Explanation
The purpose of this legislation is to authorize the Director of Finance and Management to enter into contract with Capp Inc. for the purchase of Asco Gas Shut-off Valves for the Division of Sewerage and Drainage, Jackson Pike Wastewater Treatment Plant.
The Jackson Pike Wastewater Treatment Plant has a need for twenty-seven (27) gas shut-off valves that will be used on the incinerators for digested gas supply to the burners. The Purchasing Office opened formal bids on September 17, 2009. Thirty-eight (38) bids were solicited, 2 MBE, 1 FBE. Eight (8) bids were received. A bid tabulation is attached.
The Division of Sewerage and Drainage made a recommendation to the lowest, responsive and responsible bidder Capp Inc for all items in the total amount of $26,890.65
SUPPLIER: Capp Inc (23-1412101) Expires 8-5-11
FISCAL IMPACT: $26,890.65 is budgeted and needed for this purchase.
The company is not debarred according to the Excluded Party Listing System of the Federal Government or prohibited from being awarded a contract according to the Auditor of State Unresolved Findings for Recovery Certified Search.
Title
To authorize the Director of Finance and Management to establish a purchase order with Capp Inc for the purchase of Asco Gas Shut-Off Valves for the Division of Sewerage and Drainage, and to authorize the expenditure of $26,890.65 from the Sewerage System Operating Fund. ($26,890.65)
Body
WHEREAS, the Jackson Pike Wastewater Treatment Plant has a need for twenty-seven (27) gas shut-off valves that will be used on the incinerators for digested gas supply to the burners, and
WHEREAS, the Purchasing Office opened formal bids on September 17, 2009. Thirty-eight (38) bids were solicited, 2 MBE, 1 FBE. Eight (8) bids were received. A bid tabulation is attached, and
WHEREAS, The Division of Sewerage and Drainage made a recommendation to the lowest, responsive and responsible bidder Capp Inc for all items in ...
Click here for full text