File #: 1873-2005    Version: 1
Type: Ordinance Status: Passed
File created: 10/31/2005 In control: Utilities Committee
On agenda: 12/12/2005 Final action: 12/14/2005
Title: To authorize the Director of Public Utilities to modify the contract with Metcalf & Eddy of Ohio, Inc., for Professional Engineering Services for the Dublin Road Water Plant Treatment Capacity Increase Study and Evaluation, for the Division of Water, to amend the 2005 C.I.B., to authorize the City Auditor to transfer funds within the Waterworks Enlargement Voted 1991 Bonds Fund, to authorize the City Auditor to transfer funds within the Water Limited Fund, to authorize the expenditure of $3,242,874.90 from the Water Works Enlargement Voted 1991 Bonds Fund, and to authorize the expenditure of $137,363.10 from the Water Limited Fund ($3,380,238.00)
Attachments: 1. DRWP_VicMap.pdf, 2. DRWP Cap Inc Scope.pdf, 3. Mod 1 Scope of Services 102505.pdf, 4. DRWP Pilot Schedule 110205.pdf, 5. Information to be included in Contracting Legislation 05-084.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
12/14/20051 MAYOR Signed  Action details Meeting details
12/14/20051 ACTING CITY CLERK Attest  Action details Meeting details
12/12/20051 Columbus City Council ApprovedPass Action details Meeting details
12/12/20051 COUNCIL PRESIDENT Signed  Action details Meeting details
12/5/20051 Columbus City Council Read for the First Time  Action details Meeting details
11/18/20051 Auditor Reviewer Reviewed and Approved  Action details Meeting details
11/18/20051 CITY AUDITOR Reviewed and Approved  Action details Meeting details
11/18/20051 Utilities Drafter Sent for Approval  Action details Meeting details
11/18/20051 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
11/18/20051 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
11/15/20051 Utilities Drafter Sent for Approval  Action details Meeting details
11/10/20051 Finance Reviewer Reviewed and Approved  Action details Meeting details
11/10/20051 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
11/9/20051 EBOCO Reviewer Reviewed and Approved  Action details Meeting details
11/9/20051 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
11/9/20051 Utilities Drafter Sent for Approval  Action details Meeting details
11/8/20051 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
11/8/20051 Utilities Drafter Sent for Approval  Action details Meeting details
11/2/20051 Utilities Drafter Sent for Approval  Action details Meeting details
11/2/20051 Utilities Reviewer Sent for Approval  Action details Meeting details
11/1/20051 Utilities Drafter Sent for Approval  Action details Meeting details
11/1/20051 Utilities Reviewer Reviewed and Approved  Action details Meeting details
10/31/20051 Utilities Drafter Sent for Approval  Action details Meeting details
Explanation
 
BACKGROUND: As per the recommendations of the Water Beyond 2000 project, this contract will provide for a production study to evaluate the feasibility and changes required to increase current design capacity of the Dublin Road Water Plant from 65 mgd to 90 mgd, while maintaining water quality and compliance with existing and future regulatory requirements.  Full scale and pilot scale demonstrations are required for Ohio EPA for approval. Previous legislation authorized expenditure for the engineering evaluation.  This legislation authorizes the expenditure for the demonstration, including operation of the pilot plant.  
 
CC  329.16 CONTRACT MODIFICATIONS:
1.      Amount of additional funds to be expended under this modification: $3,380,238.00
2.      The services identified to be included in this contract modification were anticipated at the time of executing  the original contract.  The legislation for the original contract indicated the intent to seek approval for this contract modification.
3.      The work under this contract modification is a continuation of work previously performed by the Consultant; therefore, no other processes were used for procurement of these services.
4.      The cost of this modification is based on material and labor, and was negotiated between the Consultant and the City, as documented by the Consultant's quotation letters, and verified by the Project Engineer.
 
CONTRACT AMOUNT:
Original contract amount                        $485,125.00      
Modification No.1                           $3,380,238.00      
New contract amount                        $3,865,363.00      
 
FISCAL IMPACT:  The original authorization for expenditures for this project occurred August 19, 2003 in the amount of $485,125.00.  This project was included in the 2005 C.I.B and $3,000,000.00 was budgeted. Funding for this project is being provided by companion legislation in the amount of $2,077,538.82.
 
 
CONTRACT COMPLIANCE NUMBER: 22-2581306
 
 
 
Title
 
To authorize the Director of Public Utilities to modify the contract with Metcalf & Eddy of Ohio, Inc., for Professional Engineering Services for the Dublin Road Water Plant Treatment Capacity Increase Study and Evaluation, for the Division of Water, to amend the 2005 C.I.B., to authorize the City Auditor to transfer funds within the Waterworks Enlargement Voted 1991 Bonds Fund, to authorize the City Auditor to transfer funds within the Water Limited Fund, to authorize the expenditure of $3,242,874.90 from the Water Works Enlargement Voted 1991 Bonds Fund, and to authorize the expenditure of $137,363.10 from the Water Limited Fund ($3,380,238.00)
 
 
 
Body
 
WHEREAS: Contract No. EL-003668 was authorized by Ordinance No. 0987-2003,  passed July 7, 2003, was executed August 19, 2003 and approved by the City Attorney on September 2, 2003, to provide for Professional Engineering Services for the Dublin Road Water Plant Treatment Capacity Increase Study and Evaluation, and
 
WHEREAS: It is necessary to modify Contract No. EL-003668 to provide for full scale and pilot scale demonstrations which are required for Ohio EPA for approval to increase current design capacity of the Dublin Road Water Plant from 65 mgd to 90 mgd, and
 
WHEREAS: The services identified to be included in this contract modification were anticipated at the time of executing the original contract.  The legislation for the original contract indicated the intent to seek approval for this contract modification., and
 
WHEREAS: This modification provides for an increase of $3,380,238.00 to this contract, and
 
WHEREAS: It is necessary to authorize the Director of Public Utilities to modify Contract No. EL-003668  , for the Dublin Road Water Plant Treatment Capacity Increase Study and Evaluation for the preservation of public health, peace, property and safety, now, therefore;
 
 
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS
 
Section 1. That the Director of Public Utilities be and is hereby authorized to modify Contract No. EL-003668 with Metcalf & Eddy of Ohio, Inc. in the amount of $3,380,238.00 for Professional Engineering Services necessary for the Dublin Road Water Plant Treatment Capacity Increase Study and Evaluation for the Division of Water, Department of Public Utilities, Project No. 690428, Contract No. 1009, terms and conditions of which are on file in the office of the Division of Water.
 
Section 2. That for the purpose of paying the cost thereof, the expenditure of $3,242,874.90 is hereby authorized from Waterworks Enlargement Voted 1991 Bonds, Fund No. 606, Department of Public Utilities, Division of Water, Dept./Division No. 60-09, Object Level Three 6682, Project No. 690428, OCA Code 606428.
 
Section 3. That for the purpose of paying the cost thereof, the expenditure of $137,363.10 is hereby authorized from Water Limited Fund, Fund No. 607, Department of Public Utilities, Division of Water, Dept./Division No. 60-09, Object Level Three 6682, Project No. 690428, OCA Code 607428
 
Section 4. That $117,776.00 is hereby appropriated for the Waterworks Enlargement Voted 1991 Bonds, Fund No. 606, Department of Public Utilities, Division of Water, Dept./Division No.  60-09, Object Level Three 6682, Project No. 690331, OCA 606331.
 
Section 5. That the City Auditor is hereby authorized to transfer the unencumbered balance in a project account to the unallocated balance account within the same fund upon receipt of certification by the Director of the Department administering said project; that the project has been completed and the monies are no longer required for said project except that no transfer shall be so made from a project account funded by monies from more than one source.
 
Section 6.  That the City Auditor is hereby authorized and directed to transfer funds within the Waterworks Enlargement Voted 1991 Bonds Fund, Fund No. 606, Department of Public Utilities, Division of Water, as follows:
 
From:
      690026      Miscellaneous Water Facilities,
                  OCA Code 642900                              $19,626.51
From:
      690236      Water Main Rehabilitation,
                  OCA Code 642900                              $19,473.98
From:
      690328      Parsons Avenue Water Plant,
                  OCA Code 642900                              $3,414.00
From:
      690331      HCWP Lagoons 1 & 2 Sludge Removal,
                  OCA Code 606331                              $117,776.00
From:
      690359      South Wellfield Expansion,
                  OCA Code 642900                              $9,971.00
From:
      690379      DRWP Chlorine Storage Improvements,
                  OCA Code 642900                              $697,196.83
From:
      690394      Water Meter Renewal,
                  OCA Code 606394                              $1,715.00
From:
      690403      Champion Avenue 20" Water Main,
                  OCA Code 606403                              $24,000.00
From:
      690404      Livingston Avenue 24" Water Main,
                  OCA Code 606404                              $42,000.00
From:
      690413      HCWP Automation Upgrade,
                  OCA Code 606413                              $41,162.76
From:
      690426      Taylor Road Storage Tank,
                  OCA Code 606426                              $14,000.00
From:
      690474      Morse Road 36" Water Main,
                  OCA Code 606474                              $175,000.00
 
To:
      690428      DRWP Treatment Capacity Increase Study and Evaluation,
                  OCA Code 606428                              $1,165,336.08
 
Section 7.  That the City Auditor is hereby authorized and directed to transfer funds within the Water Limited Fund, Fund No. 607, Department of Public Utilities, Division of Water, as follows:
 
From:
      690405      Refugee Road 16" Water Main,
                  OCA Code 642926                              $135,060.80
From:
      690406      Mount Vernon Avenue 12" Water Main,
                  OCA Code 642926                              $2,302.30
 
To:
      690428      DRWP Treatment Capacity Increase Study and Evaluation,
                  OCA Code 607428                              $137,363.10
 
Section 8.  That Section 1, Public Utilities/Water 60-09 of Ordinance 1070-2005 is hereby amended as follows:
 
PROJECT                                                                                                2005
     NO.                 PROJECT                               BUDGET
  690428      DRWP Treatment Capacity Increase Study and Evaluation      $3,380,238 *(1)*
  690331      HCWP Lagoons 1 & 2 Sludge Removal                             $5,281,992 *(2)*
 
Section 9.  That this ordinance shall take effect and be in force from and after the earliest period allowed by law.
 
                           2005                    2005
                     ORIGINAL              AMENDED
                      BUDGET                BUDGET                  COMMENTS
*(1)*                  $3,000,000              $3,380,238            AUTHORITY INCREASED
*(2)*                         $5,662,230              $5,281,992            AUTHORITY DECREASED