File #: 2430-2012    Version: 1
Type: Ordinance Status: Passed
File created: 10/30/2012 In control: Public Utilities Committee
On agenda: 12/10/2012 Final action: 12/12/2012
Title: To authorize the Director of Public Utilities to enter into a planned modification of the Boiler Maintenance Services contract with General Temperature Control, Inc., for the Division of Sewerage and Drainage, and to authorize the expenditure of $75,000.00 from the Sewerage System Operating Fund. ($75,000.00)
Attachments: 1. ORD 2430-2012 Boiler Maintenance - FEM 1502.6 Mod 3 Addt'l. Info

Explanation

 

The Director of Public Utilities entered into a contract with General Temperature Control, Inc. for Boiler Maintenance Services, FEM Project No. 1502.6 for the Division of Sewerage and Drainage, Southerly Wastewater Treatment Plant on July 7, 2009.  This contract was the result of a Director's Bid received on March 11, 2009.  General Temperature Control, Inc. was the lowest, responsive, responsible bidder and met all requirements of the specifications.  The original contract was for a period of one year with three (3) one year renewal options on a year to year basis upon mutual agreement, availability of funding and Columbus City Council approval.  The Division of Sewerage and Drainage is utilizing the third extension option.  This is the 4th year of a four (4) year contract.  The contract will expire on July 6, 2013.

 

This contract will continue to provide weekly, monthly and yearly maintenance of 7 boilers currently in use at the Southerly Wastewater Treatment Plant.  This contract provides the chemicals required for treating the water contained in the boilers at Southerly and Jackson Pike Waste Water Treatment Plants.  This contract also provides the necessary maintenance and/or repairs of these boilers and the boilers at other DOSD facilities.  This modification will provide additional funding necessary for the payment of services to be provided through July 6, 2013.  This modification does not extend the length of the contract.

 

SUPPLIER:  General Temperature Control, Inc. (31-1201236) Expires 3/13/2014

General Temperature Control, Inc. does not hold MBE/FBE status.

 

The company is not debarred according to the Excluded Party Listing System of the Federal Government or prohibited from being awarded a contract according to the Auditor of State Unresolved Findings for Recovery Certified Search.

 

1. Amount of additional funds:  Total amount of additional funds needed for this contract modification No. 3 is $75,000.00.  Total contract amount including this modification is $443,760.00.

 

2.Reason additional funds were not foreseen:  The need for additional funds was known at the time of the initial contract, as this is an annual expenditure.  This legislation for Modification Number 3, is to provide additional funding necessary for the payment of services to be provided through July 6, 2013. 

 

3. Reason other procurement processes not used:  Work under this modification is a continuation of services included in the scope of the original bid contract, with minor scope modifications.  No lower pricing/more attractive terms and conditions are anticipated at this time.

 

4. How was cost determined:  The cost for inspection and maintenance of the process and heating boilers at the Southerly Wastewater Treatment Plant is in accordance with the original agreement.  The budgetary price for chemicals and anticipated maintenance is based on previous expenditures for these services.

 

FISCAL IMPACT:  $75,000.00 is budgeted and needed for this purchase.

 

$50,591.89 has been spent through October 2012

$109,253.21was spent in 2011

$69,528.72 was spent in 2010

$6,000.00 was spent in 2009

 

Title

 

To authorize the Director of Public Utilities to enter into a planned modification of the Boiler Maintenance Services contract with General Temperature Control, Inc., for the Division of Sewerage and Drainage, and to authorize the expenditure of $75,000.00 from the Sewerage System Operating Fund.  ($75,000.00)

 

Body

 

WHEREAS, the Department of Public Utilities has a contract with General Temperature Control, Inc. for Boiler Maintenance Services, FEM Project No. 1502.6 for the Division of Sewerage and Drainage, Southerly Wastewater Treatment Plant; and

 

WHEREAS, with this modification, funding to continue the Boiler Maintenance Services for the Southerly Waste Water Treatment Plant, chemicals required for treating the water contained in the boilers at Southerly and Jackson Pike Wastewater Treatment Plants and troubleshooting boiler problems at the Jackson Pike Waste Water Treatment Plant, Sewer Maintenance Operations Center (SMOC) and other Division of Sewerage and Drainage facilities as necessary; and

 

WHEREAS, the Division of Sewerage and Drainage wishes to modify and increase EL009405 with General Temperature Control, Inc. for Boiler Maintenance Services to provide additional funding necessary for 2013; and 

 

WHEREAS, the vendor has agreed to modify and increase EL009405 at current prices and conditions, and it is in the best interest of the City to exercise this option; now, therefore

 

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:

 

Section 1.  That the Director of Public Utilities be and is hereby authorized to modify and increase the contract with General Temperature Control, Inc. for Boiler Maintenance Services for the Division of Sewerage and Drainage.

 

Section 2.  That the expenditure of $75,000.00 or so much thereof as may be needed, be and the same hereby is authorized from the Sewer System Operating Fund, Fund 650 as follows:

 

OCA:  605378

Object Level 1:  03

Object Level 03:  3372

 

Section 3. That this Ordinance shall take effect and be in force from and after the earliest period allowed by law.