header-left
File #: 1437-2018    Version: 1
Type: Ordinance Status: Passed
File created: 5/14/2018 In control: Public Service & Transportation Committee
On agenda: 7/9/2018 Final action: 7/12/2018
Title: To amend the 2018 Capital Improvement Budget; to authorize the Director of Public Service to enter into a contract modification with Complete General Construction Company in connection with the Bridge Rehabilitation - Annual Citywide Contract (2017) project; to authorize the expenditure of up to $214,674.00 from the Streets and Highways Bond Fund to pay for the contract modification; and to declare an emergency. ($214,674.00)
Attachments: 1. ORD 1437-2018 Accounting Template
Explanation
1. BACKGROUND
This legislation authorizes the Director of Public Service to modify and increase an existing contract with Complete General Construction Company for the Bridge Rehabilitation - Annual Citywide Contract (2017) project, and to provide payment for construction administration and inspection services.

Ordinance 3133-2017 authorized the Director of Public Service to enter into a contract with Complete General Construction Company for the construction of the Bridge Rehabilitation - Annual Citywide Contract (2017) project and to provide for construction administration and inspection services. The work for this contract consists of the routine maintenance of several bridges within the City of Columbus.

Ordinance 0683-2018 authorized the Director of Public Service to enter into a contract modification with Complete General Construction Company for the construction of the Bridge Rehabilitation - Annual Citywide Contract (2017) project and to provide for construction administration and inspection services. The work for that modification consisted of a lighting upgrade project to the Broad Street Bridge. This ordinance will add additional funding in order to complete the modification contract for the lighting upgrade project to the Broad Street Bridge.

The original contract amount: $1,450,000.00 (PO095746, Ord. 3133-2017)
The total of Modification No. 1: $200,000.00 (PO110379, Ord. 0683-2018)
The total of Modification No. 2: $180,500.00 (This Ordinance)
The contract amount including all modifications: $1,830,500.00

The amount of construction administration and inspection services for this modification will be $34,174.00. The total legislated amount for this modification and construction inspection and administration is $214,674.00.

Searches in the System for Award Management (Federal) and the Findings for ...

Click here for full text