer Revenue Bonds Fund | Fund 665 | OBJLVL3: 6678 | Division of Sewerage and Drainage | Div. 60-05:
 
FROM:  
Proj. No. | Proj. Name | OCA | Amount
650350 | Wastewater Treatment Plants Rehabilitation | 665350 | $800,574.00
650364 | SWWTP Headworks, Part 2 | 665364 | $146,131.00
650367 | SWWTP Primary and Aeration | 665367 | $26,271.00
 
TO:
Proj. No. | Proj. Name | OCA | Amount
650353 | SWWTP Digester Rehabilitation | 665353 | $972,976.00
 
 
Section 3.  That the 2008 Capital Improvements Budget Ordinance No.0690-2008 is hereby amended as follows, to provide sufficient budget authority for the award of the agreement stated herein.
 
Project No. | Project Name | Current Authority | Revised  Authority | (Change)
650350 | Wastewater Treatment Plants Rehabilitation | $1,300,574 | $500,000 | (-$800,574)
650364 | SWWTP Headworks, Part 2 | $19,483,488 | $19,337,357 | (-$146,131)
650367 | SWWTP Primary and Aeration | $31,125,416 | $31,099,145 | (-$26,271)
650353 | SWWTP Digester Rehabilitation | $2,000,577 | $2,973,553 | (+$972,976.00)
 
 
Section 4.  That for the purpose of paying the cost of the professional engineering services contract modification, the following expenditure, or as much thereof as may be needed, by and the same is hereby authorized as follows: Division 60-05 | Fund 665 | SWWTP Digester Rehabilitation | Project No. 650353 | OBJLVL3: 6678 | OCA Code 665353 | Amount $972,976.00.
 
Section 5.  That the City Auditor is hereby authorized to transfer any unencumbered balance in the project account to the unallocated balance within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies are no longer required for said project; except that no transfer shall be made from a project by monies from more than one source.
 
Section 6.  That the City Auditor is authorized to establish proper project accounting numbers as appropriate.
 
Section 7.  That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this ordinance.
 
Section 8.  That the said firm shall perform the work to the satisfaction of the Director of Public Utilities and the Administrator of the Division of Sewerage and Drainage.
 
Section 9.  That this ordinance shall take effect and be in force from and after the earliest period allowed by law.