header-left
File #: 1148-2009    Version: 1
Type: Ordinance Status: Passed
File created: 8/26/2009 In control: Utilities Committee
On agenda: 9/21/2009 Final action: 9/22/2009
Title: To authorize the Director of Public Utilities to enter into an agreement with JD Power Systems LLC for the removal, transport and installation of a 75 KW generator for the Division of Sewerage and Drainage and to authorize the expenditure of $32,499.00 from the Sewerage System Operating Fund. ($32,499.00)
Attachments: 1. 75 KW Additional Info.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
9/22/20091 MAYOR Signed  Action details Meeting details
9/22/20091 CITY CLERK Attest  Action details Meeting details
9/21/20091 Columbus City Council ApprovedPass Action details Meeting details
9/21/20091 COUNCIL PRESIDENT Signed  Action details Meeting details
9/14/20091 Columbus City Council Read for the First Time  Action details Meeting details
9/4/20091 Utilities Drafter Sent for Approval  Action details Meeting details
9/4/20091 Auditor Reviewer Reviewed and Approved  Action details Meeting details
9/4/20091 CITY AUDITOR Reviewed and Approved  Action details Meeting details
9/4/20091 Utilities Drafter Sent for Approval  Action details Meeting details
9/4/20091 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
9/4/20091 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
9/3/20091 Utilities Drafter Sent for Approval  Action details Meeting details
9/3/20091 Finance Reviewer Reviewed and Approved  Action details Meeting details
9/3/20091 Finance Reviewer Reviewed and Approved  Action details Meeting details
9/3/20091 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
9/2/20091 Utilities Drafter Sent for Approval  Action details Meeting details
9/2/20091 EBOCO Reviewer Sent for Approval  Action details Meeting details
9/2/20091 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
9/1/20091 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
8/31/20091 Utilities Reviewer Reviewed and Approved  Action details Meeting details
8/31/20091 Utilities Reviewer Sent for Approval  Action details Meeting details
8/26/20091 Utilities Drafter Sent for Approval  Action details Meeting details
Explanation
 
The purpose of this legislation is to authorize the Director of Public Utilities to enter into an agreement with JD Power Systems LLC for the Transport and Installation of a 75 KW Generator for the Division of Sewerage and Drainage, Jackson Pike Wastewater Treatment Plant.
 
The Jackson Pike Wastewater Treatment Plant has a need for a 75 KW generator to be removed and transported from the wastewater treatment plant and installed at the 250 W. Whittier Street location. The generator will be used to power gates at the Whittier Street storm tanks. The current generator at the Whittier Street storm tanks has reached it's useful life and is not operating properly to ensure proper gate operations. Because of the age of the current equipment the generator could fail to perform completely. The Jackson Pike Wastewater Treatment Plant has a larger generator that can be removed and installed at the Whittier Street location. It is more cost effective for the Division of Sewerage and Drainage to transport the larger generator than to purchase a new piece of equipment.
 
The Director of Public Utilities opened formal bids on August 5, 2009. Four (4) bids were received. A bid tabulation follows:
 
JD Power Systems: $32,499.00
Jess Howard Electric: $33,350.00
Cummins Bridgeway LLC: $37,331.00
Proline Electric Inc: $40,690.00
 
SUPPLIER: JD Power Systems LLC (26-3637530) Expires: 8-20-11
 
FISCAL IMPACT: $32,499.00 is budgeted and needed for this purchase.
 
The company is not debarred according to the Excluded Party Listing System of the Federal Government or prohibited from being awarded a contract according to the Auditor of State Unresolved Findings for Recovery Certified Search.  
 
 
 
 
Title
 
To authorize the Director of Public Utilities to enter into an agreement with JD Power Systems LLC for  the removal, transport and installation of a 75 KW generator  for the Division of Sewerage and Drainage and to authorize the expenditure of $32,499.00 from the Sewerage System Operating Fund. ($32,499.00)
 
 
 
Body
 
WHEREAS, The Jackson Pike Wastewater Treatment Plant has a need for a 75 KW generator to be removed and transported to the W. Whittier Street location, and
 
WHEREAS, the generator will be used to power gates at the Whittier Street storm tanks, and
 
WHEREAS, the current generator at the Whittier Street storm tanks has reached it's useful life and is not operating properly to ensure proper gate operations, and
 
WHEREAS, because of the age of the current equipment the generator could fail to perform completely. The Jackson Pike Wastewater Treatment Plant has a larger generator that can be removed and installed at the Whittier Street locatin. It is more cost effective for the Division of Sewerage and Drainage to transport the larger generator then to purchase a new piece of equipment, and
 
WHEREAS, The Director of Public Utilities opened formal bids on August 5, 2009. Four (4) bids were received, and the award was made to lowest, responsive and responsible bidder, JD Power Systems LLC, now, now, therefore
 
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
 
Section 1. That the Director of Public Utilities be and is hereby authorized to enter into an agreement with JD Power Systems LLC for the removal, transport and installation of a 75 KW generator for the Division of Sewerage and Drainage.
 
Section 2. That the expenditure of $32,499.00or so much thereof as may be needed, be and the same hereby is authorized from the Sewerage System Operating Fund, Fund No. 650 as follows:
 
OCA 604819
Object Level 1: 03
Object Level 03: 3390
 
Section 3. That this Ordinance shall take effect and be in force from and after the earliest period allowed by law.