header-left
File #: 1833-2003    Version: 1
Type: Ordinance Status: Passed
File created: 7/9/2003 In control: Utilities Committee
On agenda: 9/22/2003 Final action: 9/24/2003
Title: To authorize the Director of Public Utilities to modify the professional engineering services contract with URS Corporation for the Big Walnut Augmentation/Rickenbacker Interceptor Sewer Project; to authorize the appropriation, transfer and expenditure of $2,887,224.00 from the Sewer System Reserve Fund to the Ohio Water Pollution Control Loan Fund; for the Division of Sewerage and Drainage, and to declare an emergency. ($2,887,224.00)
Attachments: 1. 491_1.tif, 2. 491_2.tif
Date Ver.Action ByActionResultAction DetailsMeeting Details
9/24/20031 CITY CLERK Attest  Action details Meeting details
9/23/20031 MAYOR Signed  Action details Meeting details
9/22/20031 Columbus City Council ApprovedPass Action details Meeting details
9/22/20031 COUNCIL PRESIDENT Signed  Action details Meeting details
9/15/20031 Columbus City Council Tabled to Certain DatePass Action details Meeting details
8/27/20031 Finance Reviewer Reviewed and Approved  Action details Meeting details
8/27/20031 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
8/21/20031 Utilities Drafter Sent for Approval  Action details Meeting details
8/6/20031 City Clerk's Office Sent back for Clarification/Correction  Action details Meeting details
7/30/20031 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
7/18/20031 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
7/17/20031 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
7/17/20031 Utilities Drafter Sent for Approval  Action details Meeting details
7/17/20031 Auditor Reviewer Contingent Within  Action details Meeting details
7/17/20031 CITY AUDITOR Reviewed and Approved  Action details Meeting details
7/17/20031 Auditor Reviewer Reviewed and Approved  Action details Meeting details
7/17/20031 Utilities Drafter Sent for Approval  Action details Meeting details
7/17/20031 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
7/16/20031 Utilities Drafter Sent for Approval  Action details Meeting details
7/16/20031 EBOCO Reviewer Reviewed and Approved  Action details Meeting details
7/16/20031 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
7/16/20031 Utilities Drafter Sent for Approval  Action details Meeting details
7/16/20031 Finance Reviewer Reviewed and Approved  Action details Meeting details
7/16/20031 Finance Reviewer Reviewed and Approved  Action details Meeting details
7/14/20031 Utilities Drafter Sent for Approval  Action details Meeting details
7/11/20031 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
7/11/20031 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
7/11/20031 Utilities Drafter Sent for Approval  Action details Meeting details
7/10/20031 Utilities Drafter Sent for Approval  Action details Meeting details
7/10/20031 Utilities Reviewer Reviewed and Approved  Action details Meeting details
Explanation
1. BACKGROUND:
This legislation authorizes modifying the professional engineering services contract with URS Corporation in connection with the Big Walnut Augmentation/Rickenbacker Interceptor Sewer Project.

This professional services contract was originally procured with a scope that included a multi-year renewable contract option for an entire scope of services. This provision allows the City to appropriate funds annually or on an as-needed basis depending upon the project's progress. This modification will fund services through May 31, 2004, and includes the balance of Part 2 design services, construction contract procurement, and the first five months of construction services on Part 1 of the Project.

This project will construct in two parts. Part 1 will install a 168-inch diameter sanitary interceptor sewer from the Southerly Wastewater Treatment Plant to the Alum Creek Drive/State Route 317 intersection, including the Shook Road and Rickenbacker Port Authority trunk sewers. Part 2 will construct a 144-inch diameter sanitary interceptor sewer from Alum Creek Drive/State Route 317 intersection north along Alum Creek Drive to the existing 108-inch Outfall Sewer.

2. PROFESSIONAL ENGINEERING SERVICES MOD. AWARD: This contract is a multi-year contract that allows the City to appropriate funds on an as-need basis to cover the costs of services for a 12-18 month period, and it is necessary to fulfill the schedule and funding commitments for this project. This work is a planned, continuation of the services as originally included within the existing contract's scope of service. The contract total, including this modification is $12,606,721.00. It is also projected that modifications will be required in fiscal years 2004 and 2005 based upon current project schedules. These services are of a highly specialized and technical nature, and it is not practical or economical to have these services performed by city personnel. The costs hav...

Click here for full text