header-left
File #: 0248-2006    Version: 1
Type: Ordinance Status: Passed
File created: 1/30/2006 In control: Utilities Committee
On agenda: 2/27/2006 Final action: 3/1/2006
Title: To authorize the Director of Public Utilities to enter into contract with the Complete General Construction Company, for the construction of the Frebis/Ellsworth Sewer Improvements Project; to authorize the appropriation of $454,728.91 and the expenditure of $390,452.40 from the Ohio Water Pollution Control Loan Fund; to amend the 2005 Capital Improvements Budget; for the Division of Sewerage and Drainage; and to declare an emergency. ($390,452.40)
Attachments: 1. ORD0248-2006MAP.pdf, 2. ORD0248-2006LegislationInformation.pdf, 3. ORD0248-2006BidTab.pdf, 4. ORD0248Q2006ualityContractor.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
3/1/20061 CITY CLERK Attest  Action details Meeting details
2/28/20061 MAYOR Signed  Action details Meeting details
2/27/20061 Columbus City Council ApprovedPass Action details Meeting details
2/27/20061 COUNCIL PRESIDENT Signed  Action details Meeting details
2/8/20061 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
2/8/20061 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
2/7/20061 EBOCO Reviewer Reviewed and Approved  Action details Meeting details
2/7/20061 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
2/7/20061 Utilities Drafter Sent for Approval  Action details Meeting details
2/6/20061 Auditor Drafter Sent for Approval  Action details Meeting details
2/6/20061 Auditor Reviewer Reviewed and Approved  Action details Meeting details
2/6/20061 CITY AUDITOR Reviewed and Approved  Action details Meeting details
2/6/20061 Utilities Drafter Sent for Approval  Action details Meeting details
2/3/20061 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
2/3/20061 Utilities Drafter Sent for Approval  Action details Meeting details
2/2/20061 Utilities Drafter Sent for Approval  Action details Meeting details
2/2/20061 Utilities Reviewer Reviewed and Approved  Action details Meeting details
2/2/20061 Utilities Reviewer Sent for Approval  Action details Meeting details
2/2/20061 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
2/2/20061 Utilities Drafter Sent for Approval  Action details Meeting details
2/2/20061 Finance Reviewer Reviewed and Approved  Action details Meeting details
2/2/20061 Finance Reviewer Reviewed and Approved  Action details Meeting details
2/1/20061 Utilities Drafter Sent for Approval  Action details Meeting details
Explanation
1.  BACKGROUND:
This legislation authorizes the Director of Public Utilities to execute a contract with the Complete General Construction Company, Inc., for the construction of the Frebis/Ellsworth Sewer Improvements Project.  This project will construct infrastructure modifications to the sanitary and storm systems; and will rehabilitate sections of sanitary sewer lines serving homes within the project area that is located in the Driving Park Community.   (See Legislation Attachment)
 
2.  FISCAL IMPACT:
This legislation appropriates a total of $454,728.91 from the OWDA Loan that will be used to fund this contract and the construction administration and inspection services contract.  $390,452.40 is for the cost of construction services.  The remaining $64,276.51 (Obj. Level 3 Request) is for the cost of construction administration and inspection services that will be requested within a separate professional engineering services contract award with DLZ Ohio, Inc.
 
3.  EMERGENCY DESIGNATION:
The  Division of Sewerage and Drainage is requesting City Council to consider this legislation an emergency measure in order to allow for the immediate commencement of this contract work that is necessary to rehabilitate sanitary sewer infrastructure serving a residential area in the Driving Park community, pursuant to ensuring the continued operation of this vital sanitary sewer infrastructure.
 
Title
To authorize the Director of Public Utilities to enter into contract with the Complete General Construction Company, for the construction of the Frebis/Ellsworth Sewer Improvements Project; to authorize the appropriation of $454,728.91 and the expenditure of $390,452.40 from the Ohio Water Pollution Control Loan Fund; to amend the 2005 Capital Improvements Budget; for the Division of Sewerage and Drainage; and to declare an emergency.  ($390,452.40)
 
Body
WHEREAS, one competitive bid for the construction of the Frebis/Ellsworth Sewer Improvements Project was received on November 30, 2005, and
 
WHEREAS, the Ohio Water Development Authority approved a loan to the City of Columbus on January 26, 2006, in the principal amount of $3,477,724.39, identified as OWDA Loan No. 4442, for the Frebis/Ellsworth Sewer Improvements Project; the Livingston Ave. Sewer Improvements Project; and the Forest Street Sewer Improvements Project; with eligible costs including the construction contract, and the construction administration services contract; and
 
WHEREAS, it is immediately necessary for the City Council to both appropriate the  proceeds from the aforementioned loan agreement and to authorize the expenditure of funds from the Ohio Water Pollution Control Loan Fund for the construction of the Frebis/Ellsworth Sewer Improvements Project; and
 
WHEREAS, an emergency exists in the usual daily operation of the Division of Sewerage and Drainage, in that it is necessary for this City Council to authorize the Director of Public Utilities to execute a contract for the construction of the Frebis/Ellsworth Sewer Improvements Project; to appropriate and authorize the expenditure of the proceeds from the aforementioned loan, all of which is necessary to allow for the immediate rehabilitation of this aging and structurally deficient sanitary sewer infrastructure, for the preservation of the public health, peace, property, and safety; now, therefore,
 
BE IT ORDAINED BY THE COUNCIL OF THE CITY OF COLUMBUS:
 
Section 1.  That the proceeds from the Ohio Water Development Authority Loan No. 4442, that provides funding for the for the Frebis/Ellsworth Sewer Improvements Project; and funds from the unappropriated monies in Fund 666, the amount of $454,728.91 for the cost of construction and construction administration services, is hereby appropriated to the Division of Sewerage and Drainage, Division 60-05, Fund No. 666:
Div.: 60-05| Fund 666| Proj: 650634| OCA Code 666634| Obj. Level 3: 6630| $390,452.40
Div.: 60-05| Fund 666| Proj: 650634| OCA Code 666634| Obj. Level 3: 6676| $64,276.51
 
Section 2.  That the Director of Public Utilities be, and hereby is, authorized to award and execute a contract for the construction of the Frebis/Ellsworth Sewer Improvements Project with the lowest, best, responsive and responsible bidder, Complete General Construction Company, Inc., 1221 E. Fifth Ave., Columbus, Ohio 43219, in the amount of $390,452.40, in accordance with the terms and conditions of the Contract on file in the Sewer System Engineering Section Office of the Division of Sewerage and Drainage.
 
Section 3.  That for the purpose of paying the cost of construction contract, the expenditure of $390,452.40 or as much thereof as may be needed, is hereby authorized from the Ohio Water Pollution Control Loan Fund as follows:
Div.: 60-05| Fund 666| Proj. 650634| OCA Code 666634| Obj. Level 3: 6630| $390,452.40
 
Section 4.  That the 2005 Capital Improvements Budget Ordinance No. 1070-2005 is hereby amended as follows, to provide sufficient sanitary infrastructure improvements budget authority as requested within Section 1 herein.
 
CURRENT:
650634:  Frebis/Ellsworth Sewer Improve. | $0.00 (OWDA)
      
AMENDED TO:
650634:  Frebis/Ellsworth Sewer Improve. | $454,728.91 (OWDA)
 
Section 5.  That for the reasons stated in the preamble hereto, which is hereby made a part hereof, this ordinance is hereby declared to be an emergency measure and shall take effect and be in force from and after its passage and approval by the Mayor, or ten days after passage if the Mayor neither approves nor vetoes the same.