File #: 2874-2025    Version: 1
Type: Ordinance Status: Consent
File created: 10/20/2025 In control: Finance & Governance Committee
On agenda: 11/24/2025 Final action:
Title: To authorize the Director of Finance and Management, on behalf of the Office of Construction Management, to modify and increase the professional architectural / engineering services agreement with Abbot Studios Architects, for the Department of Public Service’s Marion Road Outpost Replacement project; to authorize a transfer of $268,393.71 within the Street Construction Maintenance & Repair Operating Fund; to authorize an expenditure up to $350,519.75 within the Street Construction Maintenance & Repair Operating Fund; and to declare an emergency. ($350,519.75)
Attachments: 1. ORD 2874-2025 Secy of State, 2. ORD 2874-2025 Funding
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.
Explanation

1. BACKGROUND: This legislation authorizes the Director of Finance and Management, on behalf of the Office of Construction Management, to modify and increase the professional architectural / engineering services agreement, with Abbot Studios Architects, for the Department of Public Service’s Marion Road Outpost Replacement project, in an amount up to $350,519.75.

The original contract provided design services for the demolition and design of a new facility at the Marion Road Outpost.

Modification No. 1 (current) is needed to update drawings that were held for two years due to lack of funding.

2. MODIFICATION INFO:

A. The amt of additional funds to be expended under the modification: $350,519.75

Original Contract Amount: $720,951.25 (PO306486/PO498518)
Modification No. 1 (current): $350,519.75
Total (Original and Mod 1): $1,070,951.25

B. Why the need for additional goods or services could not be foreseen at the time the contract was initially awarded.
Funding for construction was unavailable and the project was put on hold for approximately two years. Funding is now available and the preconstruction phase needs to be restarted.

C. Why it would not be in the city’s best interests to have the additional contract requirements awarded through other procurement processes?
There is no need to use another procurement process as the City already awarded the design contract to Abbot Studios Architects. Their drawings need updated for site compliance review and approval by the Building and Zoning Department.

D. How the price for the additional goods or services which are subject of the modification was determined.
The contractor submitted a fee proposal and was accepted by the Dept. of Finance & Management, Office of Construction Management as well as the Department of Public Service.

3. CONTRACT COMPLIANCE INFO: Abbot Studios Architects, Vendor No. 004796, expires 10/17/27, Majority-designated

Searches in the Excluded Party List System (F...