Title: To authorize the Director of the Department of Public Utilities to modify contracts with Ironsite, Inc. and Watershed Organic Lawn Care LLC for the Green Infrastructure Inspection and Maintenance Project to add additional funding; and to authorize the expenditure of $50,000.00 from the Water Operating Fund and $200,000.00 from the Stormwater Operating Fund. ($250,000.00)
Indexes: MBE Participation
Attachments: 1. ORD 2611-2024 Financial Coding

Explanation

BACKGROUND

The purpose of this legislation is to authorize the Director of the Department of Public Utilities to modify contracts with Ironsite, Inc. and Watershed Organic Lawn Care LLC for services associated with the Green Infrastructure Inspection and Maintenance Project. The City of Columbus is committed to investing in green infrastructure. As part of this commitment, the City has built a number of bio-retention basins in the right-of-way and/or on City owned property.   

 

The City is currently responsible for the maintenance of 62 Facilities with 1,061 basins and wetlands. These facilities are located in Clintonville, Linden, Eastmoor, American Addition, Southwest Columbus, Blacklick, Hilltop, the South Side, Dublin, Reynoldsburg, Easton, Barthman Parsons, West Town Street/US 62, 2nd Street, River South Roadways West Rich Street, West Main Street Riversouth, West Broad St. at Starling Street, Hoover Reservoir, 910 Dublin Road, Dublin Road Water Plant, Griggs Reservoir, O’Shaughnessy Reservoir, Mound Street Booster Station and the Smoky Row Booster Station. Each facility and location may have multiple sites with basins, swales or other types of green infrastructure. Additional facilities may be added in the future.

 

PROCUREMENT

The Department of Public Utilities publicly advertised and solicited competitive bids in accordance with Section 329 of Columbus City Code (RFQ025742). Thirty-one (31) vendors (1-EBE/WBE, 26-MAJ, 3-MBE, 1-WBE) were solicited and two (1-EBE/WBE and 1 MAJ) bids were received and opened on September 13, 2023.

 

The bids for Ironsite, Inc. for Group 1 and Watershed Organic Lawn Care LLC for Groups 2 and 3 as the lowest responsive, responsible and best bidders.

 

CONTRACT AMOUNTS / TIMELINE

The contract term is for one year through November 30, 2024. The contract language allows to renew annually for two (2) additional years based upon mutual agreement, availability of funds, and approval by Columbus City Council. Future modifications will be required to incorporate additional green infrastructures into this contract as facilities are constructed and turned over to the City for maintenance. If unforeseen issues or difficulties are encountered that would require additional funding, a modification would be requested. We are currently in the second year of the contract per Ordinance #0233-2024.

 

This legislation seeks to and add funding to the contract. This Ordinance is being submitted in accordance with the relevant provisions of Chapter 329 of City Code pertaining to contract renewals and modifications.

 

Cost summary:

Original Contract, Ordinance #2799-2023                                          $283,000.00

Modification/Renewal #1, Ordinance #0233-2024                   $279,000.00

Modification #2 (pending), Ordinance #2611 -2024               $250,000.00

Estimated Contract Total:                                                                                        $812,000.00

 

1.               Amount of additional funds:  Total amount of additional funds needed for this contract modification is to ADD $250,000.00. Total contract amount including this modification is $812,000.00.

 

2.                                  Reason additional funds were not foreseen: The need for additional funds were included in the initial contract as additional green infrastructures are completed and are turned over to the City for maintenance.

 

3.               Reason other procurement processes are not used: This contract was awarded through the competitive bidding process for Green Infrastructure Inspection and Maintenance Services.  Planned contract modifications were anticipated to add funds for continuation of services. This is one of those planned contract modifications so a new procurement process is not required.

 

4.               How cost was determined: A cost proposal was provided by Watershed Organic Lawn Care LLC and Ironsite, Inc. in their bid and was reviewed by the Division of Sewerage and Drainage and was deemed acceptable.

 

SUPPLIERS / CONTRACT COMPLIANCE INFORMATION 

Ironsite, Inc., vendor #005926, EBE/WBE status, expires 7/16/25

Watershed Organic Lawn Care LLC, vendor #005742, majority status, expires 3/31/25

 

The certification of Watershed Organic Lawn Care LLC and Ironsite, Inc. was in good standing at the time of the contract award. The company is not debarred according to the Excluded Party Listing System of the Federal Government or prohibited from being awarded a contract according to the Auditor of State Unresolved Findings for Recovery Certified Search.

 

MINORITY AND WOMAN OWNED BUSINESS ENTERPRISE & SMALL LOCAL BUSINESS ENTERPRISE PROGRAM

This contract was put in place with an ODI determined MBE/WBE program goal of 15%. Ironsite, Inc. is classified as an EBE/WBE company. Ironsite, Inc. anticipates performing the work on this contract modification. The MBE/WBE percentage for this contract modification is expected to be 15%.

 

FISCAL IMPACT

$250,000.00 funds are budgeted and available for this expenditure

$636,564.93 was spent in 2023

$310,240.69 was spent in 2022

 

Title

 

To authorize the Director of the Department of Public Utilities to modify contracts with Ironsite, Inc. and Watershed Organic Lawn Care LLC for the Green Infrastructure Inspection and Maintenance Project to add additional funding; and to authorize the expenditure of $50,000.00 from the Water Operating Fund and $200,000.00 from the Stormwater Operating Fund. ($250,000.00)

 

 

Body

WHEREAS, the Department of Public Utilities entered into contracts for the Green Infrastructure Inspection and Maintenance Project in accordance with Chapter 329 of the Columbus City Code, pursuant to solicitation, RFQ025742, with Ironsite, Inc. and Watershed Organic Lawn Care; and

 

WHEREAS,  the Department of Public Utilities wishes to modify to increase funding to contracts with Ironsite, LLC and Watershed Organic Lawn Care for Green Infrastructure Inspection and Maintenance Project; and

 

WHEREAS, the vendors have agreed to modify to extend the expiration of the contract and to increase the contract at current prices and conditions; and

 

WHEREAS, it has become necessary in the usual daily operation of the Department of Public Utilities to authorize the Director to modify to increase the funding on the contracts with Ironsite, Inc. and Watershed Organic Lawn Care for Green Infrastructure Inspection and Maintenance Project, thereby preserving the public peace, property, health, welfare, and safety; and  NOW THEREFORE;

 

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:

 

SECTION 1.  That the Director of Public Utilities be and is hereby authorized to modify to add funding to contracts with Ironsite, Inc. and Watershed Organic Lawn Care for Green Infrastructure Inspection and Maintenance Project, in accordance with the terms and conditions as shown in the agreement on file in the Department of Public Utilities. Total amount of this modification is $250,000.00. Total contract amount including this modification is $812,000.00.

 

SECTION 2.  That the expenditure of $250,000.00 or so much thereof as may be needed, be and is hereby authorized $50,000.00 in Object Class 02 and $150,000.00 in Object Class 03 Services from Fund 6200-Stomwater Operating and $30,000.00 in Object Class 02 and $20,000.00 in Object Class 03 from Fund 6000-Water Operating per the accounting codes in the attachment to this ordinance.

 

SECTION 3.  That the funds necessary to carry out the purpose of this ordinance are hereby deemed appropriated and the City Auditor shall establish such accounting codes as necessary.

 

SECTION 4.  That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this Ordinance.

 

SECTION 5.  That this Ordinance shall take effect and be in force from and after the earliest period allowed by law.