File #: 0959-2009    Version: 1
Type: Ordinance Status: Passed
File created: 6/26/2009 In control: Utilities Committee
On agenda: 7/13/2009 Final action: 7/14/2009
Title: To authorize the Director of Public Utilities to modify and increase the construction contract with Complete General Construction Company due to unforeseen conditions found during construction on the West 5th Avenue Underpass Stormwater System Improvements Project, for the Division of Sewerage and Drainage; to authorize the transfer of $72,783.00 within the Storm Sewer Bond Fund; to amend the 2009 Capital Improvements Budget to authorize the expenditure of $72,783.00 within the Storm Sewer Bonds Fund.; and to declare an emergency. ($72,783.00)
Attachments: 1. ORD0959-2009 MAP.pdf, 2. CIP 610846 Director's Legislation Information Sheet CM No. 2.pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details
7/14/20091 MAYOR Signed  Action details Meeting details
7/14/20091 CITY CLERK Attest  Action details Meeting details
7/13/20091 Columbus City Council ApprovedPass Action details Meeting details
7/13/20091 COUNCIL PRESIDENT Signed  Action details Meeting details
7/2/20091 CITY ATTORNEY Reviewed and Approved  Action details Meeting details
7/2/20091 Utilities Drafter Sent to Clerk's Office for Council  Action details Meeting details
7/1/20091 Utilities Drafter Sent for Approval  Action details Meeting details
7/1/20091 EBOCO Reviewer Sent for Approval  Action details Meeting details
7/1/20091 ODI DIRECTOR Reviewed and Approved  Action details Meeting details
7/1/20091 Utilities Drafter Sent for Approval  Action details Meeting details
7/1/20091 Auditor Reviewer Reviewed and Approved  Action details Meeting details
7/1/20091 CITY AUDITOR Reviewed and Approved  Action details Meeting details
7/1/20091 Utilities Drafter Sent for Approval  Action details Meeting details
6/30/20091 UTILITIES DIRECTOR Reviewed and Approved  Action details Meeting details
6/30/20091 Utilities Drafter Sent for Approval  Action details Meeting details
6/30/20091 Finance Reviewer Reviewed and Approved  Action details Meeting details
6/30/20091 Finance Reviewer Sent for Approval  Action details Meeting details
6/30/20091 FINANCE DIRECTOR Reviewed and Approved  Action details Meeting details
6/29/20091 Utilities Reviewer Reviewed and Approved  Action details Meeting details
6/29/20091 Utilities Drafter Sent for Approval  Action details Meeting details
6/29/20091 Utilities Reviewer Reviewed and Approved  Action details Meeting details
6/29/20091 Utilities Reviewer Reviewed and Approved  Action details Meeting details
6/26/20091 Utilities Drafter Sent for Approval  Action details Meeting details
Explanation

BACKGROUND: This Ordinance authorizes the Director of Public Utilities to modify and increase the construction contract with Complete General Construction Company for the West 5th Avenue Underpass Stormwater System Improvements Project, for the Division of Sewerage and Drainage. This modification is required due as a result of insufficient original force account to compensate the Contractor for the work performed at the City's request which were outside the original contract scope. Such work was necessitated by changed site conditions unknown at the time of the project bidding. This will be the final contract modification to close out this contract.

The contract modification consists of relocation of the concrete box necessitated by a conflict with an AT&T ductbank, ex. 42" water line which had to be depressurized while maintaining services (not originally planned), additional derrick stones placed at the outlet to Olentangy River, and miscellaneous traffic signal work at the Olentangy River Road and Fifth Ave. intersection which had to be implemented to better respond to traffic patterns.

1. Amount of additional funds to be expended: $72,783.00
Original Contract Amount: $1,281,254.04
Modification No. 01: $90,000.00
Amount of original contract, Mod. No. 01 and this modification: $1,444,037.04

2. Reasons additional goods/services could not be foreseen:
Unknown site conditions included relocation of the concrete box necessitated by a conflict with an AT&T ductbank, ex. 42" water line which had to be depressurized while maintaining services (not originally planned), additional derrick stones placed at the outlet to Olentangy River, and miscellaneous traffic signal work at the Olentangy River Road and Fifth Ave. intersection which had to be implemented to better respond to traffic patterns.

3. Reason other procurement processes are not used:
The out of scope work was performed during the course of the original cont...

Click here for full text