Title: To authorize the City Auditor to transfer $41,800.00 within the voted Recreation and Parks Bond fund; to amend the 2012 Capital Improvements Budget Ord. 0368-2012; to authorize and direct the Director of Recreation and Parks to enter into contract with DLZ Ohio, Inc for the Clinton Como Park & Woodbridge Green Park Design ; to authorize the expenditure of $38,000.00 and a contingency of $3,800.00 for a total of $41,800.00 from the Voted Recreation and Parks Bond Fund; and to declare an emergency. ($41,800.00)
Explanation
Background:
Proposals were received by the Recreation and Parks Department on March 15th, 2012 for the Clinton Como Park & Woodbridge Green Park Design , as follows:
                                                                             Status                        
                              DLZ                                          MBE
                             CYP Studios                              FBE
                             POD Design, LLC                        ASN
                             Blake Rafeld & Associates            MAJ
                             Stantec                                          MAJ
                             CD + Designs, LLC                        MAJ
                             EMH&T                                    MAJ
                             Floyd Browne                              MAJ
                             Edge Group                                    MAJ
                             Edsall & Associates                        FBE
                             
 
Consultant shall provide site services to prepare design development, construction plans and specifications for bidding for park improvements.   Work is to include park improvements and renovations at the following parks. Services shall include the design development of the schematic plans, presentations, public meeting(s) as identified, including Area Commission approval, cost estimates and construction schedule, construction, bid documents and construction administration services.
Clinton-Como and Woodbridge Green Parks  
Both of these are north side parks.  Clinton-Como Park is located at 399 West Pacemont Avenue (43202).  Park facilities have deteriorated and community has participated in preliminary discussions for renovation.  Woodbridge Green Park is located at 1700 Hard Road (43235).  Playground has been installed within the previous 12 months and will not be a part of renovations.   Public presentations: Clinton-Como is in the Clintonville Area Commission.  Woodbridge Green is in the Far Northwest Area Commission.
     
Principal Parties:
DLZ Ohio, Inc.
Ram Rajadhyaksha (contact)
6121 Huntley Road
Columbus, OH  43229
Phone: 614-888-0040
Contract Compliance #311268980
Contract Compliant through 2/22/13
50+ Columbus Employees
 
Fiscal Impact: $41,800.00 from the Voted Recreation and Parks Bond Fund 702.
Title
To authorize the City Auditor to transfer $41,800.00 within the voted Recreation and Parks Bond fund; to amend the 2012 Capital Improvements Budget Ord. 0368-2012; to authorize and direct the Director of Recreation and Parks to enter into contract with DLZ Ohio, Inc for the Clinton Como Park & Woodbridge Green Park Design ; to authorize the expenditure of $38,000.00 and a contingency of $3,800.00 for a total of $41,800.00 from the Voted Recreation and Parks Bond Fund; and to declare an emergency.  ($41,800.00)
Body
WHEREAS, funds are being moved to alternate projects within Fund 702 to establish correct funding project detail location for the Clinton Como Park & Woodbridge Green Park Design Improvements Project; and
WHEREAS, the 2012 Capital Improvement Budget will be amended to reflect the fund transfers from projects within Fund 702; and
 
WHEREAS, it is necessary to enter into contract with  DLZ Ohio, Inc for the Clinton Como Park & Woodbridge Green Park Design ; and
WHEREAS, an emergency exists in the usual daily operation of the Recreation and Parks Department in that it is immediately necessary to enter into said contract so that work may begin during the current construction season; NOW, THEREFORE
 
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
 
SECTION 1.   That the Director of Recreation and Parks be and he is hereby authorized and directed to enter into contract with DLZ Ohio, Inc for the Clinton Como Park & Woodbridge Green Park Design.
 
SECTION 2. That the City Auditor is hereby authorized to transfer $41,800.00 within the voted Recreation and Parks Bond Fund No. 702 for the projects listed below:
FROM:
Project                                                 OCA Code       Object Level 3         Amount
510035-100181 McDonald Complex                     723581              6620                   $41,800.00
TO:      
Project                                                OCA Code       Object Level 3          Amount
510017-100100 (Clinton Como)                             717100               6620                   $20,900.00
510017-100444 (Woodbridge Green)                     717444            6620                    $20,900.00
SECTION 3. That the 2012 Capital Improvements Budget Ord. 0368-2012 is hereby amended as follows in order to provide sufficient budget authority for this legislation.
 
CURRENT:
Fund 702; Project 510035-100181/McDonald Complex/ $2,500,000/ (Voted carryover)
Fund 702; Project 510017-100100/Clinton Como/ $0.00/ (Voted carryover)
Fund 702; Project 510017-100444/Woodbridge Green/ $0.00/ (Voted carryover)
AMENDED TO:
Fund 702; Project 510035-100181/McDonald Complex/ $2,458,200/ (Voted carryover)
Fund 702; Project 510017-100100/Clinton Como/ $20,900/ (Voted carryover)
Fund 702; Project 510017-100444/Woodbridge Green/ $20,900/ (Voted carryover)
SECTION 4. That the expenditure of $41,800.00 or so much thereof as may be necessary to pay the cost thereof, be and is hereby authorized from the Voted Recreation & Parks Bond Fund 702, as follows:
Project                                                       OCA Code           Object Level 3       Amount
510017-100100 (Clinton Como)                        717100                  6680                  $20,900.00
510017-100444 (Woodbridge Green)                717444                  6680                       $20,900.00
SECTION 5.  That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this legislation.
SECTION 6.   That for the reasons stated in the preamble hereto, which is hereby made a part hereof, this ordinance is hereby declared to be an emergency measure and shall take effect and be in force from and after its passage and approval by the Mayor, or 10 days after passage if the Mayor neither approves nor vetoes the same.