Explanation
1. BACKGROUND:
This legislation authorizes the Director of Public Utilities to enter into a professional engineering services contract with Camp, Dresser and McKee, Inc. for purposes of undertaking an update to the Division of Sewerage and Drainage's computerized hydraulic model of its sanitary and combined sewer system, in connection with the Sewer System Capacity Model Project.
This contract will continue the development and enhancement of the City's Sewer System capacity Model (SSCM). The SSCM is the culmination of the City's long-term commitment (beginning with the "Olentangy Scioto Interceptor Sewer Tributary Study - Phase I Report" and ending with the "Columbus Sewer Capacity Study - Phase III" report and model; which was updated in the method and extent by the Model Update 2000 project (MU 2000) to accurately evaluate collection system capacity deficiencies and devising economical solutions to those deficiencies.
This contract will provide the professional engineering and technical services required to update the SSCM from year 2000 to 2006 conditions. The model update is necessary to ensure continued conformance with the existing consent orders between the City of Columbus and the State of Ohio; ongoing efforts to eliminate sanitary sewer overflows; minimize Water-in-Basement (WIB) occurrences; evaluate future development/expansion of served areas and evaluate collection system capital improvements projects included in the City's Wet Weather Management Plan (WWMP), submitted to the Ohio EPA on July 1, 2005.
2. PROCUREMENT INFORMATION:
The basis for selection of the chosen professional engineering services firm: The Division advertised Request for Proposals (RFP's) for the subject services in the City Bulletin in accordance with the provisions of Section 329.14 of Columbus City Codes. The Division of Sewerage and Drainage received technical proposals on June 5, 2006 from the Camp, Dresser and McKee, Inc.; and Metcalf and Eddy of...
Click here for full text