File #: 2566-2024    Version: 1
Type: Ordinance Status: First Reading
File created: 9/13/2024 In control: Public Utilities & Sustainability Committee
On agenda: 10/21/2024 Final action:
Title: To authorize the Director of Public Utilities to modify and increase a professional engineering services contract with CDM Smith, Inc., for the Southerly Plant Wide Control System Improvements project; to appropriate funds in the Sanitary Revolving Loan Fund; and to authorize an expenditure of up to $3,894,000.00 from the Sanitary Revolving Loan Fund to pay for the contract modification. ($3,894,000.00)
Indexes: MBE Participation, WBE Participation
Attachments: 1. ORD 2566-2024 Utilization, 2. ORD 2566-2024 Accounting Template
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.
Explanation
1. BACKGROUND
This Ordinance authorizes the Director of Public Utilities to execute a planned contract modification to increase funding for the professional engineering services contract with CDM Smith, Inc., for the Southerly Plant Wide Control System Improvements project, CIP #650378-100001, in an amount up to $3,894,000.00.

The Division of Sewerage and Drainage completed an evaluation of programmable logic controllers and monitoring equipment at both the Jackson Pike and Southerly Waste Water Treatment Plants (WWTP) between March 2019 and May 2021. The evaluation identified control systems and components that are no longer supported by the original manufacturer and repair parts are difficult to acquire.

An RFP was formally advertised on the Vendor Services and Bonfire websites from 11/7/22 through 12/2/22 to select a company to design replacements for the antiquated control and monitoring systems and equipment identified throughout the Southerly WWTP. Funding was provided to analyze alternatives and perform preliminary engineering for the replacements. This phase has been completed.

The second phase (this modification) of the contract will perform detailed design engineering and develop biddable plans based on the decisions made in the first phase of the contract.

The Community Planning Area for this project is 99-Citywide

1.1 Future Modifications: The future anticipated needs below are for engineering services during construction. The purchase of equipment and construction will be funded through a separate contract and are not included below.

1.2 Amount of additional funds to be expended: $3,894,000.00.

Cost summary:
Original Contract, Preliminary Design $ 917,700.00 (ORD 0637-2023; PO379679)
Modification 1 (current) $ 3,894,000.00
Modification 2 (future) $ 4,000,000.00

Estimated Contract Total $ 8,811,700.00

1.3. Reason other procurement processes are not used: This contract was awarded ...

Click here for full text