Explanation
Background: This legislation authorizes the Public Service Director to enter into a contract for the Transportation Division in the amount of $673,457.53 for the Resurfacing and Curb Ramps 2003, UIRF, and to pay construction inspection costs up to $101,025.00. This improvement includes resurfacing, curb ramps, curbs, and other associated work in various locations within the Urban Infrastructure Recovery Fund (UIRF) boundaries. The Notice to Proceed is estimated for July 23, 2003. Project completion is estimated at 90 days. This project was advertised by the Transportation Division in the Columbus City Bulletin, Dodge Reports and Builders Exchange. Fourteen contractors (13 majority, 1 minority) were solicited and five bids (4 majority, 1 minority) were received and tabulated on May 29, 2003 as follows:
Gaddis and Son, Inc.*/
Decker Construction Company, A Joint Venture $673,457.53
McDaniel's Construction Corp., Inc.* $696,318.15
Miller Pavement Maintenance, Inc. $699,566.40
Columbus Asphalt Paving Inc. $722,436.90
Shelly and Sands, Inc. $739,665.11
* - minority contractor
Evaluation of the qualtity contractor criteria confirms the low bidder and therefore award is to be made to Gaddis and Son, Inc./Decker Constructi...
Click here for full text