File #: 2996-2024    Version: 1
Type: Ordinance Status: Passed
File created: 10/25/2024 In control: Public Utilities & Sustainability Committee
On agenda: 12/9/2024 Final action: 12/11/2024
Title: To authorize the Director of the Department of Public Utilities to enter into a construction contract with Danbert Electrical Corporation for the UIRF Franklinton Active Parkways Lighting project; to amend the 2024 Capital Improvement Budget; and to authorize the expenditure of up to $275,427.20 for the project. ($275,427.20)
Indexes: MBE Participation, WBE Participation
Attachments: 1. ORD 2996-2024 Map, 2. ORD 2996-2024 Accounting Template, 3. ORD 2996-2024 Utilization

Explanation

1.  BACKGROUND

This ordinance authorizes the Director of Public Utilities to enter into a construction contract with Danbert Electrical Corporation, via the City’s Invitation For Bid process, for the UIRF Franklinton Active Parkways Lighting project, CIP #440007-102231, in an amount up to $273,427.20, and to encumber funds with the Department of Public Service for prevailing wage services in an amount up to $2,000.00, for a total expenditure of $275,427.20.

 

The lighting improvements consist of the installation of pedestrian scale lighting along both sides of the median parks on Dakota Avenue from Rich Street to State Street, and Guilford Street from the first alley north of Broad Street to the second alley north of Broad Street, using post top fiberglass poles with acorn LED luminaires.

 

This work occurs in the Franklinton community, which is planning area (54).

 

TIMELINE:  Contract work is required to be completed in a manner acceptable to the City within 180 days from the date that a Notice to Proceed (NTP) is given by the City. Allowing 3 months for the legislation and execution process, estimated construction would begin in January of 2025 and be completed by July of 2025.  

 

ESTIMATED COST OF PROJECT:  The bid amount and proposed award amount is $273,427.20, including a 10% construction contingency amount that will be utilized to fund needed and approved changes in the work.  No contract modifications are anticipated at this time; however, construction exigency might later compel modification of this contract, if unforeseen difficulties are encountered.

 

Cost summary:

 

                     Original Contract                                               $           273,427.20

                     Future Anticipated Needs                          $                    0.00

                     Prevailing Wage Charge                          $                              2,000.00

CONTRACT TOTAL                                               $           275,427.20

                                                                                     

 

2.  ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT

The installation and conversion to LED lighting within the project area would provide both an additional sense of safety and security to the residents.  This may also deter criminal activity, which would lessen the financial impact on city resources such as the Police and Fire departments.  

 

3.  BID INFORMATION

This project was formally advertised on the Vendor Services and Bid Express websites from 9/10/2024 through 10/9/24.   Three bids were received:

 

     Name                                           Bid Amount_______    _     City/State                        Status                    

Danbert Electrical Corporation                                $273,427.20                                    Plain City, OH                                 MAJ

Complete General Construction                                $319,750.03                      Columbus, OH                        MAJ                     

U.S. Utility Contractor                                                       $362,447.60                      Hilliard, OH                            MAJ

 

The Danbert Electrical Corporation’s bid was evaluated and deemed the lowest, best, most responsive bid.  Danbert Electrical Corporation’s certification was in good standing at the time of the contract award.

 

4.  CONTRACT COMPLIANCE INFORMATION

Danbert Electrical Corporation’s contract compliance number is CC023222 and expires 6/29/25. 

 

5.  MINORITY AND WOMAN OWNED BUSINESS ENTERPRISE & SMALL LOCAL BUSINESS ENTERPRISE PROGRAM

This contract was bid with an anticipated City of Columbus MBE/WBE Program goal of 10% as assigned by the City’s Office of Diversity and Inclusion (ODI).  The low bidder, Danbert Electrical Corporation, submitted a Utilization Plan meeting the 10% goal.  After review of their Utilization Plan and other related information the contractor submitted with their bid response, ODI has approved an MBE/WBE Program goal of 10% for this contract.  Failure by the contractor to meet this goal subjects the contractor to the Penalties for Non-Compliance as described in the bid documents for this contract.

 

As part of their proposal, Danbert Electrical Corporation, has proposed the following four subcontractors to perform contract work:

 

Company Name                                            City/State                                     ODI Certification Status

Garcia Surveyors                                        Columbus, Ohio                                                 MBE

Danbert, Inc.                                               Plain City, Ohio                                                 MAJ

Green Sytems                                                                                          Columbus, Ohio                                                 WBE

 

The certification of the above companies was in good standing at the time the bid was awarded.

 

6. PRE-QUALIFICATION STATUS

Construction pre-qualification is not required for this contract as the construction estimate was under $500,000.00.

 ,

7.  FISCAL IMPACT

Funding in the amount of $275,427.20 is available and appropriated within the Electricity Bond Fund, Fund 6303.  The 2024 Capital Improvement Budget must be amended to align budget authority with the proper project. 

 

Title

To authorize the Director of the Department of Public Utilities to enter into a construction contract with Danbert Electrical Corporation for the UIRF Franklinton Active Parkways Lighting project; to amend the 2024 Capital Improvement Budget; and to authorize the expenditure of up to $275,427.20 for the project.  ($275,427.20)

 

Body

WHEREAS, the Department of Public Utilities is engaged in the UIRF Franklinton Active Parkways Lighting project, CIP #440007-102231; and

 

WHEREAS, three bids for the UIRF Franklinton Active Parkways Lighting project were received and opened on 10/9/2024; and

 

WHEREAS, the bid from Danbert Electrical Corporation was evaluated and deemed the lowest, best, most responsive bid; and

 

WHEREAS, it is necessary to amend the 2024 Capital Improvement Budget to align budget authority with the proper project; and

 

WHEREAS, it is necessary to authorize the Director of the Department of Public Utilities to enter into a construction services contract with Danbert Electrical Corporation for the UIRF Franklinton Active Parkways Lighting project; and

 

WHEREAS, it is necessary to expend funds to pay for this project; now, therefore,

 

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:

 

SECTION 1.  That the 2024 Capital Improvement Budget authorized by Ordinance 1907-2024 be amended as follows to establish sufficient budget authority for this project:

 

Fund / Project Number / Project Name (Funding Source) / Current Authority / Revised Authority / Change

6303 / 440007-100000 / UIRF Funded Street Lighting Projects (Urban Infrastructure Recovery Fund) (Voted Electricity Carryover) / $1,515,689.00 / $1,240,262.00 / ($275,427.00)

6303 / 440007-102231 / UIRF Franklinton Active Parkways Lighting (Voted Electricity Carryover) / $73,325.00 / $348,752.00 / $275,427.00

 

SECTION 2.  That the Director of Public Utilities is hereby authorized to enter into a construction services contract for the UIRF Franklinton Active Parkways Lighting project with Danbert Electrical Corporation, 7991 Memorial Drive, Plain City, Ohio 43064, in an amount up to $273,427.20, in accordance with the terms and conditions of the contract on file in the Department of Public Utilities; and to encumber funds in an amount up to $2,000.00 with the Department of Public Service to provide prevailing wage services for the project.

 

SECTION 3.  That the expenditure of up to $275,427.20, or so much thereof as may be needed, is hereby authorized from the Electricity Bond Fund, Fund 6303, per the accounting codes in the attachment to this ordinance.

 

SECTION 4.  Funds are hereby deemed appropriated and expenditures and transfers authorized to carry out the purposes of this ordinance and the City Auditor shall establish such accounting codes as necessary.

 

SECTION 5.  That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this ordinance.

 

SECTION 6.  That the City Auditor is hereby authorized to transfer the unencumbered balance in a project account to the unallocated balance account within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies are no longer required for said project.

 

SECTION 7.  That this ordinance shall take effect and be in force from and after the earliest period allowed by law.