header-left
File #: 1562-2010    Version: 1
Type: Ordinance Status: Passed
File created: 10/22/2010 In control: Public Service & Transportation Committee
On agenda: 11/15/2010 Final action: 11/16/2010
Title: To authorize the Director of Public Service to execute a planned contract modification with DLZ, Inc., for professional engineering services required for the Joyce Avenue Phase 2 Project; to amend the 2010 C.I.B.; to authorize the transfer of funds within the Build America Bonds Fund and the Streets and Highways G.O. Bonds Fund; to authorize the expenditure of $714,982.65 from the Build America Bonds Fund and the Streets and Highways G.O. Bonds Fund for the Division of Design and Construction and; and to declare an emergency. ($714,982.65)
Attachments: 1. 1562-2010 Subconsultan information.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
11/17/20101 CITY CLERK Attest  Action details Meeting details
11/16/20101 MAYOR Signed  Action details Meeting details
11/15/20101 Columbus City Council ApprovedPass Action details Meeting details
11/15/20101 COUNCIL PRESIDENT PRO-TEM Signed  Action details Meeting details
11/11/20101 City Clerk's Office Sent back for Clarification/Correction  Action details Meeting details
11/11/20101 Service Drafter Sent to Clerk's Office for Council  Action details Meeting details
11/5/20101 CITY AUDITOR Reviewed and Approved  Action details Meeting details
11/5/20101 Service Drafter Sent for Approval  Action details Meeting details
11/5/20101 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
11/5/20101 Service Drafter Sent to Clerk's Office for Council  Action details Meeting details
11/4/20101 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
11/4/20101 Service Drafter Sent for Approval  Action details Meeting details
11/4/20101 Auditor Reviewer Reviewed and Approved  Action details Meeting details
11/3/20101 Finance Reviewer Reviewed and Approved  Action details Meeting details
11/3/20101 Finance Reviewer Reviewed and Approved  Action details Meeting details
11/3/20101 Finance Reviewer Reviewed and Approved  Action details Meeting details
10/29/20101 EBOCO Reviewer Sent for Approval  Action details Meeting details
10/29/20101 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
10/29/20101 Service Reviewer Sent for Approval  Action details Meeting details
10/27/20101 Service Reviewer Reviewed and Approved  Action details Meeting details
10/27/20101 Service Drafter Sent for Approval  Action details Meeting details
10/27/20101 SERVICE DIRECTOR Reviewed and Approved  Action details Meeting details
10/22/20101 Service Drafter Sent for Approval  Action details Meeting details
Explanation
1. BACKGROUND:
This legislation authorizes the Director of Public Service to modify and increase a professional services engineering contract with DLZ, Inc. for the Joyce Avenue Phase 2 project.

This project consists of the reconstruction of Joyce Avenue from Kenmore Avenue to Twelfth Avenue. Improvements include curb and sidewalk on Joyce Avenue, a shared use path on Joyce Avenue, ADA curb ramps, upgrades to existing traffic lights, storm sewer, street light relocation and upgrade, and roadway widening at various locations from its current two lane configuration to a three lane configuration.

Improvements on 17th Avenue, between Joyce Ave and 300 feet west of Billiter Boulevard will consist of sidewalk improvement, curb and gutter, an enclosed storm sewer, sidewalks along Seventeenth Avenue. A storm sewer system study and design for 17th Avenue between Joyce and Brentnell Avenues will also be included.

2.65 miles of 6' foot wide sidewalk will be added in this project. The sidewalk will be along the east side Joyce Avenue from Kenmore Road to Seventeenth Avenue and on the west side of Joyce Avenue to Twelfth Avenue. An 8 foot shared use path will be added along Joyce Avenue from Kenmore Road to Twelfth Avenue. The path will be on the west side of Joyce Avenue from Kenmore Road to Seventeenth Avenue and will be on the east side of Joyce Avenue from Seventeenth Avenue to Twelfth Avenue.

Additionally, a 6 foot wide sidewalk will be constructed along both sides of Seventeenth Avenue from 300 feet west of Billiter Avenue to 490' east of the Joyce Avenue, Seventeenth Avenue intersection. A 6 foot sidewalk will be constructed from 490 feet east of Joyce Avenue, Seventeenth Avenue intersection only on the south side of Seventeenth Avenue to Brentnell Avenue.

There will be 114 ADA curb ramps that will be constructed as part of this project. There are 14 bus stops and transit routes within the limits of this project. Pedestrian genera...

Click here for full text