File #: 0980-2021    Version: 1
Type: Ordinance Status: Tabled Indefinitely
File created: 4/13/2021 In control: Public Utilities Committee
On agenda: 5/24/2021 Final action:
Title: To authorize the Director of Public Utilities to modify and increase the 2020 - 2022 Construction Administration and Inspection Services agreement with H. R. Gray & Associates, Inc. for the Real Time Control - Alum Creek Storm Tanks Project; for the Division of Sewerage & Drainage; to authorize a transfer and expenditure up to $242,319.25 within the Sanitary General Obligations Bond Fund; and to amend the 2020 Capital Improvements Budget. ($242,319.25)
Attachments: 1. ORD 0980-2021 Information, 2. ORD 0980-2021 Utilization, 3. ORD 0980-2021 Funding
Explanation

1.0 BACKGROUND: This legislation authorizes the Director of Public Utilities to execute a planned modification to the 2020 - 2022 Construction Administration and Inspection Services agreement with H. R. Gray & Associates Inc. for the following Division of Sewerage & Drainage Project:

Real Time Control - Alum Creek Storm Tanks, CIP No. 650009-100001, Planning Area = 57 - Mid East, $242,319.25

1.1. Amount of additional funds to be expended: $242,319.25
Original Agreement Amount: $ 167,845.34 PO228237, PO228238, & PO228239
Modification No. 1 $ 979,361.67 PO235282
Modification No. 2 $ 711,543.64 PO238195 & PO238199
Modification No. 3 $ 255,437.69 PO248167
Modification No. 4 $1,523,581.11 PO265076
Modification No. 5 (current) $ 242,319.25
Grand Total $3,880,088.70

1.2. Reasons additional goods/services could not be foreseen:
This is a three-year agreement for fiscal years 2020 - 2022 and modifications were anticipated and explained in the original legislation under Ordinance No. 0787-2020.

1.3. Reason other procurement processes are not used:
This is a multiyear contract that will be modified as required to provide construction administration/inspection services for construction projects that bid during the three year (2020-2022) timeframe.

1.4. How cost of modification was determined:
The cost was determined by negotiations between H.R. Gray & Associates and the Division of Sewerage & Drainage.

2.0 ECONOMIC IMPACT/ADVANTAGES; COMMUNITY OUTREACH; PROJECT DEVELOPMENT; ENVIRONMENTAL FACTORS/ADVANTAGES OF PROJECT: Division of Sewerage & Drainage projects include rehabilitation of existing sewers, repair to existing sewers, construction of new sewers, and construction of green infrastructure. The majority of the projects will reduce inflow and infiltration to the City’s sanitary sewer system thus mitigating sanitary sewer overflows to basements and waterways. Other projects provide improvement to existing storm infrastructure to ...