File #: 1997-2017    Version: 1
Type: Ordinance Status: Passed
File created: 7/13/2017 In control: Public Utilities Committee
On agenda: 7/31/2017 Final action: 8/3/2017
Title: To authorize the Director of Public Utilities to enter into an agreement with Resource International, Inc., for professional engineering services for the Holton Park and Eureka Avenue Green Infrastructure Stormwater Improvements Project; for the Division of Sewerage and Drainage; to authorize a transfer within and an expenditure of up to $291,005.80 from the Storm Water Recovery Zone Super BAB Fund; to authorize an amendment to the 2017 Capital Improvements Budget; and to declare an emergency. ($291,005.80)
Attachments: 1. Ord 1997-2017 SWIF, 2. ord. 1997-2017 Directors Recommendation Letter - Post Evaluation, 3. Ord. 1997-2017 Funding Template
Explanation

1.0 BACKGROUND: This legislation authorizes the Director of Public Utilities to enter into a professional engineering services agreement with Resource International, Inc. for the Holton Park and Eureka Avenue Green Infrastructure Stormwater Improvements Project, in an amount up to $291,005.80, for the Division of Sewerage and Drainage. This agreement will provide the detailed design, specifications, contract documents, and other reports required for the construction of the Holton Park and Eureka Ave Green Infrastructure Improvements Project. The scope of work for this project is to perform all the requisite investigation, evaluation, formulation and design work to prepare construction documents for the improvement of water quantity and water quality within the project area(s) using green solutions. The City envisions the project shall focus on providing positive treatment of stormwater with Green Infrastructure (GI) prior to its discharge into storm sewers.

1.1 Project Description / Description of Work:
This project will design and construct green infrastructure on a vacant parcel along the N. Eureka Ave corridor as well as at the Holton Park site in an effort to provide the water quality treatment for CIP 611009 - Terrace/Broad Stormwater System Improvements.

The project will require coordination with all stakeholders within the region including but not limited to: Ohio EPA, City of Columbus Department of Public Service, City of Columbus Recreation and Parks Department, City of Columbus Department of Public Utilities, and Franklin County. The consultant shall coordinate and attend public information meetings as required.

1.2 Project Timeline and Modifications:
Design is planned to start in November 2017 with expected completion in November 2019.
The Construction Phase of this project is planned to start in 2020 with completion anticipated in 2022.

1.3 Estimate full cost for this project:
Original Engineering Contract ...