File #: 1368-2009    Version: 1
Type: Ordinance Status: Passed
File created: 10/9/2009 In control: Development Committee
On agenda: 11/16/2009 Final action: 11/17/2009
Title: To authorize the Directors of Development and Public Service to amend the Design Agreement for the Columbus Coated Fabrics site with Wagenbrenner Development, Inc. by increasing the scope of work to include a traffic study of existing and projected conditions around the site and to increase the contract amount by $18,700; to amend the 2009 CIB; and to authorize the expenditure of $18,700.00 from the Development G.O. Bonds Fund. ($18,700)
Date Ver.Action ByActionResultAction DetailsMeeting Details
11/17/20091 ACTING MAYOR Signed  Action details Meeting details
11/17/20091 CITY CLERK Attest  Action details Meeting details
11/16/20091 Columbus City Council ApprovedPass Action details Meeting details
11/16/20091 COUNCIL PRESIDENT Signed  Action details Meeting details
11/9/20091 Columbus City Council Read for the First Time  Action details Meeting details
10/29/20091 Dev Drafter Sent for Approval  Action details Meeting details
10/29/20091 Auditor Reviewer Reviewed and Approved  Action details Meeting details
10/29/20091 CITY AUDITOR Reviewed and Approved  Action details Meeting details
10/29/20091 Dev Drafter Sent for Approval  Action details Meeting details
10/29/20091 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
10/29/20091 Dev Drafter Sent to Clerk's Office for Council  Action details Meeting details
10/28/20091 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
10/27/20091 Finance Reviewer Reviewed and Approved  Action details Meeting details
10/27/20091 Finance Reviewer Reviewed and Approved  Action details Meeting details
10/26/20091 Dev Drafter Sent for Approval  Action details Meeting details
10/26/20091 Dev Drafter Sent for Approval  Action details Meeting details
10/23/20091 SERVICE DIRECTOR Reviewed and Approved  Action details Meeting details
10/23/20091 Service Drafter Sent for Approval  Action details Meeting details
10/22/20091 Service Reviewer Reviewed and Approved  Action details Meeting details
10/22/20091 Service Drafter Sent for Approval  Action details Meeting details
10/16/20091 Service Drafter Sent for Approval  Action details Meeting details
10/14/20091 Dev Drafter Sent for Approval  Action details Meeting details
10/14/20091 DEVELOPMENT DIRECTOR Reviewed and Approved  Action details Meeting details
10/14/20091 Dev Drafter Sent for Approval  Action details Meeting details
Explanation
 
Background:  The City of Columbus entered into a Design Agreement with Wagenbrenner Development, Inc. to design public right-of-way improvements in and around the former Columbus Coated Fabrics site. During the design phase it became apparent that a traffic study would be necessary to compare existing and projected conditions around the site in order to determine the need for traffic signals and additional traffic lanes. For this reason it is desirable to modify the existing design contract of $1,060,000 to include the completion of this study and to increase the dollar amount by $18,700 for a total contract amount of $1,078,700.
 
Fiscal Impact:  $18,700 is available in capital Fund 742 Development G.O. Bonds.
 
 
Title
 
To authorize the Directors of Development and Public Service to amend the Design Agreement for the Columbus Coated Fabrics site with Wagenbrenner Development, Inc. by increasing the scope of work to include a traffic study of existing and projected conditions around the site and to increase the contract amount by $18,700; to amend the 2009 CIB; and to authorize the expenditure of $18,700.00 from the Development G.O. Bonds Fund. ($18,700)
 
 
Body
 
WHEREAS, Wagenbrenner Development, Inc. is under contract with the City as the developer of the Columbus Coated Fabrics site; and
 
WHEREAS, Ordinance 0043-2009 authorized the City to enter into a Design Agreement with the developer to design public right-of-way improvements in and around the site; and
 
WHEREAS, the design phase has identified potential traffic changes due to the redevelopment and the Department of Public Service has requested a traffic study be completed; and
 
WHEREAS, it is desirable by both the Wagenbrenner Development, Inc. and the City of Columbus to modify the existing contract in scope and dollars in order to complete the traffic study so traffic changes can be made while still in the design phase; and NOW, THEREFORE,
 
 
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
 
 
Section 1.      That the Directors of Development and Public Service are hereby authorized and directed to amend EL009527 with Wagenbrenner Development, Inc. by increasing the scope and dollars by $18,700 to conduct a traffic study of existing and projected conditions in and around the Columbus Coated Fabrics redevelopment site.
 
Section 2.      That the 2009 Capital Improvements Budget established within ordinance 0806-2009 be and hereby is amended due to encumbrance cancellations as follows:
 
Fund No / Project No / Project / Current CIB Amount / Amendment Amount / CIB Amount
742 / 440104 / Misc. Economic Development / $8031 / $46,041 / $54,072
 
Section 3.      That for the purpose stated in Section 1, the expenditure of up to $18,700 from Fund 742, Development G.O. Bonds, Project No. 440104-100000 Misc. Economic Development, Object Level One 06, Object Level Three 6680, OCA Code 643106 is hereby authorized.
 
Section 4.      That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this ordinance.
 
Section 5.      That it is further agreed that in all other aspects, this contract remains unchanged.
 
Section 6.      That this ordinance shall take effect and be in force from and after the earliest period allowed by law.