Explanation
BACKGROUND: This ordinance authorizes the Public Utilities Director to enter into a contract with The Erora Group for professional services for the Division of Electricity. The Division requires professional services in 2004 to secure power supply for 2006 and beyond and to support electric transmission restructuring negotiations. Procurement of professional expertise for power supply planning, technical support, risk management, rate design and overhead study services are required by the Division in order to secure the best possible power supply and subsequent rates for its electric customers.
In accordance with Section 329.14 of the Columbus City Code, 1959, notification was sent to Columbus City Council prior to initiating the selection process for the required services. A Request for Proposals (RFP), SA001210, was advertised in the City Bulletin and eleven companies (all majority-owned businesses) were sent the proposal documents. Six proposals (all majority-owned businesses) were received and opened by the Public Utilities Director on August 4, 2004.
The Erora Group received the highest ranking based upon an evaluation committee's ranking of the offers based upon the criteria specified in the RFP: qualifications of staff, current workload and availability of personnel, project approach, and past experience. Negotiations with The Erora Group determined that the cost for the scope of services will not exceed $112,500.00. The Erora Group's contract compliance number is 611339486.
Emergency action is requested due to the necessity to proceed promptly into the first phase of a new transmission structure that occurred on October 1, 2004 as a result of FERC restructuring of electricity markets.
FISCAL IMPACT: $120,000.00 was budgeted in the Division of Electricity Operating Fund for these services. There were no similar expenditures in 2002 or 2003.
Title
To authorize the Public Utilities Director to enter into a cont...
Click here for full text