header-left
File #: 0470-2011    Version: 1
Type: Ordinance Status: Passed
File created: 3/15/2011 In control: Public Utilities Committee
On agenda: 4/25/2011 Final action: 4/27/2011
Title: To authorize the Director of Public Utilities to enter into a construction administration and inspection services agreement with Prime Engineering & Architects, Inc.; to authorize a transfer within and an expenditure of up to $672,000.00 from the Sanitary Sewer Super Build America Bond Fund; to authorize a transfer within and an expenditure of up to $300,000.00 within the Water Build America Bonds Fund; for the Division of Power and Water; to authorize an amendment to the 2011 Capital Improvements Budget; and to declare an emergency. ($972,000.00)
Attachments: 1. CA-CI Tracking Spreadsheet.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
4/27/20111 MAYOR Signed  Action details Meeting details
4/27/20111 CITY CLERK Attest  Action details Meeting details
4/25/20111 Columbus City Council ApprovedPass Action details Meeting details
4/25/20111 COUNCIL PRESIDENT Signed  Action details Meeting details
4/5/20111 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
4/5/20111 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
4/4/20111 Utilities Drafter Sent for Approval  Action details Meeting details
4/1/20111 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
3/31/20111 Finance Reviewer Reviewed and Approved  Action details Meeting details
3/31/20111 Finance Reviewer Reviewed and Approved  Action details Meeting details
3/31/20111 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
3/31/20111 Utilities Drafter Sent for Approval  Action details Meeting details
3/31/20111 EBOCO Reviewer Sent for Approval  Action details Meeting details
3/30/20111 CITY AUDITOR Reviewed and Approved  Action details Meeting details
3/30/20111 CITY AUDITOR Reviewed and Approved  Action details Meeting details
3/30/20111 Utilities Drafter Sent for Approval  Action details Meeting details
3/30/20111 Finance Reviewer Reviewed and Approved  Action details Meeting details
3/29/20111 Utilities Drafter Sent for Approval  Action details Meeting details
3/23/20111 Auditor Reviewer Reviewed and Disapproved  Action details Meeting details
3/22/20111 Utilities Drafter Sent for Approval  Action details Meeting details
3/22/20111 Finance Reviewer Reviewed and Approved  Action details Meeting details
3/22/20111 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
3/22/20111 Utilities Drafter Sent for Approval  Action details Meeting details
3/21/20111 Utilities Reviewer Reviewed and Approved  Action details Meeting details
3/21/20111 Utilities Drafter Sent for Approval  Action details Meeting details
3/21/20111 Utilities Reviewer Sent for Approval  Action details Meeting details
3/21/20111 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
3/18/20111 Utilities Drafter Sent for Approval  Action details Meeting details
3/17/20111 Utilities Reviewer Reviewed and Approved  Action details Meeting details
3/16/20111 Utilities Drafter Sent for Approval  Action details Meeting details
3/16/20111 Utilities Drafter Sent for Approval  Action details Meeting details

Explanation

 

1.  BACKGROUND:

This legislation authorizes the Director of Public Utilities to enter into a construction administration and inspection services contract with Prime Engineering & Architects, Inc.  The Department of Public Utilities' project management personnel have reviewed proposals from several local firms, and is requesting City Council to authorize the award of a contract to each of the three highest ranking firms.

 

2.  MULTI-YEAR CONTRACT:

This contract establishes fixed direct labor, overhead, and fixed fee rates for the period of 2011-2013.  This ordinance will authorize the expenditure of  up to $672,000.00 for three sanitary sewer projects and up to $300,000.00 for two water projects.  The Department anticipates requesting additional appropriations to this contract during the remainder of 2011, 2012, 2013 fiscal years, through planned contract modifications duly authorized by City Council.  Under the terms of this contract, the City has the right to contract for additional services to fulfill emergency capital improvements related needs subject to the approval of a contract modification by City Council.  The rates schedules established within this contract will remain in force throughout the life of the contract.

 

3.  FISCAL IMPACT:

There is sufficient funding and authority within the Sanitary Sewer Super Build America Bond Fund to cover the project expenditures of this legislation for the sanitary sewer projects.  A transfer of funds within the Sanitary Sewer Super Build America Bond Fund, Water Build America Bonds Fund, and an amendment to the 2011 Capital Improvements Budget is necessary.

 

4.  CONTRACT COMPLIANCE INFO: 31-1373357 | FBE | Expires 11/30/12

This company is not debarred according to the Federal excluded parties listing or prohibited from being awarded a contract to the Auditor of State unresolved findings for recovery certified search.

 

5.  EMERGENCY DESIGNATION:

The Department is requesting that this ordinance be made an emergency measure in order to expedite the establishment of the contract services that are necessary to ensure that the sanitary and water systems are being rehabilitated and/or replaced to ensure the continued operation of this vital infrastructure.

 

 Title

 

To authorize the Director of Public Utilities to enter into a construction administration and inspection services agreement with Prime Engineering & Architects, Inc.; to authorize a transfer within and an expenditure of up to $672,000.00 from the Sanitary Sewer Super Build America Bond Fund; to authorize a transfer within and an expenditure of up to $300,000.00 within the Water Build America Bonds Fund; for the Division of Power and Water; to authorize an amendment to the 2011 Capital Improvements Budget; and to declare an emergency. ($972,000.00)

 

Body

 

WHEREAS, the Sewer System Engineering Section of the Division of Sewerage and Drainage and the Division of Water have a consistent and immediate demand for cost-effective construction administration and inspection services so that its capital improvements projects are completed in accordance with the Department's design requirements in order to ensure the continued operation of its sanitary and water infrastructures; and

 

WHEREAS, the Department did undertake a successful Request for Proposal process in accordance with Section 329.12 of the Columbus City Codes in an effort to find three firms to provide an ongoing source of technical personnel to supplement existing city inspection personnel that are required to protect its customers investment in its sanitary sewer and water infrastructures; and

 

WHEREAS, based upon an evaluation of the five proposals received for the three construction administration and inspection contracts to be awarded for the years of 2011-2013, utilizing a predetermined  criteria, a selection committee submitted the rankings to the Director of Public Utilities who determined that DLZ Ohio, Inc., Prime Engineering & Architects, Inc., and Stantec Consulting Services, Inc. were the highest ranking firms capable of providing the required services; and

 

WHEREAS, it is necessary for this Council to authorize the City Auditor to transfer funds within the Sanitary Sewer Super Build America Bond Fund and the Water Build America Bonds Fund; and

 

WHEREAS, it is necessary to authorize an amendment to the 2011 Capital Improvements Budget for purposes of providing sufficient budget authority for the project expenditures; and

 

WHEREAS, an emergency exists in the usual daily operation of the Department of Public Utilities in that it is immediately necessary to authorize the Director of Public Utilities to enter into contract with Prime Engineering & Architects, Inc., for the construction administration and inspection services for the projects listed herein below, which are necessary to allow for the proper operation of the City's sanitary and water infrastructure, as well as, for the preservation of the public peace, health, property, and welfare; Now, Therefore,

 

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:

 

Section 1.  That the Director of Public Utilities be, and hereby is, authorized to award and execute a professional engineering services agreement with Prime Engineering & Architects, Inc., 3000 Corporate Exchange Dr, Columbus, Ohio 43231 that will provide construction administration and inspection services for sewer improvement and water projects in accordance with the terms and conditions of the Contract on file in the office of the Division of Sewerage and Drainage's Sewer System Engineering Section.

 

Section 2.  That the said services shall be performed by Prime Engineering & Architects, Inc. to the satisfaction of the Director of Public Utilities, the Administrators of the Divisions of Sewerage and Drainage, and Power and Water, as well as the Engineering Managers of the Division of Sewerage and Drainage's Sewer System and the Division of Power and Water.

 

Section 3.  That the City Auditor be and hereby is authorized and directed to transfer up to a total of $672,000.00 from within the Sanitary Sewer Super Build America Bond Fund | Fund No. 669 | Division 60-05 | Object Level Three 6686:

 

From:

Fund No. | Project No. | Project Name | OCA Code | change

669 | 650351-100001 | WWTF Construction and Contingencies | 669351 | -$672,000.00

 

To:

Fund No. | Project No. | Project Name | OCA Code | change

669 | 650100-100000 | Sanitary Sewer Contingency | 669100 | +$100,800.00

669 | 650700-100000 | Portage Grove Area Assessment | 669700| +$107,100.00

669 | 650708-100000 | First Ave Inflow Redirection Project | 669708 | +$151,725.00

669 | 650715-100000 | Lrg Dia Sewer Rehab - Olentangy Main Trunk Sewer Ph. B | 669715 | +$312,375.00

 

Section 4.  That the City Auditor is hereby authorized to transfer up to $300,000.00 within the Division of Power and Water, Dept/Div. No. 60-09, Water Build America Bonds Fund, Fund No. 609, Object Level One 06, Object Level Three 6686, as follows:

 

Fund No. | Project No. | Project Name | OCA Code | change

609 | 690236-100019 (carryover) | Alton-Darby Rd. W.L. | 623619 | -$8,682.80

609 | 690236-100021 (carryover) | River South Ph. 2 | 623621 | -$3,750.00

609 | 690236-100025 (carryover) | Gen'l Eng. Svcs.-URS | 623624 | -$8,999.95

609 | 690335-100000 (carryover) | DRWP Olentangy Intake | 693350 | -$150,000.00

609 | 690384-100000 (carryover) | Griggs/Hoover Rdwy. Imp's | 609384 | -$128,567.25

609 | 690236-100010 (carryover) | German Village Area W.L. Imp's | 693610 | +$168,000.00

609 | 690236-100049 (carryover) | Georgesville Rd. W.L. Imp's | 693649| +$75,000.00

609 | 690236-100000 (carryover) | Water Main Rehab. | 609236 | +$57,000.00

 

Section 5.  That the 2011 Capital Improvements budget Ordinance No. 0266-2011 is hereby amended as follows, to provide sufficient budget authority for the project expenditure stated in the ordinance herein.

 

Fund No. | Project No. | Proj. Name | Current | Revised | (Change)

669 | 650351-100001 | WWTF Construction and Contingencies | $910,081 | $238,081 | (-$672,000)

669 | 650100-100000 | Sanitary Sewer Contingency | $0 | $100,800 | +$100,800

669 | 650700-100000 | Portage Grove Area Assessment | $0 | $107,100 | +$107,100

669 | 650708-100000 | First Ave Inflow Redirection Project | $0 | $151,725 | +$151,725

669 | 650715-100000 | Lrg Dia Sewer Rehab - Olentangy Main Trk Sewer | $0 | $312,375 | +$312,375

 

Project No. | Proj. Name | Current | Revised | (Change)

609 | 690236-100019 (carryover) | Alton-Darby Rd. W.L. | $8,683 | $0 | -$8,683

609 | 690236-100021 (carryover) | River South Ph. 2 | $3,750 | $0 | -$3,750

609 | 690236-100025 (carryover) | Gen'l Eng. Svcs.-URS | $9,000 | $0 | -$9,000

609 | 690335-100000 (carryover) | DRWP Olentangy Intake | $150,000 | $0 | -$150,000

609 | 690384-100000 (carryover) | Griggs/Hoover Rdwy. Imp's | $200,000 | $71,432 | -$128,568

609 | 690236-100010 (carryover) | German Village Area W.L. Imp's | $820,642 | $988,642 | +$168,000

609 | 690236-100049 (carryover) | Georgesville Rd. W.L. Imp's | $0 | $75,000 | +$75,000

609 | 690236-100000 (carryover) | Water Main Rehab. | $50,000 | $107,000 | +$57,000

 

Section 6.  That the expenditure of $672,000.00, or as much thereof as may be needed, be and the same is hereby authorized from the Sanitary Sewer Super Build America Bond Fund, as follows:

 

669 | 650100-100000 | Sanitary Sewer Contingency | 669100 | +$100,800.00

669 | 650700-100000 | Portage Grove Area Assessment | 669700| +$107,100.00

669 | 650708-100000 | First Ave Inflow Redirection Project | 669708 | +$151,725.00

669 | 650715-100000 | Lrg Dia Sewer Rehab - Olentangy Main Trunk Sewer Ph. B | 669715 | +$312,375.00

 

Section 7.  That the expenditure of $300,000.00, or as much thereof as may be needed, be and the same is hereby authorized from the Water Build America Bonds Fund as follows, Fund 609, Div. 60-09, Obj. Level 3: 6686, as follows:

 

690236-100010 (carryover) | German Village Area W.L. Imp's | OCA 693610 | $168,000.00

690236-100049 (carryover) | Georgesville Rd. W.L. Imp's | OCA 693649 | $75,000.00

690236-100000 (carryover) | Water Main Rehab. | OCA 609236 | $57,000.00

 

Section 8.  That the City Auditor is hereby authorized to transfer any unencumbered balance in the project account to the unallocated balance within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies are no longer required for said project; except that no transfer shall be made from a project by monies from more than one source.

 

Section 9. That the City Auditor is authorized to establish proper project accounting numbers as appropriate.

 

Section 10. That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this ordinance.

 

Section 11.  That for the reasons stated in the preamble hereto, which is hereby made a part hereof, this ordinance is hereby declared to be an emergency measure and shall take effect and be in force from and after its passage and approval by the Mayor, or ten days after passage if the Mayor neither approves nor vetoes the same.