header-left
File #: 1428-2017    Version: 1
Type: Ordinance Status: Passed
File created: 5/22/2017 In control: Public Utilities Committee
On agenda: 7/31/2017 Final action: 8/3/2017
Title: To authorize the Director of Public Utilities to enter into a planned modification of the Electric Power Systems Maintenance Services contract with Roberts Service Group, Inc. for the Department of Public Utilities, to authorize the expenditure of $300,000.00 from the Sewerage System Operating Fund, and $500,000.00 from the Electricity Operating Fund. ($800,000.00)
Attachments: 1. ORD 1428-2017 Financial Coding - Electric Power Sys Maint Serv - Mod #5, 2. ORD 1428-2017 Electric Power Systems Maint - Mod #5 - Addt'l Info, 3. ORD 1428-2017 Electric Power Systems Maint Svc Mod #5 - Subcontractor Work ID Form
Explanation

The purpose of this legislation is to authorize the Director of Public Utilities to enter into a planned modification of the contract with Roberts Service Group, Inc. for Electric Power Systems Maintenance Services for the various Department of Public Utilities facilities.

The Department of Public Utilities has identified various electric power equipment that requires Electric Power Systems Maintenance Services for the Division of Sewerage and Drainage, the Division of Power, and the Division of Water. The Department of Public Utilities operates and manages two (2) Wastewater Treatment Plants, a Compost Facility, a Sewer Maintenance Operations Center, sewage and storm water collection systems, three (3) Water Treatment Plants, a water distribution system and various electric substations that service the City of Columbus and its satellite communities. This modification Number 5 is for services for the Division of Sewerage and Drainage and the Division of Power facilities. Additional Department of Public Utilities facilities may be added in the future. All facilities are located within Franklin and Delaware Counties.

The work to be performed under these specifications will be electric power distribution systems and its components that require studies to be performed, inspection, testing, maintenance, repair and/or replacement with the majority of the work to be on industrial equipment/systems ranging from 120V to 15.5 kV. There may also be inspection, testing, studies performed, maintenance, repair and/or replacement work on > 15.5kV to 138kV equipment/systems that will require a Contractor or Subcontractor to have highly specialized experience in the area of high voltage.

The Department of Public Utilities advertised Request for Proposals for the subject services in the City Bulletin in accordance with the relevant provisions of Chapter 329 of City Code. Six hundred thirty-one (631) vendors (15 MBR, 36 M1A, 2 HL1, 16 F1, 6 AS1, 556 MAJ) wer...

Click here for full text