File #: 1288-2007    Version: 1
Type: Ordinance Status: Passed
File created: 7/30/2007 In control: Utilities Committee
On agenda: 9/10/2007 Final action: 9/13/2007
Title: To authorize the Director of Public Utilities to enter into an agreement with McDaniel's Construction Corp Inc for the Fabrication and Installation of HDPE SDR-17 Aeration Headers for the Division of Sewerage and Drainage, Compost Facility, to authorize the expenditure of $39,580.00 from the Sewerage System Operating Fund, and to declare an emergency. ($39,580.00)
Attachments: 1. HDPE Aeration Headers (Compost)Additonal Info.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
9/13/20071 CITY CLERK Attest  Action details Meeting details
9/12/20071 MAYOR Signed  Action details Meeting details
9/10/20071 Columbus City Council ApprovedPass Action details Meeting details
9/10/20071 COUNCIL PRESIDENT Signed  Action details Meeting details
8/20/20071 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
8/20/20071 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
8/17/20071 Auditor Reviewer Reviewed and Approved  Action details Meeting details
8/17/20071 CITY AUDITOR Reviewed and Approved  Action details Meeting details
8/17/20071 Utilities Drafter Sent for Approval  Action details Meeting details
8/16/20071 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
8/16/20071 Utilities Drafter Sent for Approval  Action details Meeting details
8/8/20071 Utilities Drafter Sent for Approval  Action details Meeting details
8/8/20071 EBOCO Reviewer Sent for Approval  Action details Meeting details
8/7/20071 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
8/7/20071 Utilities Drafter Sent for Approval  Action details Meeting details
8/7/20071 Finance Reviewer Reviewed and Approved  Action details Meeting details
8/7/20071 Finance Reviewer Reviewed and Approved  Action details Meeting details
8/7/20071 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
8/2/20071 Utilities Reviewer Sent for Approval  Action details Meeting details
7/31/20071 Utilities Reviewer Reviewed and Approved  Action details Meeting details
7/30/20071 Utilities Drafter Sent for Approval  Action details Meeting details
Explanation

The purpose of this legislation is to authorize the Director of Public Utilities to enter into an agreement with McDaniel's Construction Corp Inc. to provide fabrication and installation of HDPE SDR-17 Aeration Headers for the Division of Sewerage and Drainage, Compost Facility

The Compost Facility utilizes the headers to supply air to compost and control temperatures to meet EPA requirements. The Director of Public Utilities opened formal bids on July 11, 2007, three (3) bids were received. A tabulation of the bids follows:

McDaniel's Construction: $39,580.00
Mid Ohio Pipeline: $40,490.00
American Environmental Group $55,000.00

Supplier: McDaniel's Construction Corp Inc (31-1145406 Expires 5-29-09 AFA

Fiscal Impact: $39,580.00 is budgeted and needed for this service

Emergency legislation is being requested so that work may begin and be completed before winter and to meet current EPA requirements.


Title

To authorize the Director of Public Utilities to enter into an agreement with McDaniel's Construction Corp Inc for the Fabrication and Installation of HDPE SDR-17 Aeration Headers for the Division of Sewerage and Drainage, Compost Facility, to authorize the expenditure of $39,580.00 from the Sewerage System Operating Fund, and to declare an emergency. ($39,580.00)

Body

WHEREAS, The Compost Facility utilizes the headers to supply air to compost and control temperatures to meet EPA requirements

WHEREAS, The Director of Public Utilities opened formal bids on July 11, 2007, three (3) bids were received, and

WHEREAS, the award of the contract went to the lowest, responsive and responsible bidder, McDaniel's Construction Corp Inc. and

WHEREAS, an emergency exists in the usual daily operation of the Department of Public Utilities, in that it is immediately necessary to enter into contract for the Fabrication and Installation of HDPE SDR-17 Aeration Headers so that work may begin and be completed before winter ...