Title: To authorize the Director of Public Utilities to enter into a construction contract with Kokosing Industrial, Inc. for the Hap Cremean Water Plant (HCWP) UV Disinfection Facility Project; to authorize the appropriation and transfer of $14,539,450.00 from the Water System Reserve Fund to the Water Supply Revolving Loan Account Fund; and to authorize the appropriation and expenditure of $14,539,450.00 from the Water Supply Revolving Loan Account Fund for the Division of Water. ($14,539,450.00)
Attachments: 1. Ord. 1456-2018 Information, 2. ORD. 1456-2018 Bid Tab, 3. Ord. 1456-2018 HCWP Map, 4. Ord. 1456-2018 QFF Eval Loan Funded, 5. Ord. 1456-2018 SWIF, 6. Ord. 1456-2018 Funding Template

Explanation

 

1.0 BACKGROUND:  This legislation authorizes the Director of Public Utilities to enter into a construction contract with Kokosing Industrial, Inc. for the Hap Cremean Water Plant (HCWP) UV Disinfection Facility Project, Capital Improvements Project No. 690536-100000.

 

This project will install a new UV disinfection system at the HCWP to provide a multi-barrier disinfection process (provide both chemical and physical disinfection).  Work will include: modifications to filter face piping; installation of UV reactors on effluent piping of 24 filters; installation of UV power supply and control cabinets; electrical power distribution improvements, and other work as may be necessary to complete the contract, in accordance with the plans and specifications set forth in the Invitation For Bid.

 

Planning Area: “N/A” since the HCWP serves several communities.

 

2.0 ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT:  The addition of UV disinfection provides a multi-barrier treatment operation that improves public health protection by inactivating chlorine resistant microorganisms and other harmful pathogens.  Water quality provided by the City is essential to human health and economic growth and development.  There were no public meetings held regarding this work. HCWP is a secure facility and is not publically accessible. 

 

3.0 CONSTRUCTION CONTRACT AWARD:  The Director of Public Utilities publicly opened three (3) bids on May 2, 2018 from:

 

1.                     Kokosing Industrial, Inc.                     $14,539,450.00

2.                     Shook Construction Co.                     $16,623,825.00

3.                     Ulliman Schutte Construction                     $17,046,450.00

 

Kokosing Industrial, Inc.’s bid was deemed the lowest, best, most responsive and responsible bid in the amount of $14,539,450.00.  Their Contract Compliance Number is 47-2946608 (expires 3/10/2019, Majority) and their DAX Vendor No. is 012309.  Additional information regarding bidders, description of work, contract time frame and detailed amounts can be found on the attached Information form.

Searches in the Excluded Party List System (Federal) and the Findings for Recovery list (State) produced no findings against Kokosing Industrial, Inc.

 

3.1 PRE-QUALIFICATION STATUS: Kokosing Industrial, Inc. and all proposed subcontractors have met code requirements with respect to pre-qualification, pursuant to relevant sections of Columbus City Code Chapter 329.

 

4.0 FISCAL IMPACT:  This Ordinance authorizes the City Auditor to appropriate and transfer funds from the Water System Reserve Fund to the Water Supply Revolving Loan Account Fund in order to fund this proposed expenditure.  This transaction is a temporary measure that is required until such time as the Division is able to execute a loan with the Water Supply Revolving Loan Account Fund and reimburse the Water System Reserve Fund.  The loan is expected to be approved in June 2018.

 

 

Title

 

To authorize the Director of Public Utilities to enter into a construction contract with Kokosing Industrial, Inc. for the Hap Cremean Water Plant (HCWP) UV Disinfection Facility Project; to authorize the appropriation and transfer of $14,539,450.00 from the Water System Reserve Fund to the Water Supply Revolving Loan Account Fund; and to authorize the appropriation and expenditure of $14,539,450.00 from the Water Supply Revolving Loan Account Fund for the Division of Water.  ($14,539,450.00)

 

 

Body

 

WHEREAS, three (3) bids for the Hap Cremean Water Plant (HCWP) UV Disinfection Facility Project were received and publicly opened in the offices of the Director of Public Utilities on May 2, 2018; and

 

WHEREAS, the lowest, best, most responsive and responsible bid was from Kokosing Industrial, Inc. in the amount of $14,539,450.00; and

 

WHEREAS, it is necessary to authorize the Director of the Department of Public Utilities to enter into a construction contract for the Hap Cremean Water Plant (HCWP) UV Disinfection Facility Project; and

 

WHEREAS, it is necessary to both appropriate funds from the Water System Reserve Fund and to authorize the transfer of said funds into the Water Supply Revolving Loan Account Fund in order to temporarily fund this expenditure, until such time as the City is able to execute a loan for the above stated purpose and reimburse the Water System Reserve Fund; and

 

WHEREAS, the City anticipates incurring certain Original Expenditures (as defined in Section 1.150-2(c) of the Treasury Regulations (the “Treasury Regulations”) promulgated pursuant to the Internal Revenue Code of 1986, as amended) with respect to the construction of the Project described in this Ordinance (collectively, the “Project”); and

 

WHEREAS, it has become necessary in the usual daily operation of the Division of Water, Department of Public Utilities, to authorize the Director of Public Utilities to enter into a construction contract with Kokosing Industrial, Inc. for the Hap Cremean Water Plant (HCWP) UV Disinfection Facility Project, for the preservation of the public health, peace, property and safety; now, therefore

 

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:

 

SECTION 1.  That the Director of Public Utilities is hereby authorized to enter into a construction contract for the Hap Cremean Water Plant (HCWP) UV Disinfection Facility Project with Kokosing Industrial, Inc., 6235 Westerville Rd., Westerville, OH 43081 (FID# 47-2946608); in an amount up to $14,539,450.00; in accordance with the terms and conditions of the contract on file in the Office of the Division of Water.

 

SECTION 2.  That said construction company shall conduct the work to the satisfaction of the Director of Public Utilities and the Administrator of the Division of Water.

 

SECTION 3. That from the unappropriated monies and from all monies estimated to come into said fund from any and all sources and unappropriated for any other purpose during the fiscal year ended December 31, 2018, the sum of $14,539,450.00 is appropriated in Fund 6003 - Water System Reserve Fund, in Object Class 10 - Transfer Out Expenditure, per the account codes in the attachment to this ordinance.

 

SECTION 4. That the transfer of $14,539,450.00 or so much thereof as may be needed, is hereby authorized between Fund 6003 - Water System Reserve Fund and Fund 6011 - Water Supply Revolving Loan Account Fund, per the account codes in the attachment to this ordinance.

 

SECTION 5. That the appropriation and expenditure of $14,539,450.00 or so much thereof as may be needed, is hereby authorized in Fund 6011 - Water Supply Revolving Loan Account Fund, in Object Class 06 - Capital Outlay, per the accounting codes in the attachment to this ordinance.

 

SECTION 6.  That upon obtaining other funds for the purpose of funding water system capital improvement work, the City Auditor is hereby authorized to repay the Water System Reserve Fund the amount transferred under Section 5 above, and said funds are hereby deemed appropriated for such purpose.

 

SECTION 7.  That the City intends that this Ordinance constitute an "official intent" for purposes of Section 1.150-2(e) of the Treasury Regulations, and that the City reasonably expects to reimburse itself for certain Original Expenditures incurred with respect to the Project from the proceeds of obligations to be issued by the City in a principal amount currently estimated to be $14,539,450.00 (the "Obligations").

 

The City intends to make a reimbursement allocation on its books for the Original Expenditures not later than eighteen months following the later to occur of the date of the Original Expenditure to be reimbursed or the date the Project for which such Original Expenditures were made is "placed in service" within the meaning of Treasury Regulations Section 1.150-2(c).  Upon the issuance of the Obligations, the proceeds of such Obligations shall be used to reimburse the Water System Reserve Fund 6003, which is the fund from which the advance for costs of the Project will be made.

 

SECTION 8.  That the funds necessary to carry out the purpose of this Ordinance are hereby deemed appropriated, and the City Auditor shall establish such accounting codes as necessary.

 

SECTION 9.  That the City Auditor is hereby authorized and directed to transfer any unencumbered balance in the project account to the unallocated balance within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies no longer required for said project; except that no transfer shall be made from a project account by monies from more than one source.

 

SECTION 10.  That the City Auditor is authorized to establish proper project accounting numbers as appropriate.

 

SECTION 11.  That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this Ordinance.

 

SECTION 12.  That this Ordinance shall take effect and be in force from and after the earliest period allowed by law.