File #: 0623-2007    Version: 1
Type: Ordinance Status: Passed
File created: 4/11/2007 In control: Public Service & Transportation Committee
On agenda: 6/4/2007 Final action: 6/11/2007
Title: To authorize the Director of Public Service to enter into a contract for the Transportation Division with Strawser Paving Company for construction of West Edge Business Center Roadway Resurfacing project; to authorize the expenditure $224,291.92 from the Voted 1995, 1999, 2004 Streets and Highways Fund and $125,902.78 from the Northland and Other Acquisitions Fund; to amend the 2007 CIB; and to declare an emergency. ($350,194.70)
Attachments: 1. UIRF_West_Edge_Business_Center_Roadway_Resurfacing_map.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
6/11/20071 CITY CLERK Attest  Action details Meeting details
6/8/20071 MAYOR Signed  Action details Meeting details
6/4/20071 Columbus City Council ApprovedPass Action details Meeting details
6/4/20071 COUNCIL PRESIDENT Signed  Action details Meeting details
5/17/20071 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
5/17/20071 Service Reviewer Sent for Approval  Action details Meeting details
5/17/20071 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
5/17/20071 Service Reviewer Sent to Clerk's Office for Council  Action details Meeting details
5/16/20071 EBOCO Reviewer Reviewed and Approved  Action details Meeting details
5/15/20071 Auditor Reviewer Reviewed and Approved  Action details Meeting details
5/15/20071 CITY AUDITOR Reviewed and Approved  Action details Meeting details
5/15/20071 Service Reviewer Sent for Approval  Action details Meeting details
5/14/20071 Finance Reviewer Reviewed and Approved  Action details Meeting details
5/14/20071 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
5/14/20071 Service Reviewer Sent for Approval  Action details Meeting details
5/11/20071 Finance Reviewer Reviewed and Approved  Action details Meeting details
5/8/20071 Finance Reviewer Reviewed and Approved  Action details Meeting details
5/7/20071 SERVICE DIRECTOR Reviewed and Approved  Action details Meeting details
5/3/20071 Service Reviewer Reviewed and Approved  Action details Meeting details
4/30/20071 Service Drafter Sent for Approval  Action details Meeting details
Explanation
 
Background:  This legislation authorizes the City to enter into a contract in an amount up to $322,922.70 for the West Edge Business Center Roadway Resurfacing project and to pay construction inspection costs up to $27,272.00.  This improvement details construction on Buchanan, Van Buren, and Pierce Drives and includes work of replacing concrete curb and resurfacing the asphalt roadway, and other associated work. Limited sidewalk work will be included where there are ramps.  (See the attached map.)  The estimated Notice to Proceed date is June 1, 2007. This project is to be constructed by July 1, 2007.  The project was let by the Transportation Division and was advertised in the City Bulletin and  Dodge Reports.  Eleven bidders/suppliers requested the bid (nine majority, two minority) and six bids were received (five majority, one minority) and tabulated on April 10, 2007 as follows:
 
Strawser Paving Company
$322,922.70
Decker Construction Company
$389,293.65
Kokosing Construction Company, Inc.
$405,606.71
Shelly and Sands, Inc.
$410,183.73
Columbus Asphalt Paving, Inc.           
$413,920.13
The McDaniel's Construction Corp., Inc.*
$466,893.46
 
          *minority bidder
           
Award is to be made to Strawser Paving Company, CC# 31-4412354 (expiration 03/7/2009), as the lowest, best, most responsive and most responsible bidder.
 
Fiscal Impact:  Funding in the amount of $45,394.92 for this project is available from a cancelled encumbrance of a completed project, $178,897.00 is budgeted and available in the 1995, 1999, 2004 Voted Streets and Highway Fund from the 2007 Capital Improvement Budget and $125,902.78 for this project is budgeted within the Development Department's Northland and Other Acquisitions Fund for this work.
 
Emergency Action: Emergency action is requested so that this project can start and complete construction this season.
 
Title
 
To authorize the Director of Public Service to enter into a contract for the Transportation Division with Strawser Paving Company for construction of West Edge Business Center Roadway Resurfacing project; to authorize the expenditure $224,291.92 from the Voted 1995, 1999, 2004 Streets and Highways Fund and $125,902.78 from the Northland and Other Acquisitions Fund; to amend the 2007 CIB; and to declare an emergency.  ($350,194.70)
 
Body
 
WHEREAS, bids were received on March 29, 2007, and tabulated on April 10, 2007,  for the West Edge Business Center Roadway Resurfacing project and
 
WHEREAS, a satisfactory bid has been received; and
 
WHEREAS, it is necessary to provide for construction inspection costs; and
 
WHEREAS, it is necessary to amend the 2007 Capital Improvements Budget; and
 
WHEREAS,  an emergency exists in the usual daily operation of the Transportation Division, in that the contract should be let immediately so that the work may proceed without delay, in order to meet a scheduled construction start date of June 1, 2007; now, therefore
 
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
SECTION 1.  That the Public Service Director be and is hereby authorized to enter into a contract with Strawser Paving Company, 1595 Frank Road, Columbus, Ohio 43223, for the construction of the of West Edge Business Center Roadway Resurfacing project in the amount of $322,922.70, for the Transportation Division in accordance with the specifications and plans on file in the office of the Director of Public Service, which are hereby approved; to obtain and pay for the necessary inspection costs associated with the project up to a maximum of $27,272.00.
 
SECTION 2.  That the 2007 Capital Improvements Budget established within ordinance 0733-2007 be and hereby is amended due to cancellation of Encumbrance EA029750/002 as follows:
 
Project Number/Project Name/Current CIB Amount/Amended Amount/CIB Amount as Amended
590109/ Mound Souder (Carryover) /$178,897.00 (Carryover) /$45,395.00 (Carryover)/ $224,292.00 (Carryover)
 
SECTION 3.  That for the purpose of paying the cost of the contract and inspection, the sum of $224,291.92 or so much thereof as may be needed, is hereby authorized to be expended from the 1995, 1999,  2004 Voted Streets and Highways Fund for the Transportation Division and $125,902.78 or so much thereof as may be needed from the Northland and Other Acquisition Fund for the Development Department, is hereby authorized to be expended, as follows:
 
Fund      Dept./Div      OCA       OL3      Project No.
704      59-09            644385      6631      590109-Mound/Souder                           $224,291.92
735      44-01            735020      6631      440104-Misc. Economic Development      $125,902.78
 
SECTION 4.  That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this ordinance.
 
SECTION 5.  That for the reasons stated in the preamble hereto, which is hereby made a part hereof, this ordinance is hereby declared to be an emergency measure and shall take effect and be in force from and after its passage and approval by the Mayor, or ten days after passage if the Mayor neither approves nor vetoes the same.