Title: To authorize the Finance and Management Director to enter into contract for the Facilities Management Division with General Maintenance and Engineering Company, for the renovation of the roof at the Fire Administration building, to authorize the expenditure of $116,793.00 from the Safety Voted Bond Fund, and to declare an emergency. ($116,793.00)
Date Ver.Action ByActionResultAction DetailsMeeting Details
12/14/20051 MAYOR Signed  Action details Meeting details
12/14/20051 ACTING CITY CLERK Attest  Action details Meeting details
12/12/20051 Columbus City Council ApprovedPass Action details Meeting details
12/12/20051 COUNCIL PRESIDENT Signed  Action details Meeting details
11/28/20051 Finance Drafter Sent to Clerk's Office for Council  Action details Meeting details
11/23/20051 Finance Drafter Sent for Approval  Action details Meeting details
11/23/20051 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
11/22/20051 CITY AUDITOR Reviewed and Approved  Action details Meeting details
11/22/20051 Finance Drafter Sent for Approval  Action details Meeting details
11/22/20051 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
11/21/20051 Finance Drafter Sent for Approval  Action details Meeting details
11/21/20051 Auditor Reviewer Reviewed and Approved  Action details Meeting details
11/21/20051 CITY AUDITOR Reviewed and Approved  Action details Meeting details
11/18/20051 SAFETY DIRECTOR Reviewed and Approved  Action details Meeting details
11/16/20051 Finance Drafter Sent for Approval  Action details Meeting details
11/16/20051 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
11/16/20051 Finance Drafter Sent for Approval  Action details Meeting details
11/15/20051 Finance Reviewer Reviewed and Approved  Action details Meeting details
11/15/20051 EBOCO Reviewer Reviewed and Approved  Action details Meeting details
11/15/20051 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
11/11/20051 Finance Drafter Sent for Approval  Action details Meeting details
Explanation
 
BACKGROUND:  This ordinance authorizes the Finance and Management Director to enter into contract for the Facilities Management Division with General Maintenance and Engineering Company, in the amount of $116,793.00 for the renovation of the roof at Fire Administration building, 3675 Parsons Avenue.  The current roof is approximately twenty-five years old and leaks.   The renovation will consist of the replacement of the current roof with a granular-textured roof of modified bitumen asphalt.  The contractor has sixty days upon notification of the award of the contract to complete the project.  The roof will include a two-year workmanship guarantee from the contractor and a thirty-year workmanship and material guarantee from the manufacturer.  This roof renovation work is a LEED project.  
 
Formal proposals were solicited on September 29, 2005.  Three firms submitted proposals on October 18, 2005 as follows:  (0 MBE, 0 FBE).
 
                      General Maintenance and Engineering Co.         $116,793.00
VEC Systems                        $138,900.00
K & W Roofing, Inc.                                        $159,199.00                                      
                      
                          
It is the recommendation of the Facilities Management Division to award this contract to the most responsive and responsible bidder, General Maintenance and Engineering Company.  
 
Emergency action is requested so that the contractor will be able to complete this project during good weather.  
 
Fiscal Impact:  The Fire Division budgeted $185,000.00 in the Capital Improvement Budget for this project.  The cost of this contract is $116,793.00.  General Maintenance and Engineering Company Contract Compliance Number 31-14188545, expiration 02/25/2008.
 
 
Title
 
To authorize the Finance and Management Director to enter into contract for the Facilities Management Division with General Maintenance and Engineering Company, for the renovation of the roof at the Fire Administration building, to authorize the expenditure of $116,793.00 from the Safety Voted Bond Fund, and to declare an emergency.  ($116,793.00)
 
 
Body
 
WHEREAS, the roof at the Fire Administration building is in disrepair and in need of replacement, and  
 
WHEREAS, the Facilities Management Division recommends acceptance of the bid submitted by General Maintenance and Engineering Company as the most responsive and responsible bid, and
WHEREAS; an emergency exists in the usual daily operation of the Facilities Management Division in that it is immediately necessary to authorize the Finance and Management Director to enter into contract with General Maintenance and Engineering Company for a roof renovation at the Fire Administration building so that such renovations can be done in good weather, thereby preserving the public health, peace, property, safety, and welfare; now, therefore:
 
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
 
SECTION 1.  That the Finance and Management Director is hereby authorized to contract with General Maintenance and Engineering Company for the renovation of the roof at the Fire Administration building, 3675 Parsons Avenue.
 
SECTION 2.   That the expenditure of $116,793.00, or so much thereof that may be necessary in regard to the action authorized in SECTION 1, be and is hereby authorized and approved as follows:
 
Division: 30-04
Fund: 701
Project:  340103
OCA Code: 644559
Object Level 1: 06
Object Level 3: 6620
Amount: $116,793.00
 
SECTION 3. That for reasons stated in the preamble hereto, which is hereby made a part hereof, this ordinance is hereby declared to be an emergency measure and shall take effect and be in force from and after its passage and approval by the Mayor, or ten days after passage if the mayor neither approves or vetoes the same.