This ordinance will authorize the Director of Recreation and Parks to modify the contract with The Quandel Group for construction services relative to the Alum Creek Maintenance/Warehouse Facility Project.
The original contract authorized the renovation of 1533 Alum Creek Industrial Drive, West for the Recreation and Parks Department's Maintenance and Warehouse operations. The Quandel Group has requested an increase in the original contract EL007487 due to unforseen circumstances which necessitated a change in the scope and budget.
The original contract in the amount of $2,654,900.00 included a project contingency of $461,885.49 for a total contract amount of $3,116,785.49. The amount of this modification request is $215,795.73 bringing the total modified cost of the contract to $3,332,581.22.
This modification includes the following: changes due to the unstable sub-base under the proposed vehicular storage area; additional costs for truck canopy installation; unforseen mold remediation; additional code requirements for electrical, mechanical, fire and drainage systems that were not anticipated by the architect; and unanticipated utility connection fees.
The Contract Compliance Number for The Quandel Group is #23-2315218 and their Contract Compliance is effective through 11/30/08.
Fiscal Impact:
$215,795.73 has been identified in the 1999/2004 Recreation and Parks Voted Bond Fund to meet the financial obligation of this contract modification.
Title
To authorize and direct the Director of Recreation and Parks to modify the contract with The Quandel Group for additional construction services relative to the Alum Creek Maintenance/Warehouse Facility Project and to authorize the expenditure of $215,795.73 from the 1999/2004 Recreation and Parks Voted Bond Fund. ($215,795.73)
Body
WHEREAS, it is necessary to modify the contract with The Quandel Group for additional construction services for the Alum Creek Maintenance/Warehouse Facility Project; and
WHEREAS, unforseen changes have necessitated an increase in the scope and budget; now, therefore
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
SECTION 1. That the Director of Recreation and Parks be and he is hereby authorized and directed to modify the contract with The Quandel Group for additional construction services for the Alum Creek Maintenance/Warehouse Facility Project
SECTION 2. That the expenditure of $215,795.73 or so much thereof as may be necessary, be and is hereby authorized from the 1999/2004 Recreation and Parks Voted Bond Fund No. 702; Dept. No. 51-01; Facility Improvements, Project No. 510035; OCA Code 644526; Object Level 3 No. 6620, to pay the cost thereof.
SECTION 3. That the monies in the foregoing Section 2 shall be paid upon order of the Director of Recreation and Parks, and that no order shall be drawn or money paid except by voucher, the form of which shall be approved by the City Auditor.
SECTION 4. That the City Auditor is hereby authorized to transfer the unencumbered balance in a project account to the unallocated balance account within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies are no longer required for said project; except that no transfer shall be so made from a project account funded by monies from more than one source.
SECTION 5. That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this ordinance.
SECTION 6. That this ordinance shall take effect and be in force from and after the earliest period allowed by law.