File #: 0405-2011    Version: 1
Type: Ordinance Status: Passed
File created: 3/3/2011 In control: Public Utilities Committee
On agenda: 4/11/2011 Final action: 4/13/2011
Title: To authorize the Director of Public Utilities to execute a construction contract with Darby Creek Excavating, Inc. for the German Village Area Water Line Improvements Project; for the Division of Power and Water; to authorize a transfer and expenditure within the Water Build America Bonds Fund; for the Division of Power and Water; and to amend the 2011 Capital Improvements Budget. ($820,641.87)
Attachments: 1. ORD0405-2011 bid tab.pdf, 2. ORD0405-2011 QFF.pdf, 3. ORD0405-2011 Information.pdf, 4. ORD0405-2011 Sub ID.pdf, 5. ORD0405-2011 map.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
4/13/20111 CITY CLERK Attest  Action details Meeting details
4/12/20111 MAYOR Signed  Action details Meeting details
4/11/20111 Columbus City Council ApprovedPass Action details Meeting details
4/11/20111 COUNCIL PRESIDENT Signed  Action details Meeting details
4/4/20111 Columbus City Council Read for the First Time  Action details Meeting details
3/22/20111 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
3/22/20111 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
3/21/20111 Utilities Drafter Sent for Approval  Action details Meeting details
3/18/20111 Utilities Drafter Sent for Approval  Action details Meeting details
3/18/20111 Auditor Reviewer Reviewed and Approved  Action details Meeting details
3/18/20111 CITY AUDITOR Reviewed and Approved  Action details Meeting details
3/18/20111 Utilities Drafter Sent for Approval  Action details Meeting details
3/18/20111 EBOCO Reviewer Sent for Approval  Action details Meeting details
3/18/20111 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
3/17/20111 Finance Reviewer Reviewed and Approved  Action details Meeting details
3/17/20111 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
3/16/20111 Finance Reviewer Reviewed and Approved  Action details Meeting details
3/15/20111 Finance Reviewer Reviewed and Approved  Action details Meeting details
3/15/20111 Finance Reviewer Reviewed and Approved  Action details Meeting details
3/14/20111 Utilities Drafter Sent for Approval  Action details Meeting details
3/11/20111 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
3/9/20111 Utilities Reviewer Sent for Approval  Action details Meeting details
3/8/20111 Utilities Drafter Sent for Approval  Action details Meeting details
3/7/20111 Utilities Drafter Sent for Approval  Action details Meeting details
3/4/20111 Utilities Reviewer Reviewed and Approved  Action details Meeting details
3/4/20111 Utilities Drafter Sent for Approval  Action details Meeting details
3/4/20111 Utilities Reviewer Reviewed and Approved  Action details Meeting details
3/3/20111 Utilities Drafter Sent for Approval  Action details Meeting details
Explanation
 
1.  BACKGROUND:  This legislation authorizes the Director of Public Utilities to enter into a construction contract with Darby Creek Excavating, Inc., in the amount of $820,641.87; for the German Village Area Water Line Improvements Project, Division of Power and Water Contract Number 1126.
 
This project provides for general rehab of the area distribution system and includes construction of new water lines, abandoning existing 2-inch diameter and smaller water lines, installing fire hydrants, and transferring water services.  The purpose of the project is to improve flow and water quality, improve fire protection, and replace water mains that require repeated regular maintenance.  This project will include the installation of approximately 4,800 feet of 6-inch water lines at the following locations:  Whittier Street, Ebner Street, City Park Avenue, Washington Avenue, Kent Street and Gault Street.
 
2. CONSTRUCTION CONTRACT AWARD:  The Director of Public Utilities publicly opened eleven bids on February 23, 2011.  Bids were received from:  Darby Creek Excavating, Inc. - $820,641.87; Danbert, Inc. - $838,744.28; Fields Excavating, Inc. - $903,352.01; John Eramo & Sons, Inc. - $914,616.73; Beheler Excavating, Inc. - $942,279.58; Columbus Asphalt Paving Co. - $991,141.86; Shelly & Sands, Inc. - $1,014,332.00; George J. Igel & Co. - $1,086,634.73; Complete General Construction Co. - $1,161,007.65; and Conie Construction Co. - $782,100.00 (non-responsive).
 
The lowest, best, most responsive, responsible bid was from Darby Creek Excavating, Inc. in the amount of $820,641.87.  Their Contract Compliance Number is 31-1345111 (3/5/12, Majority).  Additional information regarding each bidder, description of work, contract time frame and detailed amounts can be found on the attached Information form.
 
Searches in the Excluded Party List System (Federal) and the Findings for Recovery list (State) produced no findings against Darby Creek Excavating, Inc.
 
3.  FISCAL IMPACT This legislation includes a transfer of funds within the Water Build America Bonds Fund and an amendment to the 2011 Capital Improvements Budget.
 
 
Title
 
To authorize the Director of Public Utilities to execute a construction contract with Darby Creek Excavating, Inc. for the German Village Area Water Line Improvements Project; for the Division of Power and Water; to authorize a transfer and expenditure within the Water Build America Bonds Fund; for the Division of Power and Water; and to amend the 2011 Capital Improvements Budget.  ($820,641.87)
 
 
Body
 
WHEREAS, eleven bids for the German Village Area Water Line Improvements Project were received and publicly opened in the offices of the Director of Public Utilities on February 23, 2011; and
 
WHEREAS, the lowest, best, most responsive, responsible bid was from Darby Creek Excavating, Inc. in the amount of $820,641.87; and
 
WHEREAS, it is necessary to authorize the Director of the Department of Public Utilities to award and execute a construction for the German Village Area Water Line Improvements Project; and
 
WHEREAS, it is necessary for this Council to authorize the City Auditor to transfer funds within the Water Build America Bonds Fund; and
 
WHEREAS, it is necessary to authorize an amendment to the 2011 Capital Improvements Budget for purposes of providing sufficient funding and expenditure authority for the aforementioned project expenditure; and
 
WHEREAS, it has become necessary in the usual daily operation of the Division of Power and Water, Department of Public Utilities, to authorize the Director of Public Utilities to enter into a construction contract with Darby Creek Excavating, Inc. for the German Village Area Water Line Improvements Project, for the preservation of the public health, peace, property and safety; now therefore,
 
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
 
SECTION 1.  That the Director of Public Utilities be and hereby is authorized to award and execute a construction contract for the German Village Area Water Line Improvements Project with the lowest, best, most responsive, responsible bidder, Darby Creek Excavating, Inc., 6790 Brooksmiller Rd., Circleville, Ohio 43113; in the amount of $820,641.87; in accordance with the terms and conditions of the contract on file in the Office of the Division of Power and Water.
 
SECTION 2.  That the City Auditor is hereby authorized to transfer $820,641.87 within the Division of Power and Water, Dept/Div. No. 60-09, Water Build America Bonds Fund, Fund No. 609, Object Level One 06, Object Level Three 6629, as follows:
 
Fund No. | Project No. | Project Name | OCA Code | change
609 | 690460-100000 (carryover) | Dublin Rd. W.M. | 609460 | -$820,641.87
609 | 690236-100010 (carryover) | German Village W.L. | 693610 | +$820,641.87
 
SECTION 3.  That the 2011 Capital Improvements Budget is hereby amended as follows:
 
Fund No. | Project No. | Project Name | Current Authority | Revised Authority | change
609 | 690460-100000 (carryover) | Dublin Rd. W.M. | $1,029,091 | $208,449 | -$820,642
609 | 690236-100010 (carryover) | German Village W.L. | $0 | $820,642 | +$820,642
 
SECTION 4.  That the expenditure of $820,641.87 is hereby authorized for the German Village Area Water Line Improvements Project within the Water Build America Bonds Fund, Fund No. 609, Division 60-09, Project No. 690236-100010 (carryover), Object Level Three 6629, OCA Code 693610.
 
SECTION 5.  That said construction company shall conduct the work to the satisfaction of the Director of Public Utilities and the Administrator of the Division of Power and Water.
 
SECTION 6.  That the City Auditor is hereby authorized and directed to transfer any unencumbered balance in the project account to the unallocated balance within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies no longer required for said project; except that no transfer shall be made from a project account by monies from more than one source.
SECTION 7.  That the City Auditor is authorized to establish proper project accounting numbers as appropriate.
 
SECTION 8.  That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this Ordinance.
 
SECTION 9.  That this Ordinance shall take effect and be in force from and after the earliest period allowed by law.