File #: 1653-2003    Version: 1
Type: Ordinance Status: Passed
File created: 6/18/2003 In control: Utilities Committee
On agenda: 7/7/2003 Final action: 7/7/2003
Title: To authorize the Director of Public Utilities to enter into an agreement with Malcolm Pirnie, Inc., for professional engineering services for the Wastewater Treatment Facilities Upgrade, General Program--Overall Engineering Consultant (OEC) Services, for the Division of Sewerage and Drainage; to amend the 2002 Capital Improvements Budget; to appropriate and authorize the transfer of funds from the Sewerage System Reserve Fund to the 1991 Sanitary Bond Fund; to authorize the expenditure of $3,825,000.00 from the 1991 Sanitary Bond Fund; and to declare an emergency. ($3,825,000.00)
Date Ver.Action ByActionResultAction DetailsMeeting Details
7/8/20031 MAYOR Signed  Action details Meeting details
7/8/20031 CITY CLERK Attest  Action details Meeting details
7/7/20031 Columbus City Council ApprovedPass Action details Meeting details
7/7/20031 COUNCIL PRESIDENT Signed  Action details Meeting details
6/27/20031 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
6/26/20031 CITY AUDITOR Reviewed and Approved  Action details Meeting details
6/26/20031 Utilities Drafter Sent for Approval  Action details Meeting details
6/26/20031 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
6/25/20031 Auditor Reviewer Contingent Within  Action details Meeting details
6/24/20031 Utilities Drafter Sent for Approval  Action details Meeting details
6/24/20031 Finance Reviewer Reviewed and Approved  Action details Meeting details
6/24/20031 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
6/24/20031 Utilities Drafter Sent for Approval  Action details Meeting details
6/23/20031 EBOCO Reviewer Reviewed and Approved  Action details Meeting details
6/23/20031 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
6/20/20031 Utilities Drafter Sent for Approval  Action details Meeting details
6/19/20031 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
6/18/20031 Utilities Drafter Sent for Approval  Action details Meeting details
6/18/20031 Utilities Reviewer Reviewed and Approved  Action details Meeting details
6/18/20031 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
Explanation

BACKGROUND

Need: This legislation authorizes the Director of Public Utilities to enter into an agreement with Malcolm Pirnie, Inc., for professional engineering services for the Wastewater Treatment Facilities Upgrade, General Program--Overall Engineering Consultant (OEC) Services, Project 650360, for the Division of Sewerage and Drainage. It amends the 2002 Capital Improvements Budget. It also appropriates and transfers funds from the Sewerage System Reserve Fund to the 1991 Sanitary Bond Fund.

Procurement Information: This procurement was conducted in accordance with the Request For Statement of Qualifications (RFSQ) process set forth in Section 329.13, Columbus City Codes, 1959. The process was conducted as follows:

1. Written notice of need was made to City Council on February 13, 2002.

2. The RFSQ was published in the "City Bulletin" on February 23 and March 2, 2002.

3. All Offerors were required to obtain an Offeror's Information packet by March 15, 2002.

4. Statements of Qualifications (SOQs) were received on April 8, 2002 from four firms; no MBE or FBE firms submitted an SOQ.

5. The Division's Evaluation Committee recommended three firms for further consideration. On June 3, 2002 the firms were notified in writing of this action and were requested to submit a technical proposal. The three firms were:

BBS Corporation/Brown and Caldwell
Camp Dresser & McKee
Malcolm Pirnie, Inc.

6. Proposals from the three firms were received on July 12, 2002.

7. The evaluation and final ranking of the firms were based upon the quality and feasibility of the proposals.

8. On July 26, 2002 the Evaluation Committee reported its recommendation for selection to the Director. All three firms were notified in writing of the final selection.

9. Subsequent discussions and negotiations with the selected firm have resulted in further refinement of the scope of the work and results in this ordi...

Click here for full text