Title: To authorize the transfer of funds within the Streets and Highways Bond Fund; to authorize the Director of Public Service to enter into contract with Complete General Construction Company for the East Franklinton Pedestrian Improvements project; to authorize the expenditure of up to $7,971,146.96 from the Streets and Highways Bond Fund for the project; and to declare an emergency. ($7,971,146.96)
Indexes: MBE Participation, WBE Participation
Attachments: 1. Ord. 1855-2024 Accounting Template, 2. Ord. 1855-2024 Project Boundary Map, 3. Ord. 1855-2024 Subcontractors

Explanation

1.  BACKGROUND

This ordinance authorizes the Director of Public Service to enter into contract with Complete General Construction Company for the East Franklinton Pedestrian Improvements project and to provide payment for construction, construction administration and inspection services. 

 

This contract includes improvements to State Street, Broad Street, and McDowell Street in the East Franklinton area.  Improvements include construction of concrete and paver sidewalks, new curbs, new traffic signal, storm sewer, street trees, festival electric facilities, street lighting, and pavement improvements.  A decorative lighting system will be installed under the existing railroad bridges on State Street between Lucas Street and Startling Street, and other work as may be necessary to complete the contract in accordance with the plans and specifications set forth in the Bid Submittal Documents.

 

The estimated Notice to Proceed date is July 26, 2024.  The project was let by the Office of Support Services through Vendor Services and Bid Express.  Two bids were received on May 30, 2024, (both majority) and tabulated as follows:  

     

Company Name                                            Bid Amount         City/State           Majority/ODI Certification  

Complete General Construction Company  $7,246,497.24                         Columbus, OH                      Majority

Trucco Construction Co., Inc.                                    $8,353,554.85                         Delaware, OH                     Majority

 

Award is to be made to Complete General Construction Company as the lowest responsive and responsible and best bidder for their bid of $7,246,497.24.  The amount of construction administration and inspection services will be $724,649.72.  The total legislated amount is $7,971,146.96.

 

Searches in the System for Award Management (Federal) and the Findings for Recovery list (State) produced no findings against Complete General Construction Company.

 

The certification of Complete General Construction Company and all associated subcontractors was in good standing at the time the bid was awarded.

 

As part of their bid Complete General Construction Company has proposed the following subcontractors to work on the project:

 

Company Name                                                  City/State                                                               Majority/ODI Certification     

CAP-STONE & Associates, Inc.                                          Columbus, Ohio                                                               WBE

Environmental Management, Inc.                     Plain City, Ohio                                                                                    MAJ                     

Griffin Pavement Striping, LLC                                          Columbus, Ohio                                                               MAJ                     

Material Hauling, LTD                                                               Westerville, Ohio                                                               MBE

Bridges Bros. Trucking L.L.C.                                          Columbus, Ohio                                                               MBE

Goldtech of Ohio, Inc.                                                               Hilliard, Ohio                                                                                    MBE

 

2. CONTRACT COMPLIANCE INFORMATION

The contract compliance number for Complete General Construction Company is CC6056 and expires 5/10/2025.

 

3. PRE-QUALIFICATION STATUS

Complete General Construction Company and all proposed subcontractors have met code requirements with respect to pre-qualification, pursuant to relevant sections of Columbus City Code Chapter 329.

 

 

4.  FISCAL IMPACT

Funding for this contract is available and appropriated within Streets and Highways Bond Fund, Fund 7704. 

 

5. MINORITY AND WOMAN OWNED BUSINESS ENTERPRISE & SMALL LOCAL BUSINESS ENTERPRISE PROGRAM

This contract was bid with a City of Columbus MBE/WBE Program goal of 15% as assigned by the City’s Office of Diversity and Inclusion (ODI).  Failure by the contractor to meet this goal subjects the contractor to the Penalties for Non-Compliance as described in the “City’s Minority and Women-Owned Business Enterprise & Small Local Business Enterprise Program Manual” and in the “City of Columbus MBE/WBE Program Special Provision” that were part of the bid documents for this contract.

 

6. EMERGENCY DESIGNATION

Emergency action is requested to expedite this contract so that the signal aspect of this project may be realized and governed by updated standards, policies, and practices, enhancing the safety of the traveling public.

 

Title

To authorize the transfer of funds within the Streets and Highways Bond Fund; to authorize the Director of Public Service to enter into contract with Complete General Construction Company for the East Franklinton Pedestrian Improvements project; to authorize the expenditure of up to $7,971,146.96 from the Streets and Highways Bond Fund for the project; and to declare an emergency. ($7,971,146.96)

 

Body

WHEREAS, the Department of Public Service is engaged in the East Franklinton Pedestrian Improvements project; and 

 

WHEREAS, the work for this project consists of improvements to State Street, Broad Street, and McDowell Street in the East Franklinton area.  Improvements include construction of concrete and paver sidewalks, new curbs, new traffic signal, storm sewer, street trees, festival electric facilities, street lighting, and pavement improvements.  A decorative lighting system will be installed under the existing railroad bridges on State Street between Lucas Street and Startling Street; and other work as may be necessary to complete the contract in accordance with the plans and specifications set forth in the Bid Submittal Documents; and

 

WHEREAS, Complete General Construction Company will be awarded the contract for the East Franklinton Pedestrian Improvements project; and

 

WHEREAS, the Department of Public Service requires funding to be available for the East Franklinton Pedestrian Improvements project for construction expense along with construction administration and inspection services; and

 

WHEREAS, it is necessary for Council to authorize a transfer of funds within Fund 7704, the Streets and Highways Bond Fund, to establish sufficient cash to pay for the project; and

 

WHEREAS, this contract opportunity was submitted to the City’s Office of Diversity and Inclusion (ODI) for review and assignment of an MBE/WBE goal prior to bidding; and

 

WHEREAS, this contract was bid with a City of Columbus MBE/WBE Program goal of 15% as assigned by the City’s Office of Diversity and Inclusion (ODI); and

 

WHEREAS, failure by the contractor to meet this goal subjects the contractor to the Penalties for Non-Compliance; and

 

WHEREAS, an emergency exists in the usual daily operation of the Department of Public Service in that it is immediately necessary to authorize the Director to enter into contract with Complete General Construction Company to ensure the safety of the travelling public and so that the signal aspect of this project may be released and governed by updated standards, policies, and practices to enhance safety of traveling public, all for the immediate preservation of the public health, peace, property, safety and welfare; now, therefore

 

BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:

 

SECTION 1.  That the transfer of $1,658,868.00, or so much thereof as may be needed, is hereby authorized within Fund 7704 (Streets and Highways Bond Fund), from Dept-Div 5912 (Design and Construction), Project P530058-100005 (NCR-Public Infrastructure), Object Class 06 (Capital Outlay) to Dept-Div 5912 (Design and Construction), Project P440104-100036 (East Franklinton Gravity 2.0 Pedestrian Improvements), Object Class 06 (Capital Outlay) between projects per the account codes in the attachment to this ordinance.

 

SECTION 2.  That the transfer of $1,686,324.96, or so much thereof as may be needed, is hereby authorized within Fund 7704 (Streets and Highways Bond Fund), from Dept-Div 5912 (Design and Construction), Project P530058-100005 (NCR-Public Infrastructure), Object Class 06 (Capital Outlay) to Dept-Div 5912 (Design and Construction), Project P440104-100036 (East Franklinton Gravity 2.0 Pedestrian Improvements), Object Class 06 (Capital Outlay) between projects per the account codes in the attachment to this ordinance.

 

SECTION 3.  That the Director of Public Service be and is hereby authorized to enter into a construction services contract with Complete General Construction Company, 1221 E. Fifth Avenue, Columbus, Ohio 43219, for the East Franklinton Pedestrian Improvements project in the amount of up to $7,246,497.24 in accordance with the specifications and plans on file in the Office of Support Services, which are hereby approved; and to pay for necessary construction administration and inspection costs associated with the project up to a maximum of $724,649.72. 

 

SECTION 4.  That the expenditure of $7,971,146.96, or so much thereof as may be needed, is hereby authorized in Fund 7704 (Streets and Highways Bond Fund), Dept-Div 5912 (Design and Construction), Project P440104-100036 (East Franklinton Gravity 2.0 Pedestrian Improvements), in Object Class 06 (Capital Outlay) per the accounting codes in the attachment to this ordinance.

 

SECTION 5.  Funds are hereby deemed appropriated and expenditures and transfers authorized to carry out the purposes of this ordinance and the City Auditor shall establish such accounting codes as necessary.

 

SECTION 6.  That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts or contract modifications associated with this ordinance.

 

SECTION 7.  That the City Auditor is hereby authorized to transfer the unencumbered balance in a project account to the unallocated balance account within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies are no longer required for said project.

 

SECTION 8.  That for the reasons stated in the preamble hereto, which is hereby made a part hereof, this ordinance is hereby declared to be an emergency measure and shall take effect and be in force from and after its passage and approval by the Mayor or ten days after passage if the Mayor neither approves nor vetoes the same.