Explanation
Bids were received by the Recreation and Parks Department on August 24th, 2010 for the Linden Park Shelter Project, as follows:
Status Bid Amount
Builderscape, Inc. MAJ $119,613.00
Meticulous Landscaping MBE $133,600.00
Williamson Builders MBE $136,708.00
Janco, LLC MAJ $139,230.00
ProCon MAJ $151,532.00
Wingler Construction MAJ $152,616.00
Central Ohio Building MAJ $159,300.00
Gutknecht Construction MAJ $185,800.00
Project work consists of :
Base Bid - the supply and installation of a 55'x 35' park shelter, 59' x 39' concrete pad and base, masonry columns and end arches, metal roof and concrete walk with base materials.
Alternate #1 - additional tree planting, staking & maintenance
Alternate #2 - add/deduct for use of manufactured stone for columns and end arches rather than reclaimed stone from original shelter.
The Contract Compliance Number for Builderscape, LLC is #20-0537419.
Contract compliant through: 7/13/2011
Financial Impact:
$131,000.00
Voted Recreation & Parks Bond Fund, Fund 746, Gov't B.A.B.S. (Build America Bonds)
Title
To authorize and direct the Director of Recreation and Parks to enter into contract with Builderscape, Inc. for the Linden Park Shelter Project, to authorize the expenditure of Base Bid $119,613.00 and a contingency of $11,387.00 for a total of $131,000.00 from the Voted Recreation and Parks Bond Fund, Fund 746 Gov't B.A.B.S. (Build America Bonds) and to declare an emergency. ($131,000.00)
Body
WHEREAS, bids were received by the Recreation and Parks Department on August 24th, 2010, and the contract for the Linden Park Shelter Project 2010 was awarded to the lowest bidder; and
WHEREAS, it is necessary to enter into contract with Builderscape, Inc. for the Linden Park Shelter Project 2010; and
WHEREAS, an emergency exists in the usual daily operation of the Recreation and Parks Department in that it is immediately necessary to expend said funds to ensure improvements proceed in a timely manner; now, therefore
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
SECTION 1. That the Director of Recreation and Parks is hereby authorized to enter into contract with Builderscape, Inc. for the Linden Park Shelter Project 2010; and
SECTION 2. That the expenditure of $131,000.00, or so much thereof may be necessary, be and is hereby authorized from:
Recreation and Parks Voted Bond Fund
Fund # 746, Project #510035-100045, Facility Shelter Renovations, OCA763545, Obj Level 3# 6620
SECTION 3. That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this legislation.
SECTION 4. That for the reasons stated in the preamble hereto, which is hereby made a part hereof, this ordinance is hereby declared to be an emergency measure and shall take effect and be in force from and after its passage and approval by the Mayor, or 10 days after passage if the Mayor neither approves or vetoes the same.