Legislation Details

File #: 1730-2026    Version: 1
Type: Ordinance Status: Consent
File created: 6/2/2026 In control: Neighborhoods, Recreation, & Parks Committee
On agenda: 6/29/2026 Final action:
Title: To authorize the Director of the Recreation and Parks Department to modify an existing contract with CK Construction Group, Inc. for the Kilbourne Run Sports Park Improvements Project; to authorize the transfer of $242,500.00 between the General Fund Income Tax Set Aside Subfund and the Recreation and Parks Bond Fund; to authorize the appropriation of $242,500.00 in the Income Tax Set Aside Subfund and Recreation and Parks Voted Bond Fund; to authorize the expenditure of $242,500.00 from the Recreation and Parks Voted Bond Fund; and to declare an emergency. ($242,500.00)
Attachments: 1. Legislation - Kilbourne Run Sports Park Improvements Construction Manager at Risk - Modification 4 - FINAL - ATTACHMENT REVISED.pdf, 2. Business_Details - CK ConstructIon Group - 053025.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

Explanation

 

Background: This ordinance authorizes the Director of the Recreation and Parks Department to modify the existing contract with CK Construction Group for the Kilbourne Run Sports Park Improvements Project. The modification amount is $215,000.00 with a contingency of $25,000.00. An additional $2,500.00 is being authorized for interdepartmental inspections and fees for a total of $242,500.00 being authorized by this ordinance.

 

Kilbourne Run Sports Park, located at 4625 Westerville Road, is a soccer specific facility that stretches over 62 acres with 35 of those acres dedicated to athletic space. This is a Construction Manager at Risk (CMR) Contract. This delivery method will save the project money and time compared to a traditional Design-Bid-Build delivery. This is one of a few planned modifications for the project's guaranteed maximum price. This modification will cover costs for Phase 2 construction which includes a traffic roundabout, park frontage, and signage.

 

This modification will include the addition of an 8-foot fence around the full-size grass fields 7, 8 and 9. There will also be a 4-foot fence around the full-size grass field 10. Fields 7, 8 and 9 are intended to be open to permit only usage and field 10 will be open to community play that does not require a permit. The additional work will also include renovation to the Kilbourne Run Gateway sign that was damaged by an errant vehicle. The original project completion date of the project was January 30, 2026. The modified project completion date, as a result of the proposed modification, will be September 1, 2026.

 

Amount of Additional Funds: $242,500.00

 

Why Additional Services Were Not Foreseen: Permanent fencing around the grass fields was not initially foreseen because the City did not predict the need to physically protect the field from errant motorized vehicles such as cars, 4-wheelers, and dirt bikes. Protecting the fields ensures the grass will successfully establish and increase the longevity of the natural playing surface. Additionally, the City did not anticipate a vehicle hitting the gateway sign and damaging it.

 

Why It Is Not In The Best Interest For The City To Award Additional Services Through Another Procurement Process: The City is maximizing the efficiency of this additional scope by awarding this service to the current vendor. The existing vendor has the most intimate understanding of the underground utilities that will need to be avoided. Also, the existing vendor is already mobilized on site, thus reducing additional overhead costs that would be associated with a new vendor.

 

How The Price For The Additional Services Was Determined: The price for additional services was determined by obtaining prices from the existing fence contractor within the project team and comparing their price to other vendor prices to ensure the cost is competitive. This method aligns with the best practices of using a Construction Manager at Risk (CMR) contract. The price for sign repair was determined by getting estimates from the subcontractors who built the original sign.

 

Principal Parties:

CK Construction Group

6245 Westerville Road

Westerville, Ohio 43081

James Negron, (614) 901-8844

Contract Compliance Number: 006875

Contract Compliance Expiration Date: Pending

 

Emergency Justification: Emergency action is requested in order to install the permanent fence before the temporary fence is scheduled to be removed in order to protect the growth of the new grass on the irrigated grass fields. 

 

Benefits to the Public: This project benefits the public by significantly enhancing the soccer amenities and outdoor sports programs the City can offer to the public. Additionally, this modification will improve the roadway and right of way, creating safer access into the park for motorists and pedestrians.

 

Community Input/Issues: Input for this project was primarily gathered through the Columbus Community Sports Park feasibility study conducted by Conventions, Sports, and Leisure International (CSL) and managed by the Recreation and Parks Department in the summer of 2021. An open house for the project was conducted in the fall of 2023. Input was also received by internal Recreation and Parks stakeholders and the Mayor’s Office.

 

Area(s) Affected: Northland (35)

 

Master Plan Relation: This project will support the Recreation and Parks Master Plan by helping to update sports related parks, expanding amenities to appeal to a more diversified audience, and updating five neighborhood parks per year.

 

Fiscal Impact: The expenditure of $35,730,125.00 was legislated for the Kilbourne Run Sports Park Improvements Project by Ordinances 1801-2023, 3061-2023, 1374-2024, and 1276-2025. This ordinance will provide funding that will modify the previously authorized amount by $242,500.00. $242,500.00 is budgeted and available from within the Recreation and Parks Voted Bond Fund 7712 to meet the financial obligations of this expenditure. The aggregate total amount authorized, including this modification, is $35,972,625.00. $242,500.00 of the funds will not be available to the Recreation and Parks Department until the proceeds of the 2025-2026 bond sale are available at a future date. Therefore, it is necessary to certify the required funds against the General Fund 1000, Income Tax Set Aside Subfund 100099. Upon the sale of bonds, this will be reimbursed.

 

Title

 

To authorize the Director of the Recreation and Parks Department to modify an existing contract with CK Construction Group, Inc. for the Kilbourne Run Sports Park Improvements Project; to authorize the transfer of $242,500.00 between the General Fund Income Tax Set Aside Subfund and the Recreation and Parks Bond Fund; to authorize the appropriation of $242,500.00 in the Income Tax Set Aside Subfund and Recreation and Parks Voted Bond Fund; to authorize the expenditure of $242,500.00 from the Recreation and Parks Voted Bond Fund; and to declare an emergency. ($242,500.00)

 

Body

 

WHEREAS, it is necessary to authorize the Director of the Recreation and Parks to modify an existing contract with CK Construction Group, Inc. for the Kilbourne Run Sports Park Improvements Project; and

 

WHEREAS, the City anticipates incurring certain Original Expenditures (as defined in Section 1.150-2(c) of the Treasury Regulations (the "Treasury Regulations") promulgated pursuant to the Internal Revenue Code of 1986, as amended, with respect to the construction of the project described in this ordinance (the "Project"); and

 

WHEREAS, it is necessary to authorize the transfer of $242,500.00 between the General Fund 1000, Income Tax Set Aside Subfund 100099, and the Recreation and Parks Bond Fund, Fund 7712; and

 

WHEREAS, funds will need to be appropriated within the General Fund 1000, Income Tax Set Aside Subfund 100099 and within the Recreation and Parks Bond Fund, Fund 7712; and

 

WHEREAS, the City will reimburse the General Fund 1000, Income Tax Set Aside Subfund 100099; and

 

WHEREAS, this transfer should be considered as a temporary funding method; and

 

WHEREAS, the aggregated principal amount of obligations which the City will issue to finance this project is presently expected not to exceed $242,500.00; and

 

WHEREAS, an emergency exists in the usual daily operations of the Recreation and Parks Department in that it is immediately necessary to authorize the Director to modify the existing contract with CK Construction Group in order to install the permanent fence before the temporary fence is scheduled to be removed in order to protect the growth of the new grass on the irrigated grass fields, all for the immediate preservation of the public health, peace, property, and safety; NOW, THEREFORE,

 

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:

 

SECTION 1. That the Director of the Recreation and Parks Department be and is hereby authorized to modify an existing contract with CK Construction Group, Inc. for the Kilbourne Run Sports Park Improvements Project.

 

SECTION 2. That the funds necessary to carry out the purpose of this ordinance are hereby deemed appropriated, and the City Auditor shall establish such accounting codes as necessary.

 

SECTION 3. That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this ordinance.

 

SECTION 4. That the City Auditor is hereby authorized to transfer the unencumbered balance in a project account to the unallocated balance account within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies are no longer required for said project.

 

SECTION 5. That from the unappropriated monies and from all monies estimated to come into said funds from any and all sources and unappropriated for any other purpose during the fiscal year ending December 31, 2026, the sum of $242,500.00 is appropriated in General Fund 1000, Income Tax Set Aside Subfund 100099, in Object Class 10 Transfer Out Operating, and in Fund 7712, Recreation and Parks Bond Fund, in Object Class 06 Capital Outlay per the account codes in the attachment to this ordinance.

 

SECTION 6. That the transfer of $242,500.00, or so much thereof as may be needed, is hereby authorized between the General Fund 1000, Income Tax Set Aside Subfund 100099, and the Recreation and Parks Bond Fund, Fund 7712, per the account codes in the attachment to this ordinance.

 

SECTION 7. That the City Auditor is hereby authorized to transfer said funds to the Recreation and Parks Voted Bond Fund 7712, at such time as is deemed necessary by the City Auditor, and to expend said funds, or so much thereof as may be necessary.

 

SECTION 8. That upon obtaining other funds from the 2025-2026 Bond Sale for the City of Columbus, the City Auditor is hereby authorized and directed to repay the General Fund 1000, Income Tax Set Aside Subfund 100099 the amount transferred under Section 9.

 

SECTION 9. That the City intends that this ordinance constitutes an "official intent" for purposes of Section 1.150 2(e) of the Treasury Regulations, and that the City reasonably expects to reimburse itself for certain Original Expenditures incurred with respect to the Project from the proceeds of obligations to be issued by the City in a principal amount currently estimated to be $242,500.00 (the "Obligations"). The City intends to make a reimbursement allocation on its books for the Original Expenditures not later than eighteen months following the later to occur of the date of the Original Expenditure to be reimbursed or the date the Project for which such Original Expenditures were made is "placed in service" within the meaning of Treasury Regulations Section 1.150 2(c). Upon the issuance of the Obligations, the proceeds of such Obligations shall be used to reimburse the fund from which the advance for costs of the Project will be made.

 

SECTION 10. That for the purpose stated in Section 1, the expenditure of $242,500.00, or so much thereof as may be necessary to pay the cost thereof, be and is hereby authorized from the Recreation and Parks Voted Bond Fund 7712 in object class 06 Capital Outlay per the accounting codes in the attachments to this ordinance. 

 

SECTION 11. That for the reasons stated in the preamble hereto, which is made a part hereof, this ordinance is hereby declared to be an emergency measure and shall take effect and be in force from and after its passage and approval by the Mayor or ten days after passage if the Mayor neither approves nor vetoes the same.