Title: To amend the 2023 Capital Improvement Budget; to authorize the Director of Public Service to enter into a contract modification with Dynotec, Inc. in connection with the Bikeway Development - Tussing Road SUP Brice Road to Hines Road project; and to authorize the expenditure of up to $90,000.00 from the Streets and Highways Bond Fund for the project; ($90,000.00)
Attachments: 1. ORD 0091-2024 accounting template
Explanation
1. BACKGROUND
This ordinance authorizes the Director of Public Service to modify a professional services contract with Dynotec, Inc. to add additional funds for design of the Bikeway Development - Tussing Road SUP Brice Road to Hines Road project.
The intent of this project is to provide the City of Columbus with the design for a new shared use path (SUP) along the south side of Tussing Road from Brice Road to Hines Road.
Ordinance 1794-2021 authorized the Director of Public Service to enter into a professional services contract with Dynotec, Inc. for the Bikeway Development - Tussing Road SUP Brice Road to Hines Road project. This ordinance authorizes the Director of Public Service to modify the contract in the amount of $90,000.00.

1.1 Amount of additional funds to be expended: $90,000.00
The original contract amount: $722,304.00 (PO284304, Ord. 1794-2021)
The total of Modification No. 1: $90,000.00 (This Ordinance)

The contract amount including all modifications: $812,304.00

1.2 Reasons additional goods/services could not be foreseen:
When Task 2 was authorized, it was identified that the project had a $50,000 shortfall in funding, so R/W Plans were moved to "If-Authorized" so the immediately necessary work could proceed. Stage 1 comments led to the need for additional work that has already been authorized including: a)SUL-A's to be performed (in the amount of approximately $20,000), and b) the addition of Water Works Plans (in the amount of approximately $20,000) for waterline relocations.

1.3 Reason other procurement processes are not used:
Dynotec is prime consultant on the Tussing Road SUP Project. The amount being requested is for the consultant and project team to perform the following services: a) R/W Plan development, b) temporary R/W staking, c) setting R/W pins after construction, d) pedestrian signal upgrades, and e) on-going services during bidding...