File #: 0200-2023    Version: 1
Type: Ordinance Status: Passed
File created: 1/12/2023 In control: Public Utilities Committee
On agenda: 3/20/2023 Final action: 3/22/2023
Title: To authorize an amendment to the 2022 Capital Improvement Budget; to authorize a transfer of cash and appropriation between projects within the Water Bond Fund and within the Sanitary Bond Fund; to authorize the Director of Public Utilities to enter into a contract for Construction Administration and Inspection Services with Resource International; and to authorize an expenditure of up to $540,123.70 from the Water Bond Fund and the Sanitary Bond Fund for the contract. ($540,123.70)
Indexes: WBE Participation
Attachments: 1. ORD 0200-2023 Accounting Template, 2. ORD 0200-2023 Map, 3. ORD 0200-2023 Utilization Plan

Explanation

1.  BACKGROUND

This ordinance authorizes the Director of Public Utilities to enter into a contract with Resource International for construction administration/inspection services for Department of Public Utilities construction projects bid during the calendar years 2023 through 2025 as part of the Construction Administration/Construction Inspection Services 2023-2025 contracts. 

 

The first three construction projects to be administered by Resource International under this contract are:

• CIP #690477-100018 North District East Tank 2023 Painting Improvements project

• CIP #690549-100012 CA-CI for General Water Construction Projects

• CIP #650800-100039 Construction Administration Services 2023-2025

 

Resource International will be assigned these construction projects as tasks on their contract and will ensure the work is performed to City of Columbus construction standards and specifications.  Future construction projects assigned to Resource International will be added to their Construction Administration/Construction Inspection Services 2023-2025 contract as tasks, and the contract will be modified to authorize the Resource International work and to add funding to pay for the work.

 

This work will be primarily be performed in Columbus Community Area 39 - Clintonville.

 

2.  PROCUREMENT

The Department of Public Utilities advertised a Request for Proposals on the Vendor Services and Bonfire websites from 10/14/22 through 11/18/22 in order to solicit proposals for the Construction Administration/Construction Inspection Services 2023-2025 contracts with the intention of awarding contracts to multiple companies.  Proposals were received from the following companies:

 

Name

CC No.

Exp. Date

 City/State

Status

CTL Engineering

CC-004209

7/31/2024

Columbus, OH

MBE

DLZ Ohio

CC-004939

4/29/2024

Columbus, OH

MBE

EMH&T

CC-004214

11/16/2024

Columbus, OH

MAJ

FAR Group

None

None

Stafford, VA

Unknown

Resource Intl.

CC-004197

5/31/2023

Columbus, OH

WBE

Smoot Construction

CC-004871

6/30/2023

Columbus, OH

MBE

Stantec

CC-000462

7/28/2023

Columbus, OH

MAJ

True Inspection

CC-011399

10/19/2024

Columbus, OH

MBE

Anser Advisory

CC-041113

3/3/2024

Columbus, OH

MAJ

Hill International

CC-000990

11/9/2024

Columbus, OH

MAJ

Mannik Smith

CC-006578

10/11/2024

Columbus, OH

MAJ

PRIME CMS

CC-024771

10/4/2024

Columbus, OH

MAJ

 

All proposals were considered responsive and were evaluated by the evaluation committee.  The six companies with proposals scored the highest by the evaluation company will be offered contracts if City Council approves.  The six companies (in score order) are:  Resource International; DLZ; CTL Engineering; EMH&T; PRIME CMS; and Stantec.  Resource International is the first of the contracts to go before City Council for approval.

 

3.  ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT

This work will ensure the Department’s construction projects are done correctly and will last the anticipated service life.   No community outreach is planned at this time.

 

4.  CONTRACT COMPLIANCE INFORMATION

Resource International’s contract compliance number is CC-004197 and expires 5/31/23

 

Searches in the Excluded Party List System (Federal) and the Findings for Recovery list (State) were not required for this contract as no State or Federal money will be used to pay for contracted services.

                                                        

5.  MINORITY AND WOMAN OWNED BUSINESS ENTERPRISE & SMALL LOCAL BUSINESS ENTERPRISE PROGRAM

This contract opportunity was submitted to the City’s Office of Diversity and Inclusion (ODI) for review and assignment of an MBE/WBE goal prior to bidding.  ODI determined there was not an opportunity for MBE/WBE participation in this contract and did not assign a goal.  This contract was not bid with a City of Columbus MBE/WBE Program goal and the requirements of the City’s MBE/WBE Program are not applicable to this contract.  Resource International is ODI certified as a WBE.  As shown in the Utilization Plan attached to this ordinance, Resource International plans to do the work on this task without subcontractors so the MBE/WBE participation is 100% for the first contract task.

 

6.  FISCAL IMPACT

Funds in the amount of $540,123.70 are available and appropriated within the Water Bond Fund ($490,123.70), Fund 6006, and within the Sanitary Bond Fund ($50,000.00), Fund 6109.  An amendment to the 2022 Capital Improvement Budget is necessary to align budget authority with the proper projects.  A transfer of cash and appropriation within the Water Bond Fund and within the Sanitary Bond Fund is needed to align cash and appropriation with the proper projects.

 

Title

To authorize an amendment to the 2022 Capital Improvement Budget; to authorize a transfer of cash and appropriation between projects within the Water Bond Fund and within the Sanitary Bond Fund; to authorize the Director of Public Utilities to enter into a contract for Construction Administration and Inspection Services with Resource International; and to authorize an expenditure of up to $540,123.70 from the Water Bond Fund and the Sanitary Bond Fund for the contract.  ($540,123.70)

 

Body

WHEREAS, the Department of Public Utilities advertised a Request for Proposals for Construction Administration/Construction Inspection Services; and

 

WHEREAS, Resource International was one of six firms selected by the evaluation committee to provide these services; and

 

WHEREAS, an amendment to the 2022 Capital Improvement Budget is needed to align budget authority with the proper projects; and

 

WHEREAS, it is necessary to transfer cash and appropriation within the Water Bond Fund and the Sanitary Bond Fund to align cash and appropriation within the proper projects; and

 

WHEREAS, funds must be expended to pay for the construction administration and inspection services Resource International provides under the Construction Administration/Construction Inspection Services 2023-2025 contract;

 

WHEREAS, it has become necessary in the usual daily operation of the Department of Public Utilities to authorize the Director to enter into a contract with Resource International for Construction Administration/Construction Inspection Services for the North District East Tank 2023 Painting Improvements; now, therefore

 

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:

 

SECTION 1.  That the 2022 Capital Improvement Budget authorized by Ordinance 1896-2022 be amended as follows to establish sufficient budget authority for this project:

 

Fund / Project Number / Project Name / Current / Change / Amended

6006 / 690603 - 100000 / Ohio State University Area Utility Easement Project - Water (Voted Water Carryover) / $120,000.00 / ($120,000.00) / $0.00

6006 / 690236 - 100148 / New World Drive WL Imp's (Voted Water Carryover) / $46,421.00 / ($46,421.00) / $0.00

6006 / 690521 - 100003 / Large Diameter Valve Replacement (Voted Water Carryover) / $3,197.00 / ($3,197.00) / $0.00

6006 / 690521 - 100008 / 2019 Water Main Repairs (Voted Water Carryover) / $1,325.00 / ($1,325.00) / $0.00

6006 / 690528 - 100002 / 2016 Gen'l Engineering Services - Distribution Group (Voted Water Carryover) / $160,170.00 / ($160,170.00) / $0.00

6006 / 690549 - 100011 / General Construction (CA-CI) for 2020, 2021, 2022 (Voted Water Carryover) / $250,000.00 / ($159,011.00) / $90,989.00

 

6006 / 690477-100018 / North District East Tank 2023 Painting Improvements (Voted Water Carryover) / $0.00 / $440,124.00 / $440,124.00

6006 / 690549-100012 / General Construction (CA-CI) for 2023, 2024, 2025 (Voted Water Carryover) / $0.00 / $50,000.00 / $50,000.00

 

6109 / 650800-100038 / Construction Administration Services 2020 to 2022 (Voted Sanitary Carryover) / $40,190.00 / ($40,190.00) / $0.00

6109 / 650895-100007 / Sunbury Rd / Mock Rd HSTS Elimination Project (Voted Sanitary Carryover) / $231,662.00 / ($9,811.00) / $221,851.00

 

6109 / 650800-100039 / Construction Administration Services 2023-2025 (Voted Sanitary Carryover) / $0.00 / $50,000.00 / $50,000.00

 

SECTION 2.  That the transfer of cash and appropriation between projects within the Water Bond Fund, Fund 6006, and within the Sanitary Bond, Fund 6109, is authorized per the accounting codes in the attachment to this ordinance.

 

SECTION 3.  That the Director of Public Utilities is hereby authorized to enter into a contract with Resource International, 6350 Presidential Gateway, Columbus, Ohio, 43231, for construction administration and inspection services, in accordance with the terms and conditions as shown in the contract on file with the Department of Public Utilities.

 

SECTION 4. That the expenditure of up to $540,123.70 is hereby authorized per the accounting codes in the attachment to this ordinance.

 

SECTION 5.  Funds are hereby deemed appropriated and expenditures and transfers authorized to carry out the purposes of this ordinance and the City Auditor shall establish such accounting codes as necessary.

 

SECTION 6.  That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this ordinance.

 

SECTION 7.  That the City Auditor is hereby authorized to transfer the unencumbered balance in a project account to the unallocated balance account within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies are no longer required for said project.

 

SECTION 8.  That this Ordinance shall take effect and be in force from and after the earliest period allowed by law.