Title: To authorize the Director of Public Utilities to enter into a contract modification with Evans Mechwart Hambleton & Tilton Incorporated for the Construction Administration/Construction Inspection Services 2023-2025 contract; to authorize an amendment to the 2024 Capital Improvement Budget; and to expend up to $214,836.28 from the Sanitary Bond Fund for the modification. ($214,836.28).
Attachments: 1. ORD 0515-2025 Accounting Template, 2. ORD0515-2025 Utilization, 3. Business_Details (2)

Explanation

1.  BACKGROUND

This ordinance authorizes the Director of Public Utilities to enter into a contract modification with Evans Mechwart Hambleton & Tilton Inc. (EMH&T Inc.), for construction administration/inspection services for Department of Public Utilities construction projects bid during the calendar years 2023 through 2025 as part of the Construction Administration/Construction Inspection Services 2023-2025 contracts.  The construction project to be administered by EMH&T Inc. under this contract modification is the Blueprint Volunteer Sump Pump 2025 project, CIP No. 650876-129992, in an amount up to $214,836.28.

 

The Blueprint Volunteer Sump Pump 2025 project will install sump pumps in homes to redirect foundation drain away from the sanitary sewer lateral to the house’s sump pit.  This will reduce rainwater infiltration of the sanitary sewers by directing the rainwater to storm sewers.  This redirection reduces basement flooding and assists with compliance of environmental requirements to keep rainwater out of the sanitary sewer system.  This project will cover 400 properties that represent the 10% target participation rate in the following areas: Clintonville 1, Phase 4; Clintonville 3, Phase 1; Hilltop 1, Phase 3; Hilltop 4;  and Phase 1 of Miller/Kelton, Linden, James/Livingston, Old Beechwold, and 5th by Northwest 1.  Construction administration and inspection services ensure work is consistent with and conforms to plans and specifications, and that the construction and any associated issues are handled efficiently and in the best interest of the City of Columbus.

 

This work will primarily be performed in Community Planning Area 99 - Citywide.

 

UPDATED TIMELINE

The original contract allowed for work is to be completed within the timeframe established by the individual construction contracts.  This contract modification will be in effect through the completion of construction for this project.

 

1.1. Amount of additional funds to be expended:  $214,836.28

Original Contract:                                                             $ 1,934,456.02 (PO386052)

Modification #1:                                                               $    178,477.12 (PO402261)

Modification #2:                                                                                   $    495,415.00 (PO425785 and PO425788)

Modification #3:                                                               $ 1,133,050.50 (PO486138)

Modification #4: (current):                                                $     214,836.28 (TBD)

 

                                                          Total:                     $ 3,956,234.92

 

1.2. Reasons additional goods/services could not be foreseen: 

This is a three-year agreement for fiscal years 2023 - 2025 and modifications were anticipated and explained in the original legislation under Ordinance 0745-2023.

 

1.3. Reason other procurement processes are not used: 

This is a multi-year contract that will be modified as required to provide Construction Administration/Construction Inspection services for construction projects that bid during the three-year (2023-2025) timeframe. Another procurement process is not required.   

 

1.4. How cost of modification was determined:

The cost of this modification was determined by negotiations between EMH&T Inc. and Department of Public Utilities project staff based upon the existing contract labor titles, maximum labor rates, allowable contract expenses, and the time estimated to be needed to perform contract tasks.

 

2. ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT

This work will ensure the Department’s construction projects are performed correctly and will last the anticipated service life.   No community outreach is planned at this time.

 

3.  CONTRACT COMPLIANCE INFORMATION

EMH&T Inc.’s contract compliance number is CC-004214 and expires 11/8/2025. 

                                                        

4.  MINORITY AND WOMAN OWNED BUSINESS ENTERPRISE & SMALL LOCAL BUSINESS ENTERPRISE PROGRAM

This contract opportunity was submitted to the City’s Office of Diversity and Inclusion (ODI) for review and assignment of an MBE/WBE goal prior to bidding.  ODI determined there was not an opportunity for MBE/WBE participation in this contract and did not assign a goal.  This contract was not bid with a City of Columbus MBE/WBE Program goal and the requirements of the City’s MBE/WBE Program are not applicable to this contract.  EMH&T Inc. is ODI certified as a majority company.  As shown in the Utilization Plan attached to this ordinance, EMH&T Inc. plans to use no sub-consultants on this task.  The MBE/WBE spend for this modification is anticipated to be $0.00, or 0% for the contract.

 

EMH&T Inc.’s certification was in good standing at the time of this contract modification.

 

5.  FISCAL IMPACT

Funds are appropriated and available within the Sanitary Bond Fund, Fund 6109, for this expenditure.  An amendment to the 2024 Capital Improvement Budget is needed to align budget authority with the proper project.

 

 Title

To authorize the Director of Public Utilities to enter into a contract modification with Evans Mechwart Hambleton & Tilton Incorporated for the Construction Administration/Construction Inspection Services 2023-2025 contract; to authorize an amendment to the 2024 Capital Improvement Budget; and to expend up to $214,836.28 from the Sanitary Bond Fund for the modification. ($214,836.28).

 

Body

WHEREAS, the Department of Public Utilities is engaged in the Blueprint Volunteer Sump Pump 2025 project; and

 

WHEREAS, Contract No. PO386052 was authorized by Ordinance No. 0745-2023, for the Construction Administration/Construction Inspection Services 2023-2025 Project; and

 

WHEREAS, a planned contract modification is needed to add additional funds for the Construction Administration/Construction Inspection tasks needs to be performed for the Blueprint Volunteer Sump Pump 2025 project; and

 

WHEREAS, the contract with EMH&T Inc. will need to be modified to add this task to the contract and to add funding to pay for the task; and

 

WHEREAS, an amendment to the 2024 Capital Improvement Budget is needed to align budget authority with the proper project; and

 

WHEREAS, funds must be expended from the Sanitary Bond Fund, Fund 6109, to pay for the construction administration and inspection services EMH&T Inc. provides under the Construction Administration/Construction Inspection Services 2023-2025 contract; NOW, THEREFORE,

 

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:

 

SECTION 1.  That the 2024 Capital Improvement Budget authorized by Ordinance 1907-2024 be amended as follows to establish sufficient budget authority for this project:

 

Fund / Project Number / Project Name (Funding Source) / Current Authority / Revised Authority / Change

6109 / P650876-153001 / Volunteer Sump Pump Program - Blueprint Hilltop 4, Phase 1 (Voted Sanitary Carryover) / $116,020.00 / $0.00 / ($116,020.00)

6109 / P650876-153004 / Blueprint Hilltop 1 Volunteer Sump Pump Program Project 2 (Voted Sanitary Carryover) / $67,741.00 / $0.00 / ($67,741.00)

6109 / P650876-157001 / Volunteer Sump Pump Program - Blueprint James Livingston 5, Phase 1 (Voted Sanitary Carryover) / $55,422.00 / $24,347.00 / ($31,075.00)

 

6109 / P650876-129992 / Blueprint Volunteer Sump Pump 2025 (Voted Sanitary Carryover) / $0.00 / $214,836.00 / $214,836.00

 

SECTION 2.  That the Director of the Department of Public Utilities is authorized to enter into a contract modification with EMH&T Inc., 5500 New Albany Rd, Columbus, Ohio 43054, for construction administration and inspection services, in accordance with the terms and conditions as shown in the contract on file with the Department of Public Utilities, in an amount not to exceed $214,836.28.

 

SECTION 3. That an expenditure not to exceed $214,836.28 is authorized per the accounting codes in the attachment to this Ordinance.

 

SECTION 4.  That funds are deemed appropriated and expenditures and transfers authorized to carry out the purposes of this Ordinance and the City Auditor shall establish such accounting codes as necessary.

 

SECTION 5.  That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this Ordinance.

 

SECTION 6.  That the City Auditor is authorized to transfer the unencumbered balance in a project account to the unallocated balance account within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies are no longer required for said project.

 

SECTION 7.  That this Ordinance shall take effect and be in force from and after the earliest period allowed by law.