Title: To authorize the Director of Public Utilities to modify (Mod #1) an existing engineering agreement with CDM Smith, Inc. for the Blueprint Linden, Agler / Berrell Area project; to authorize the transfer of $783,791.76 within and the expenditure of up to $1,183,791.76 from the Sanitary Sewer General Obligation Bond Fund (G.O.); and to amend the 2016 Capital Improvements Budget. ($1,183,791.76)
Attachments: 1. Ord 3010-2016 SWIF 5. Schedule 2A-1 Subcontractor Work ID Form (Linden Mod #1)_CDM_Smith, 2. Ord 3010-2016 Director's Legislation Info Sheet (Linden Mod#1), 3. Ord 3010-2016 DAX Financial Coding Agler Berrell Mod 1

Explanation

 

1.   BACKGROUND: This legislation authorizes the Director of Public Utilities to modify (Mod #1) an engineering agreement with CDM Smith, Inc. for the Blueprint Linden, Agler / Berrell Area Project, CIP 650870-100703. The scope of work for this proposed phase of the project is as follows: (1) to refine the recommendations included in the Preliminary Design Report previously developed as part of the initial phase of work; (2) provide detailed design services to produce fully independent construction documents for the green infrastructure technologies; (3) provide other related work items necessary to achieve the project goals of: mitigating Designed Sewer Relief (DSR) activations, reduce Water In Basement (WIB) occurrences, and street/yard flooding; and (4) provide storm water detention and treatment via the re-purposing of Columbus Land Redevelopment Office (Land Bank), abandoned, and vacant parcels for the implementation of Green Infrastructure (GI).  The specific work activities of this scope include development of detailed construction drawings and bidding documents, meetings with stakeholders, submission of permits, and providing responses to all contractors inquires during the bidding process.

 

1.1                     Amount of additional funds to be expended:  $1,183,791.76

 

Original Contract                     $1,599,336.26

Modification No. 1(Current)                     $1,183,791.76

CURRENT TOTAL                                                  $2,783,128.02

 

Modification No. 2 (Future)                     $   200,000.00

                     Future Total                                                              $2,983,128.02

                     

1.2 Reasons additional goods/services could not be foreseen: 

This Contract Modification No. 1 was planned and anticipated, and so stated in the original contract’s legislation.

 

1.3 Reason other procurement processes are not used:

Re-bid of the project will likely result in a higher project costs as much of the project history would be lost and required to be rediscovered by another consultant unless won by the same consultant.  In such a case, significant time would be wasted in acquiring and evaluating the new proposals without significant benefit.

 

1.4 How cost of modification was determined:

The costs of Contract Modification #1 were determined by negotiations between CDM Smith and DOSD.

 

2.   PROJECT TIMELINE: Original contract: 9/16/14 through 12/31/16. This planned contract modification is scheduled for 12/31/16 through 8/31/18 (Approximately 20 months). The future planned contract modification: 8/31/18 through 12/31/21.

 

3.                     EMERGENCY DESIGNATION: Emergency designation is not requested. This is a 30-Day request.

4.   CONTRACT COMPLIANCE NO: 04-2473650 | FBE | 11/15/2018 | Vendor #: 000180

5.   ECONOMIC / ENVIRONMENTAL IMPACT: The City has embarked upon its approved Wet-Weather Management Plan (WWMP). Currently, that plan is almost entirely comprised of a series of treatment plant capacity upgrades, storage tanks, tunnels, and other piping system augmentations; collectively known as “gray” infrastructure. After approval of the WWMP, the use of more renewable, sustainable, and environmentally friendly systems, commonly referred to as “green” infrastructure, has been recognized and implemented in many communities as a potential solution to many of the elements associated with consent order requirements. It is anticipated there will be a greater economic impact and advantages by implementing a group of smaller projects which would be conducive for competition with local suppliers and vendors as opposed to the large scale, previously devised, WWMP projects. Community and Outreach for the project will be conducted by the City, the selected consultant and the Public Outreach Consultant, RAMA Consulting, which is currently under contract for this work.

6.   FISCAL IMPACT: This legislation authorizes: the transfer within of $783,791.76 and the expenditure of $1,183,791.76 from the Sanitary Sewer General Obligation Bond Fund (G.O.), Fund 6109; and an amendment to 2016 Capital Improvements Budget

 

Title

 

To authorize the Director of Public Utilities to modify (Mod #1) an existing engineering agreement with CDM Smith, Inc. for the Blueprint Linden, Agler / Berrell Area project; to authorize the transfer of $783,791.76 within and the expenditure of up to $1,183,791.76 from the Sanitary Sewer General Obligation Bond Fund (G.O.); and to amend the 2016 Capital Improvements Budget. ($1,183,791.76)

 

Body

 

WHEREAS, it is necessary to authorize the Director of Department of Public Utilities to modify (Mod #1) an engineering agreement with CDM Smith, Inc. for the Blueprint Linden, Agler/Berrell Area project, CIP 650870-100703; and

 

WHEREAS, the original contract was authorized by Ordinance No. 1273-2014, passed by the Columbus City Council on July 21, 2014; executed by the Director on September 09, 2014; approved by the City Attorney on September 15, 2014 in the amount of $1,599,336.26; and

 

WHEREAS, it is necessary for City Council to authorize the transfer within of $783,791.76  and the expenditure of up to $1,183,791.76 from the Sanitary Sewer System GO Bond Fund, Fund 6109; and

 

WHEREAS, it is necessary to amend the 2016 Capital Improvements Budget for purposes providing sufficient budget authority for the aforementioned expenditures; and

 

WHEREAS, it has become necessary in the usual daily operation of the Division of Sewerage and Drainage, Department of Public Utilities to authorize the Director of Public Utilities to modify an existing professional engineering agreement with CDM Smith, for the Agler / Berrell Blueprint Linden Project, CIP 650870-100703, for the preservation of public health, welfare, peace, property, and safety at the earliest practical date; now, therfore

BE IT ORDAINED BY THE CITY OF COLUMBUS

SECTION 1: That the Director of Public Utilities is hereby authorized to modify (Mod #1) an engineering agreement with CDM Smith, Inc., 445 Hutchinson Avenue, Suite 820, Columbus; Ohio, 43235 for the Blueprint Linden, Agler/Berrell Area project, CIP 650870-100703 in the amount of $1,183,791.76; in accordance with the terms and conditions of the contract on file in the Office of the Division of Sewerage and Drainage

SECTION 2. That the City Auditor is authorized and directed to transfer up to $783,791.76 from the Sanitary Sewer General Obligation Bond Fund | Fund No. 6109 | Division 60-05 | per the account codes in the attachment to this ordinance.

 

Section 3. That the 2016 Capital Improvements Budget is hereby amended, in Fund 6109, Sanitary Sewer G.O. Bonds Fund as follows:

 

Fund | Project ID | Project Name | Current Authority | Change

6109 | 650800-100000 | General CA/CI | $9,918,211 | $8,414,419 | (-$783,792)

6109 | 650870-100703 | Blueprint Linden Agler/Berrell | $400,000 | $1,183,792 | (+$783,792)

 

SECTION 4. That the Director is hereby authorized to expend up to $1,183,791.76 in the following manner: Sanitary Sewer G.O. Bond Fund | Fund 6109 | Div. 60-05. (See the attached DAX financial transaction spreadsheet)

SECTION 5. That the said firm, CDM Smith, Inc. shall perform the work to the satisfaction of the Director of Public Utilities and the Administrator of the Division of Sewerage and Drainage.

SECTION 6. That the City Auditor is hereby authorized and directed to transfer any unencumbered balance in the project account to the unallocated balance within the same fund upon receipt of certification by the Director of the Department administering said project that the project has been completed and the monies no longer required for said project; except that no transfer shall be made from a project account by monies from more than one source.

SECTION 7. That the City Auditor is authorized to establish proper project accounting numbers as appropriate.

SECTION 8. That the City Auditor is authorized to make any accounting changes to revise the funding source for all contracts modifications associated with this ordinance.

SECTION 9. That this ordinance shall take effect and be in force from and after the earliest period allowed by law.