Explanation
This ordinance authorizes the Director of Public Utilities to modify a contract with TZT Manufacturing and Contracting Inc for the Jackson Pike Wastewater Treatment Plant Sludge Control Building HVAC Replacement. The HVAC system in the Sludge Control Building has been repaired over a period of three (3) years and needs to be replaced. Bids were opened on November 12, 2003 and three (3) bids were received. The tabulation below:
TZT Manufacturing and Contracting $96,000.00
Pete Miller Inc $168,168.00
Bruner Corporation $288,782.00
It has come necessary to modify the contract for additional work that was not foreseen. This work includes duct work, reconnection of alarm system as required by City inspectors.
SUPPLIER: TZT Manufacturing and Contracting Inc (31-1292609)
FISCAL IMPACT: $15,188.00 is required for this modification and is within the 2004 budget.
Emergency legislation is being requested so that the HVAC system is operational before the winter months.
Title
To authorize the Director of Public Utilities to modify a contract with TZT Manufacturing and Contracting Inc for the Sludge Building HVAC Replacement for the Division of Sewerage and Drainage, to authorize the expenditure of $15,188.00 from the Sewerage System Operating Fund and to declare an emergency. ($15,188.00)
Body
WHEREAS, the Jackson Pike Wastewater Treatment Plant Sludge Building has a need to have the HVAC system replaced, and
WHEREAS, the Director of Public Utilities opened bids on November 12, 2003, and
WHEREAS, TZT Manufacturing and Contracting Inc was the lowest, responsive and responsible bidder , and
WHEREAS, it has become necessary to modify the contract for additional work which includes duct work, reconnection of alarm system as required by City inspectors, and
WHEREAS, an emergency exists in the usual daily operation of the Department of Public Utilities, Division of Sewerage and Drainage in that it is immediately n...
Click here for full text