File #: 2359-2013    Version: 1
Type: Ordinance Status: Passed
File created: 9/30/2013 In control: Public Service & Transportation Committee
On agenda: 10/28/2013 Final action: 10/30/2013
Title: To amend the 2013 Capital Improvement Budget; to authorize the City Auditor to transfer cash and appropriation within the Streets and Highways Bond Fund; to authorize the Director of Public Service to enter into contract with Complete General Construction Company and to provide for the payment of construction administration and inspection services in connection with the Bridge Rehabilitation - Annual Citywide Contract 2013 project; to authorize the expenditure of up to $2,021,000.00 from the Streets and Highways Bonds Fund; and to declare an emergency. ($2,021,000.00)
Explanation
1.      BACKGROUND:
This legislation authorizes the Director of Public Service to enter into a contract for the construction of the Bridge Rehabilitation - Annual Citywide Contract 2013 project and to provide payment for construction administration and inspection services.  
 
The Bridge Rehabilitation - Annual Citywide Contract 2013 project consists of routine maintenance to several bridges within the City of Columbus.  Work includes crack sealing, concrete patching, tuck pointing, railing repairs, guardrail repairs, epoxy injection, maintenance of traffic, asphalt resurfacing, sealing of cracks in bridges, replacement of expansion joints, and other such work as may be necessary to complete the contract in accordance with the plans and specifications set forth in the Bid submittal documents.
 
The estimated Notice to Proceed date is November 14, 2013.  The project was let by the Office of Support Services through Vendor Services and Bid Express.  Three bids were received on September 24, 2013, (three majority) and tabulated as follows:   
      
Company Name                                        Bid Amount                   City/State            Majority/MBE/FBE     
Complete General Construction Co.        $1,197,526.51           Columbus, OH               Majority
Righter Co., Inc.                                       $1,389,300.00             Columbus, OH               Majority
Double Z Construction Company            $1,511,495.70               Columbus, OH               Majority
 
The bid documents contain Special Provision 146, which states, "It is the City's intent to fully utilize the available funding provided to its Bridge Program within the approved Capital Improvements Budget.  Therefore, the City reserves the right to increase or decrease the base contract amount, up to or down to a maximum of ($1,750,000.00).  The total amount of the work and other incidentals will not exceed the total amount of the contract price (maximum of $1,750,000.00).  In the event that the City does add bridges to the original list in order to use the remaining available funds, the contractor shall be bound by all bid specifications and other terms and conditions contained in the contract document.  The contract will be awarded to the lowest, best, responsive, responsible bidder per Columbus City Code Section 329 (determined by the base bid, not including additional funds to equal the maximum of ($1,750,000.00)."
 
Award is to be made to Complete General Construction Company as the lowest, responsive, responsible and best bidder for their bid of $1,197,526.51.  The contract amount will be for $1,750,000.00.
 
Searches in the System for Award Management (Federal) and the Findings for Recovery list (State) produced no findings against Complete General Construction Company.
 
2.  CONTRACT COMPLIANCE
The contract compliance number for Complete General Construction Company is 31-4366382 and expires 11/1/13.
 
3.  FISCAL IMPACT
Funding for this project is available within the Streets and Highways G.O. Bond Fund, No. 704.  A transfer of cash and budget authority is necessary to align funding with this project expenditure.
4. EMERGENCY DESIGNATION
Emergency action is requested in order for this project to commence as early as possible and perform necessary reconstruction to City bridges in need of rehabilitation this construction season.
 
Title
To amend the 2013 Capital Improvement Budget; to authorize the City Auditor to transfer cash and appropriation within the Streets and Highways Bond Fund; to authorize the Director of Public Service to enter into contract with Complete General Construction Company and to provide for the payment of construction administration and inspection services in connection with the Bridge Rehabilitation - Annual Citywide Contract 2013 project; to authorize the expenditure of up to $2,021,000.00 from the Streets and Highways Bonds Fund; and to declare an emergency. ($2,021,000.00)
 
Body
WHEREAS, the Division of Design and Construction is responsible for the construction and rehabilitation of bridges within the City of Columbus; and
 
WHEREAS,  it is necessary to enter into contract to provide rehabilitation of these City bridges as part of the Bridge Rehabilitation - Annual Citywide Contract 2013; and
 
WHEREAS, bids were received on September 24, 2013, and tabulated on September 25, 2013 for the Bridge Rehabilitation - Annual Citywide Contract 2013 project, and a satisfactory bid has been received; and
 
WHEREAS, it is necessary to provide for construction administration and inspection services; and
 
WHEREAS, it is necessary to authorize an amendment to the 2013 Capital Improvements Budget for the purpose of providing sufficient spending authority for the aforementioned project expenditure; and
 
WHEREAS, an emergency exists in the usual daily operation of the Division of Design and Construction in that the funding should be authorized immediately to perform necessary reconstruction to City bridges in need of rehabilitation and to maintain the project schedule, thereby preserving the public health, peace, property, safety and welfare; now, therefore
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
SECTION 1.  That the 2013 Capital Improvements Budget authorized by ordinance 0645-2013 be amended to provide sufficient authority in the appropriate project detail number for this project as follows:
Fund / Project / Project Name / Current C.I.B. / Change / C.I.B. as amended
704 / 530301-100000 / Bridge Rehabilitation (Voted 2008) / $2,475,043.00 / ($2,021,000.00) / $454,043.00
704 / 530301-160496 / Bridge Rehabilitation - Scioto Darby Executive Ct. (Voted 2008) / $0.00 / $18,984.00 / $18,984.00
704 / 530301-160135 / Bridge Rehabilitation - Cherry Creek Parkway Over Scioto Big Run (Voted 2008) / $0.00 / $35,871.00 / $35,871.00
704 / 530301-161972 / Bridge Rehabilitation - Little Avenue Over Whims Ditch East of Brown Road (Voted 2008) / $0.00 / $17,015.00 / $17,015.00
704 / 530301-162340 / Bridge Rehabilitation - Edwards Farm Road Over Hayden Run (Voted 2008) / $0.00 / $28,675.00 / $28,675.00
704 / 530301-163274 / Bridge Rehabilitation - Chapel Stone Road Over Dysar Creek (Voted 2008) / $0.00 / $14,338.00 / $14,338.00
704 / 530301-163681 / Bridge Rehabilitation - Neil Avenue under Railroad (Voted 2008) / $0.00 / $40,952.00 / $40,952.00
704 / 530301-160445 / Bridge Rehabilitation - Overbrook Drive Over Adena Brook (Voted 2008) / $0.00 / $15,640.00 / $15,640.00
704 / 530301-160585 / Bridge Rehabilitation - Maclam Drive Over Ditch (Voted 2008) / $0.00 / $22,135.00 / $22,135.00
704 / 530301-160534 / Bridge Rehabilitation - Maclam Drive Over Dry Run #1 North of Fisher Road (Voted 2008) / $0.00 / $37,368.00 / $37,368.00
704 / 530301-160291 / Bridge Rehabilitation - Fisher Road Over Stream #2 West of Wilson (Voted 2008) / $0.00 / $15,772.00 / $15,772.00
704 / 530301-162685 / Bridge Rehabilitation - Vanelm Street Over Ditch (Voted 2008) / $0.00 / $11,791.00 / $11,791.00
704 / 530301-163894 / Bridge Rehabilitation - Crete Lane Over Ditch (Voted 2008) / $0.00 / $15,169.00 / $15,169.00
704 / 530301-163509 / Bridge Rehabilitation - New Albany Road West Over Stream (Voted 2008) / $0.00 / $24,587.00 / $24,587.00
704 / 530301-163568 / Bridge Rehabilitation - New Albany Road West (o) Stream (Voted 2008) / $0.00 / $23,932.00 / $23,932.00
704 / 530301-163452 / Bridge Rehabilitation - New Albany Road West Over Stream Northwest of New Albany (Voted 2008) / $0.00 / $39,100.00 / $39,100.00
704 / 530301-163703 / Bridge Rehabilitation - Briarmeadow Drive Over Stream (Voted 2008) / $0.00 / $17,290.00 / $17,290.00
704 / 530301-162677 / Bridge Rehabilitation - Linworth Road Over Stream (Voted 2008) / $0.00 / $19,409.00 / $19,409.00
704 / 530301-160361 / Bridge Rehabilitation - McKinley Avenue Over Dry Run (Voted 2008) / $0.00 / $28,272.00 / $28,272.00
704 / 530301-163010 / Bridge Rehabilitation - Souder Avenue Over Scioto River (Voted 2008) / $0.00 / $30,779.00 / $30,779.00
704 / 530301-160224 / Bridge Rehabilitation - Groveport Road Over C&O Railroad North of Williams Road (Voted 2008) / $0.00 / $19,838.00 / $19,838.00
704 / 530301-163371 / Bridge Rehabilitation - Chatterton Road Over Blacklick Creek (Voted 2008) / $0.00 / $18,693.00 / $18,693.00
704 / 530301-161603 / Bridge Rehabilitation - Groves Road Over Mason Run East of Courtright Road (Voted 2008) / $0.00 / $14,842.00 / $14,842.00
704 / 530301-161441 / Bridge Rehabilitation - McAllister Over Hamilton Miller Ditch (Voted 2008) / $0.00 / $25,190.00 / $25,190.00
704 / 530301-163800 / Bridge Rehabilitation - Argyle Drive Over Ditch (Voted 2008) / $0.00 / $24,691.00 / $24,691.00
704 / 530301-163770 / Bridge Rehabilitation - Brentnell Boulevard Over Ditch (Voted 2008) / $0.00 / $20,613.00 / $20,613.00
704 / 530301-163657 / Bridge Rehabilitation - Lonsdale North of Livingston (Voted 2008) / $0.00 / $14,668.00 / $14,668.00
704 / 530301-162014 / Bridge Rehabilitation - McNaughten Road Over Ditch (Voted 2008) / $0.00 / $11,845.00 / $11,845.00
704 / 530301-163193 / Bridge Rehabilitation - Park Road Over Ditch (Voted 2008) / $0.00 / $17,055.00 / $17,055.00
704 / 530301-161670 / Bridge Rehabilitation - Fifth Avenue Over Mason Run East of Stelzer (Voted 2008) / $0.00 / $27,014.00 / $27,014.00
704 / 530301-160992 / Bridge Rehabilitation - Indianola Avenue Over Iuka Avenue (Voted 2008) / $0.00 / $16,577.00 / $16,577.00
704 / 530301-161891 / Bridge Rehabilitation - Overbrook Drive Over Adena Brook #3 East of High Street (Voted 2008) / $0.00 / $26,421.00 / $26,421.00
704 / 530301-162138 / Bridge Rehabilitation - Overbrook Drive Over Creek #1 West of Indianola (Voted 2008) / $0.00 / $15,180.00 / $15,180.00
704 / 530301-163517 / Bridge Rehabilitation - High Street Over Adena Brook (Voted 2008) / $0.00 / $54,510.00 / $54,510.00
704 / 530301-161832 / Bridge Rehabilitation - Roberts Road Over Conrail (Voted 2008) / $0.00 / $274,170.00 / $274,170.00
704 / 530301-100067 / Bridge Rehabilitation - Citywide (Voted 2008) / $0.00 / $982,617.00 / $982,617.00
 
SECTION 2.  That the transfer of cash and appropriation within the Streets and Highways G.O. Bond Fund, 704 be authorized as follow:
 
Transfer from:
Fund / Project / Project Name / O.L. 01-03 Codes / OCA / Amount
704 / 530301-100000 / Bridge Rehabilitation / 06-6600 / 591142 / $2,021,000.00
 
Transfer to:
Fund / Project / Project Name / O.L. 01-03 Codes / OCA / Amount
704 / 530301-160496 / Bridge Rehabilitation - Scioto Darby Executive Ct. (Voted 2008) / 06-6600 / 743196 / $18,984.00
704 / 530301-160135 / Bridge Rehabilitation - Cherry Creek Parkway Over Scioto Big Run (Voted 2008) / 06-6600 / 731135 / $35,871.00
704 / 530301-161972 / Bridge Rehabilitation - Little Avenue Over Whims Ditch East of Brown Road (Voted 2008) / 06-6600 / 743172 / $17,015.00
704 / 530301-162340 / Bridge Rehabilitation - Edwards Farm Road Over Hayden Run (Voted 2008) / 06-6600 / 743140 / $28,675.00
704 / 530301-163274 / Bridge Rehabilitation - Chapel Stone Road Over Dysar Creek (Voted 2008) / 06-6600 / 743174 / $14,337.52
704 / 530301-163681 / Bridge Rehabilitation - Neil Avenue under Railroad (Voted 2008) / 06-6600 / 743181 / $40,952.00
704 / 530301-160445 / Bridge Rehabilitation - Overbrook Drive Over Adena Brook (Voted 2008) / 06-6600 / 743445 / $15,640.00
704 / 530301-160585 / Bridge Rehabilitation - Maclam Drive Over Ditch (Voted 2008) / 06-6600 / 743585 / $22,135.00
704 / 530301-160534 / Bridge Rehabilitation - Maclam Drive Over Dry Run #1 North of Fisher Road (Voted 2008) / 06-6600 / 743134 / $37,368.00
704 / 530301-160291 / Bridge Rehabilitation - Fisher Road Over Stream #2 West of Wilson (Voted 2008) / 06-6600 / 743191 / $15,771.72
704 / 530301-162685 / Bridge Rehabilitation - Vanelm Street Over Ditch (Voted 2008) / 06-6600 / 743185 / $11,790.48
704 / 530301-163894 / Bridge Rehabilitation - Crete Lane Over Ditch (Voted 2008) / 06-6600 / 743194 / $15,169.00
704 / 530301-163509 / Bridge Rehabilitation - New Albany Road West Over Stream (Voted 2008) / 06-6600 / 743109 / $24,587.00
704 / 530301-163568 / Bridge Rehabilitation - New Albany Road West (o) Stream (Voted 2008) / 06-6600 / 743168 / $23,932.00
704 / 530301-163452 / Bridge Rehabilitation - New Albany Road West Over Stream Northwest of New Albany (Voted 2008) / 06-6600 / 743152 / $39,100.00
704 / 530301-163703 / Bridge Rehabilitation - Briarmeadow Drive Over Stream (Voted 2008) / 06-6600 / 743703 / $17,289.28
704 / 530301-162677 / Bridge Rehabilitation - Linworth Road Over Stream (Voted 2008) / 06-6600 / 743177 / $19,408.96
704 / 530301-160361 / Bridge Rehabilitation - McKinley Avenue Over Dry Run (Voted 2008) / 06-6600 / 743361 / $28,272.00
704 / 530301-163010 / Bridge Rehabilitation - Souder Avenue Over Scioto River (Voted 2008) / 06-6600 / 731010 / $30,779.00
704 / 530301-160224 / Bridge Rehabilitation - Groveport Road Over C&O Railroad North of Williams Road (Voted 2008) / 06-6600 / 743124 / $19,838.00
704 / 530301-163371 / Bridge Rehabilitation - Chatterton Road Over Blacklick Creek (Voted 2008) / 06-6600 / 743171 / $18,693.00
704 / 530301-161603 / Bridge Rehabilitation - Groves Road Over Mason Run East of Courtright Road (Voted 2008) / 06-6600 / 743603 / $14,842.00
704 / 530301-161441 / Bridge Rehabilitation - McAllister Over Hamilton Miller Ditch (Voted 2008) / 06-6600 / 731441 / $25,190.00
704 / 530301-163800 / Bridge Rehabilitation - Argyle Drive Over Ditch (Voted 2008) / 06-6600 / 743800 / $24,691.00
704 / 530301-163770 / Bridge Rehabilitation - Brentnell Boulevard Over Ditch (Voted 2008) / 06-6600 / 731770 / $20,613.00
704 / 530301-163657 / Bridge Rehabilitation - Lonsdale North of Livingston (Voted 2008) / 06-6600 / 731657 / $14,667.88
704 / 530301-162014 / Bridge Rehabilitation - McNaughten Road Over Ditch (Voted 2008) / 06-6600 / 743114 / $11,845.00
704 / 530301-163193 / Bridge Rehabilitation - Park Road Over Ditch (Voted 2008) / 06-6600 / 743193 / $17,055.00
704 / 530301-161670 / Bridge Rehabilitation - Fifth Avenue Over Mason Run East of Stelzer (Voted 2008) / 06-6600 / 743170 / $27,014.00
704 / 530301-160992 / Bridge Rehabilitation - Indianola Avenue Over Iuka Avenue (Voted 2008) / 06-6600 / 743192 / $16,576.88
704 / 530301-161891 / Bridge Rehabilitation - Overbrook Drive Over Adena Brook #3 East of High Street (Voted 2008) / 06-6600 / 743891 / $26,421.00
704 / 530301-162138 / Bridge Rehabilitation - Overbrook Drive Over Creek #1 West of Indianola (Voted 2008) / 06-6600 / 743138 / $15,180.00
704 / 530301-163517 / Bridge Rehabilitation - High Street Over Adena Brook (Voted 2008) / 06-6600 / 743117 / $54,510.00
704 / 530301-161832 / Bridge Rehabilitation - Roberts Road Over Conrail (Voted 2008) / 06-6600 / 743132 / $274,169.60
704 / 530301-100067 / Bridge Rehabilitation - Citywide (Voted 2008) / 06-6600 / 743167 / $982,616.68
 
SECTION 3.  That the Director of Public Service be and is hereby authorized to enter into contract with Complete General Construction Company, 1221 E. Fifth Avenue, Columbus, Ohio 43219, for the construction of the Bridge Rehabilitation - Annual Citywide Contract 2013 project in the amount of $1,750,000.00 or so much thereof as may be needed in accordance with the specifications and plans on file in the Office of Support Services, which are hereby approved; and to obtain and pay for the necessary inspection costs associated with the project up to a maximum of $271,000.00.  
 
SECTION 4.  That for the purpose of paying the cost of the contract and inspection, the sum of up to $2,021,000.00 or so much thereof as may be needed, is hereby authorized to be expended from the Streets and Highways G.O. Bonds Fund, No. 704,  for the Division of Design and Construction, Dept.-Div. 59-12
Contract - $1,750,000.00
Fund / Project / Project Name / O.L. 01-03 Codes / OCA / Amount
704 / 530301-160496 / Bridge Rehabilitation - Scioto Darby Executive Ct. (Voted 2008) / 06-6631 / 743196 / $16,508.00
704 / 530301-160135 / Bridge Rehabilitation - Cherry Creek Parkway Over Scioto Big Run (Voted 2008) / 06-6631 / 731135 / $31,192.00
704 / 530301-161972 / Bridge Rehabilitation - Little Avenue Over Whims Ditch East of Brown Road (Voted 2008) / 06-6631 / 743172 / $14,796.00
704 / 530301-162340 / Bridge Rehabilitation - Edwards Farm Road Over Hayden Run (Voted 2008) / 06-6631 / 743140 / $24,935.00
704 / 530301-163274 / Bridge Rehabilitation - Chapel Stone Road Over Dysar Creek (Voted 2008) / 06-6631 / 743174 / $12,467.52
704 / 530301-163681 / Bridge Rehabilitation - Neil Avenue under Railroad (Voted 2008) / 06-6631 / 743181 / $35,610.00
704 / 530301-160445 / Bridge Rehabilitation - Overbrook Drive Over Adena Brook (Voted 2008) / 06-6631 / 743445 / $13,600.00
704 / 530301-160585 / Bridge Rehabilitation - Maclam Drive Over Ditch (Voted 2008) / 06-6631 / 743585 / $19,248.00
704 / 530301-160534 / Bridge Rehabilitation - Maclam Drive Over Dry Run #1 North of Fisher Road (Voted 2008) / 06-6631 / 743134 / $32,494.00
704 / 530301-160291 / Bridge Rehabilitation - Fisher Road Over Stream #2 West of Wilson (Voted 2008) / 06-6631 / 743191 / $13,714.72
704 / 530301-162685 / Bridge Rehabilitation - Vanelm Street Over Ditch (Voted 2008) / 06-6631 / 743185 / $10,252.48
704 / 530301-163894 / Bridge Rehabilitation - Crete Lane Over Ditch (Voted 2008) / 06-6631 / 743194 / $13,190.00
704 / 530301-163509 / Bridge Rehabilitation - New Albany Road West Over Stream (Voted 2008) / 06-6631 / 743109 / $21,380.00
704 / 530301-163568 / Bridge Rehabilitation - New Albany Road West (o) Stream (Voted 2008) / 06-6631 / 743168 / $20,810.00
704 / 530301-163452 / Bridge Rehabilitation - New Albany Road West Over Stream Northwest of New Albany (Voted 2008) / 06-6631 / 743152 / $34,000.00
704 / 530301-163703 / Bridge Rehabilitation - Briarmeadow Drive Over Stream (Voted 2008) / 06-6631 / 743703 / $15,034.28
704 / 530301-162677 / Bridge Rehabilitation - Linworth Road Over Stream (Voted 2008) / 06-6631 / 743177 / $16,876.96
704 / 530301-160361 / Bridge Rehabilitation - McKinley Avenue Over Dry Run (Voted 2008) / 06-6631 / 743361 / $24,584.00
704 / 530301-163010 / Bridge Rehabilitation - Souder Avenue Over Scioto River (Voted 2008) / 06-6631 / 731010 / $26,764.00
704 / 530301-160224 / Bridge Rehabilitation - Groveport Road Over C&O Railroad North of Williams Road (Voted 2008) / 06-6631 / 743124 / $17,250.00
704 / 530301-163371 / Bridge Rehabilitation - Chatterton Road Over Blacklick Creek (Voted 2008) / 06-6631 / 743171 / $16,255.00
704 / 530301-161603 / Bridge Rehabilitation - Groves Road Over Mason Run East of Courtright Road (Voted 2008) / 06-6631 / 743603 / $12,906.00
704 / 530301-161441 / Bridge Rehabilitation - McAllister Over Hamilton Miller Ditch (Voted 2008) / 06-6631 / 731441 / $21,904.00
704 / 530301-163800 / Bridge Rehabilitation - Argyle Drive Over Ditch (Voted 2008) / 06-6631 / 743800 / $21,470.00
704 / 530301-163770 / Bridge Rehabilitation - Brentnell Boulevard Over Ditch (Voted 2008) / 06-6631 / 731770 / $17,924.00
704 / 530301-163657 / Bridge Rehabilitation - Lonsdale North of Livingston (Voted 2008) / 06-6631 / 731657 / $12,754.88
704 / 530301-162014 / Bridge Rehabilitation - McNaughten Road Over Ditch (Voted 2008) / 06-6631 / 743114 / $10,300.00
704 / 530301-163193 / Bridge Rehabilitation - Park Road Over Ditch (Voted 2008) / 06-6631 / 743193 / $14,830.00
704 / 530301-161670 / Bridge Rehabilitation - Fifth Avenue Over Mason Run East of Stelzer (Voted 2008) / 06-6631 / 743170 / $23,490.00
704 / 530301-160992 / Bridge Rehabilitation - Indianola Avenue Over Iuka Avenue (Voted 2008) / 06-6631 / 743192 / $14,414.88
704 / 530301-161891 / Bridge Rehabilitation - Overbrook Drive Over Adena Brook #3 East of High Street (Voted 2008) / 06-6631 / 743891 / $22,975.00
704 / 530301-162138 / Bridge Rehabilitation - Overbrook Drive Over Creek #1 West of Indianola (Voted 2008) / 06-6631 / 743138 / $13,200.00
704 / 530301-163517 / Bridge Rehabilitation - High Street Over Adena Brook (Voted 2008) / 06-6631 / 743117 / $47,400.00
704 / 530301-161832 / Bridge Rehabilitation - Roberts Road Over Conrail (Voted 2008) / 06-6631 / 743132 / $238,408.60
704 / 530301-100067 / Bridge Rehabilitation - Citywide (Voted 2008) / 06-6631 / 743167 / $847,060.68
 
Inspection - $271,000.00
Fund / Project / Project Name / O.L. 01-03 Codes / OCA / Amount
704 / 530301-160496 / Bridge Rehabilitation - Scioto Darby Executive Ct. (Voted 2008) / 06-6687
/ 743196 / $2,476.00
704 / 530301-160135 / Bridge Rehabilitation - Cherry Creek Parkway Over Scioto Big Run (Voted 2008) / 06-6687 / 731135 / $4,679.00
704 / 530301-161972 / Bridge Rehabilitation - Little Avenue Over Whims Ditch East of Brown Road (Voted 2008) / 06-6687 / 743172 / $2,219.00
704 / 530301-162340 / Bridge Rehabilitation - Edwards Farm Road Over Hayden Run (Voted 2008) / 06-6687 / 743140 / $3,740.00
704 / 530301-163274 / Bridge Rehabilitation - Chapel Stone Road Over Dysar Creek (Voted 2008) / 06-6687 / 743174 / $1,870.00
704 / 530301-163681 / Bridge Rehabilitation - Neil Avenue under Railroad (Voted 2008) / 06-6687 / 743181 / $5,342.00
704 / 530301-160445 / Bridge Rehabilitation - Overbrook Drive Over Adena Brook (Voted 2008) / 06-6687 / 743445 / $2,040.00
704 / 530301-160585 / Bridge Rehabilitation - Maclam Drive Over Ditch (Voted 2008) / 06-6687 / 743585 / $2,887.00
704 / 530301-160534 / Bridge Rehabilitation - Maclam Drive Over Dry Run #1 North of Fisher Road (Voted 2008) / 06-6687 / 743134 / $4,874.00
704 / 530301-160291 / Bridge Rehabilitation - Fisher Road Over Stream #2 West of Wilson (Voted 2008) / 06-6687 / 743191 / $2,057.00
704 / 530301-162685 / Bridge Rehabilitation - Vanelm Street Over Ditch (Voted 2008) / 06-6687 / 743185 / $1,538.00
704 / 530301-163894 / Bridge Rehabilitation - Crete Lane Over Ditch (Voted 2008) / 06-6687 / 743194 / $1,979.00
704 / 530301-163509 / Bridge Rehabilitation - New Albany Road West Over Stream (Voted 2008) / 06-6687 / 743109 / $3,207.00
704 / 530301-163568 / Bridge Rehabilitation - New Albany Road West (o) Stream (Voted 2008) / 06-6687 / 743168 / $3,122.00
704 / 530301-163452 / Bridge Rehabilitation - New Albany Road West Over Stream Northwest of New Albany (Voted 2008) / 06-6687 / 743152 / $5,100.00
704 / 530301-163703 / Bridge Rehabilitation - Briarmeadow Drive Over Stream (Voted 2008) / 06-6687 / 743703 / $2,255.00
704 / 530301-162677 / Bridge Rehabilitation - Linworth Road Over Stream (Voted 2008) / 06-6687 / 743177 / $2,532.00
704 / 530301-160361 / Bridge Rehabilitation - McKinley Avenue Over Dry Run (Voted 2008) / 06-6687 / 743361 / $3,688.00
704 / 530301-163010 / Bridge Rehabilitation - Souder Avenue Over Scioto River (Voted 2008) / 06-6687 / 731010 / $4,015.00
704 / 530301-160224 / Bridge Rehabilitation - Groveport Road Over C&O Railroad North of Williams Road (Voted 2008) / 06-6687 / 743124 / $2,588.00
704 / 530301-163371 / Bridge Rehabilitation - Chatterton Road Over Blacklick Creek (Voted 2008) / 06-6687 / 743171 / $2,438.00
704 / 530301-161603 / Bridge Rehabilitation - Groves Road Over Mason Run East of Courtright Road (Voted 2008) / 06-6687 / 743603 / $1,936.00
704 / 530301-161441 / Bridge Rehabilitation - McAllister Over Hamilton Miller Ditch (Voted 2008) / 06-6687 / 731441 / $3,286.00
704 / 530301-163800 / Bridge Rehabilitation - Argyle Drive Over Ditch (Voted 2008) / 06-6687 / 743800 / $3,221.00
704 / 530301-163770 / Bridge Rehabilitation - Brentnell Boulevard Over Ditch (Voted 2008) / 06-6687 / 731770 / $2,689.00
704 / 530301-163657 / Bridge Rehabilitation - Lonsdale North of Livingston (Voted 2008) / 06-6687 / 731657 / $1,913.00
704 / 530301-162014 / Bridge Rehabilitation - McNaughten Road Over Ditch (Voted 2008) / 06-6687 / 743114 / $1,545.00
704 / 530301-163193 / Bridge Rehabilitation - Park Road Over Ditch (Voted 2008) / 06-6687 / 743193 / $2,225.00
704 / 530301-161670 / Bridge Rehabilitation - Fifth Avenue Over Mason Run East of Stelzer (Voted 2008) / 06-6687 / 743170 / $3,524.00
704 / 530301-160992 / Bridge Rehabilitation - Indianola Avenue Over Iuka Avenue (Voted 2008) / 06-6687 / 743192 / $2,162.00
704 / 530301-161891 / Bridge Rehabilitation - Overbrook Drive Over Adena Brook #3 East of High Street (Voted 2008) / 06-6687 / 743891 / $3,446.00
704 / 530301-162138 / Bridge Rehabilitation - Overbrook Drive Over Creek #1 West of Indianola (Voted 2008) / 06-6687 / 743138 / $1,980.00
704 / 530301-163517 / Bridge Rehabilitation - High Street Over Adena Brook (Voted 2008) / 06-6687 / 743117 / $7,110.00
704 / 530301-161832 / Bridge Rehabilitation - Roberts Road Over Conrail (Voted 2008) / 06-6687 / 743132 / $35,761.00
704 / 530301-100067 / Bridge Rehabilitation - Citywide (Voted 2008) / 06-6687 / 743167 / $135,556.00
 
SECTION 5.  That the funds necessary to carry out the purpose of this ordinance are hereby deemed appropriated, and the City Auditor shall establish such accounting codes as necessary.
 
SECTION 6.  That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this ordinance.
 
SECTION 7.  That the City Auditor is hereby authorized to transfer the unencumbered balance in a project account to the unallocated balance account within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies are no longer required for said project.
 
SECTION 8.  That for the reasons stated in the preamble hereto, which is hereby made a part hereof, this ordinance is hereby declared to be an emergency measure and shall take effect and be in force from and after its passage and approval by the mayor, or ten days after passage if the mayor neither approves nor vetoes the same.