File #: 2466-2023    Version: 1
Type: Ordinance Status: Passed
File created: 8/25/2023 In control: Recreation & Parks Committee
On agenda: 10/30/2023 Final action: 11/1/2023
Title: To authorize the Director of Recreation and Parks to enter into contract with Guzman's General Remodeling, LLC for the Riverside Green Park Shelter Replacement Project; to authorize the transfer of $74,999.00 within the Recreation and Parks Voted Bond Fund; to authorize the amendment of the 2023 Capital Improvements Budget; and to authorize the expenditure of $74,999.00 from the Recreation and Parks Voted Bond Fund. ($74,999.00)
Attachments: 1. Legislation - Riverside Green Park Shelter Replacement - Construction - ..pdf

Explanation

 

Background: This ordinance authorizes the Director of the Recreation and Parks Department to enter into contract with Guzman’s General Remodeling, LLC, for the Riverside Green Park Shelter Replacement Project. The contract amount is for a total of $74,999.00 being authorized by this ordinance.

 

Riverside Green Park provides green space and recreation amenities to the residents of the surrounding northwest area of Columbus. The park's existing open-air shelter is at the end of its useful life. The scope of work for this project includes the construction of a new open-air shelter, picnic tables, and a grill addition for residents to use.

 

Vendor Bid/Proposal Submissions (Office of Diversity and Inclusion designation status):

 

Bids were advertised through Vendor Services, in accordance with City Code Section 329, on June 27, 2023 and received by the Recreation and Parks Department on July 21, 2023. Bids were received from the following companies:

 

Guzman’s General Remodeling, LLC (MAJ): $72,000.00

Tyevco Inc. (MAJ): $105,400.00

Builderscape (MAJ): $121,813.00

Elford Inc. (MAJ) $149,169.00

R W Setterlin Building Co (MAJ) $150,435.00

 

After reviewing the bids that were submitted, it was determined that Guzman’s General Remodeling, LLC was the lowest and most responsive bidder. Guzman’s General Remodeling, LLC and all proposed subcontractors have met code requirements with respect to prequalification, pursuant to relevant sections of Columbus City Code Chapter 329.

 

Principal Parties:

Guzman's General Remodeling, LLC

2151 London Groveport Road                                                   

Grove City, Ohio 43123

Jesus Rolando Chalco, (614) 515-4520                                               

Contract Compliance Number: 032581

Contract Compliance Expiration Date: April 13, 2024

 

Benefits to the Public: This project will provide the community with new amenities including an open air shelter and grill for use.

 

Community Input/Issues: This project will enhance the facilities within the park, addressing the requests that came from the surrounding community through 311 requests.

 

Area(s) Affected: Northwest (34)

 

Master Plan Relation: This project will support the Recreation and Parks Master Plan by providing quality recreational parks for all Columbus residents.

 

Fiscal Impact: $74,999.00 is budgeted and available from within the Recreation and Parks Voted Bond Fund 7702 to meet the financial obligations of this contract.

 

Title

 

To authorize the Director of Recreation and Parks to enter into contract with Guzman's General Remodeling, LLC for the Riverside Green Park Shelter Replacement Project; to authorize the transfer of $74,999.00 within the Recreation and Parks Voted Bond Fund; to authorize the amendment of the 2023 Capital Improvements Budget; and to authorize the expenditure of $74,999.00 from the Recreation and Parks Voted Bond Fund. ($74,999.00)

 

Body

 

WHEREAS, it is necessary to authorize the Director of Recreation and Parks to enter into contract with Guzman’s General Remodeling, LLC, for the Riverside Green Park Shelter Replacement Project; and

 

WHEREAS, it is necessary to authorize the transfer of $74,999.00 within the Recreation and Parks Voted Bond Fund 7702; and

 

WHEREAS, it is necessary to authorize the amendment of the 2023 Capital Improvements Budget Ordinance 1711-2023 in order to provide sufficient budget authority for this and future projects; and

 

WHEREAS, it is necessary to authorize the expenditure of $74,999.00 from the Recreation and Parks Voted Bond Fund 7702; and

 

WHEREAS, it has become necessary in the usual daily operations of the Recreation and Parks Department to authorize the Director to enter into contract with Guzman’s General Remodeling, LLC for the Riverside Green Park Shelter Replacement Project, all for the preservation of the public health, peace, property, safety, and welfare: and NOW THEREFORE,

 

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:

 

SECTION 1. That the Director of Recreation and Parks be and is hereby authorized to enter into contract with Guzman's General Remodeling, LLC, for the Riverside Green Park Shelter Replacement Project.

 

SECTION 2. That the funds necessary to carry out the purpose of this ordinance are hereby deemed appropriated, and the City Auditor shall establish such accounting codes as necessary.

 

SECTION 3. That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this ordinance.

 

SECTION 4. That the City Auditor is hereby authorized to transfer the unencumbered balance in a project account to the unallocated balance account within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies are no longer required for said project.

 

SECTION 5. That the transfer of $74,999.00 or so much thereof as may be needed, is hereby authorized between projects within the Recreation and Parks Bond Fund 7702 per the account codes in the attachment to this ordinance.

 

SECTION 6. That the 2023 Capital Improvements Budget Ordinance 1711-2023 is hereby amended as follows in order to provide sufficient budget authority for this ordinance and future projects.

 

Fund / Project / Project Name / Current Revised Authority / Current Remaining Authority / Change / Amended Revised Authority / Amended Remaining Authority

 

Fund 7702 / P511000-100000 / Renovation - Misc. (Voted Carryover) / $4,617,863 / $4,167,863 / $384,687 / $5,002,550 / $4,552,550 (to match cash)

 

Fund 7702 / P511000-100000 / Renovation - Misc. (Voted Carryover) / $5,002,550 / $4,552,550 / ($74,999) / $4,927,551 / $4,477,551

 

Fund 7702 / P511058-100000 / Riverside Green Park Shelter Replacement (Voted Carryover) / $0 / $0 / $74,999 / $74,999 / $74,999

 

SECTION 7. For the purpose stated in Section 1, the expenditure of $74,999.00 or so much thereof as may be necessary to pay the cost thereof, be and is hereby authorized from the Recreation and Parks Voted Bond Fund 7702 in object class 06 Capital Outlay per the accounting codes in the attachments to this ordinance.

 

SECTION 8. That this ordinance shall take effect and be in force from and after the earliest period allowed by law.